Presub notes Hertz Building
City of Yelm
Community Development Department
105 Yelm Avenue West
Yelm, WA 98597
Pre-Application Meeting
May 25, 2011
These comments are preliminary in nature and are not intended to represent final comments and or requirements for the City of Yelm. Until a complete application is made, the Community
Development Department can only attempt to inform the applicant of general requirements as they appear in the form presented by the applicant at the time of pre-submission.
Proponent: Ed Roque
Project Proposal: Convert Existing retail building into a Liquor Store
Project Location: 512 Yelm Avenue East (tax parcel number 22719340500)
Zoning and Setbacks
The property is zoned Commercial (C-1) which is codified at Chapter 17.26 YMC. The purpose of the Commercial zone is to provide for the location of business centers to serve the needs
of the community for convenience goods and services.
The C-1 zone allows Liquor stores, provided such uses not be permitted to locate within “500 feet of the exterior boundary property line of any public school grounds measured along the
most direct route over or across established public walks, streets or other public passageway to the nearest public entrance of the premises provided for license”.
Yelm Community Schools has a special education student facility at 401 Yelm Ave East, which would be considered a public school ground. The School District has preliminarily indicated
that it has no objection to the location of the liquor store at the proposed location. Prior to occupancy, however, the applicant would need to obtain approval of the location from
the Washington State Liquor Control Board and from Yelm Community Schools.
Critical Areas
All of Yelm is considered a critical aquifer recharge area. The City critical area maps indicate that the property is located outside of wetlands, flood zones, landslide hazard areas,
and high ground water areas.
Land Use Approval
The proposed use is allowed in the C-1 zoning district and, provided there is no expansion of the existing building, no land use permit approval is required. Prior to occupancy, however,
the site must be brought into conformance with current development regulations as described in these notes.
Fees
Civil Plan Review Billed on a cost recovery basis
Traffic Impact Fee $1,321.00 per peak PM trip
Building Plan Review Based on 1997 UBC fee Schedule
Building Permit Based on 1997 UBC fee Schedule
Sewer Connection Fee $6,219 per ERU or $3,179 if part of LID
Sewer Inspection Fee $145.00 per ERU
Water Connection Fee $5,217.00 per ERU
Water Meter Fee Based on meter size
Landscaping
The purpose of landscaping requirements is to preserve the aesthetic character of communities; to promote retention and protection of existing vegetation; and to reduce the impacts of
development on drainage systems and natural habitats.
Existing landscaping does not meet current requirements, but is adequate for a change of use. The existing landscaping must be maintained and, if an irrigation system is present and
utilized, an irrigation meter will be required to be installed along with an appropriate backflow prevention device. An irrigation budget will be established based on the amount of
area landscaped and the Washington Irrigation Guide. The City monitors and limits irrigation usage to the established budget.
Design Considerations
A trash enclosure that fully screens required garbage and recycling bins is required if not present currently. Refuse areas must be screened with an enclosure of a material and design
compatible with the overall architectural theme. A six foot wall or fence shall enclose any outdoor refuse collection point. The fence shall be a solid material such as wood or masonry.
Chain link fencing is not allowed in the Mixed Use Design Guideline District. Prior to occupancy of the building, all chain link fencing must be removed. Solid wood fencing is an appropriate
component of landscaping within the Mixed Use district.
Parking
The requirements for off-street parking and their design shall be regarded as the minimum; however, the owner, developer, or operator of the premises for which the parking facilities
are intended shall be responsible for providing adequate amounts and arrangement of space for the particular premises even though such space is in excess of the minimum set forth.
Parking shall be located off street.
Chapter 17.72 YMC requires retail uses to provide a minimum of one parking stall for every 250 square feet of gross floor area. Based on a building size of 8,300 square feet, 33 parking
spaces would be required. There are currently less than 15 improved parking spaces on the site.
All parking areas must be surfaced with asphalt or concrete, and shall be striped and landscaped to the standards of the development guidelines.
The design details for parking lot construction can be found in the Yelm Development Guidelines.
Prior to occupancy, a parking plan showing the required number of improved spaces will be required.
Transportation
The existing ingress and egress at the site is consistent with the Yelm Development Guidelines and should be maintained.
The City of Yelm has adopted a Transportation Facility Charge (TFC) of $1,321.00 per PM peak trip generated by new development. The code provides a default table that the applicant can
use to determine the number of new PM trips generated by a proposal.
The TFC charges are based on the type of use proposed. The proposed use does not generate more traffic than the previous use so, unless the building is expanded, no TFC is due.
Water
The site is currently connected to the City of Yelm water system. There is an existing 6” asphaltic concrete water line located near the middle of the property which will need to
be protected during any construction. No structures may be located within 15 feet of this water line.
If the proposed use will use more than one equivilant residential unit (ERU) of water, which currently equates to 875 cubic feet a month, additional water connection fees will be levied
at a rate of $5,217.00 per connection (fee subject to change). An estimate for water usage will be required as part of the building permit review process. Water connection fees are
payable at building permit issuance. It is not anticipated, however, that the proposed use will require additional water connections.
If there is an irrigation system currently operating, an irrigation meter will be required be installed with an approved backflow prevention device.
The property is currently not protected for potential cross-connection contamination as required by Section 246-290-490 WAC. Prior to occupancy of the building, an approved backflow
prevention device will be required to be installed and tested by the applicant and approved by the City of Yelm.
Sewer
The proposed site is currently connected to the City of Yelm’s STEP sewer system and is served by a 1,000 gallong STEP Tank adequate to provide service for a retail store. Any change
of use or expansion would require a re-evaluation of the STEP tank size.
Stormwater
The existing stormwater system must be maintained to accommodate stormwater runoff from existing impervious surfaces on the property. If additional paved parking is provided, or the
impervious area is changed in any way, a stormwater report prepared by a licensed engineer will be required.
Fire Protection
All projects need to have fire protection for the buildings. The International Building Code (IBC) provides occupancy ratings for different types of uses. The fire coverage and sprinkler
system for the proposed use must meet IBC requirements.
ADA Requirements
Sites, buildings, structures, facilities, elements and spaces, temporary or permanent, shall be accessible to persons with physical disabilities. The Site Plan Review Committee will
review all improvements for accessibility and compliance with relevant sections of Chapter 11 of the International Building Code.
Civil Plan Review
If additional paved parking is constructed, Civil Plans prepared by a licensed engineer will be required. The Yelm Development Guidelines contain standard details for all infrastructure
requirements, including parking lot layout, sewer and water lines, STEP tank design, and stormwater control.
Building Permit Process
Building Plan review, permitting and inspections will be based on Title 15 Yelm Municipal Code, adopting the International Codes, Uniform Plumbing Code and Washington State Energy Code.
By resolution, the City of Yelm re-adopted the 1997 UBC, UMC and UPC Fee schedules. Additions, alterations, repairs and change of occupancy will be based on Chapter 34 of the International
Building Code or the International Existing Building Code. New and existing buildings will be reviewed for life/ safety, seismic design, accessibility and energy code requirements.
Some, but not all factors reviewed will be:
1. Interior alterations and improvements will be reviewed under chapter 34 of the International Building Code or the International Existing Building Code.
2. New front wall will be reviewed under the IBC and shall meet the requirements of chapter 16 of the IBC for seismic and lateral forces. Any loads applied to the existing building
by the new wall shall also meet the requirements of Chapter 16 of the IBC.
3. New HVAC shall meet the requirements of the International Mechanical Code.
4. All new construction shall meet the 2009 Washington Energy Code. Alterations where practical shall meet the 2009 WEC
5. Electrical alterations will be permitted and reviewed by Labor and Industries
6. Condensation from coolers and ice machines shall be air gapped for cross connection control
Building Plans showing conformance to the above requirements and any other items deemed necessary may be submitted after Site Plan Review approval. Five (5) sets of plans, one of which
may be half scale, two (2) sets of engineering calculations, energy calculations and specifications will be required. An integrated sprinkler and fire alarm system may be required.
These plans may be submitted at a later date along with any required kitchen suppression systems. All fire related items 5’ outside the building will be subject to civil review along
with domestic water, waste, and storm water.
Concurrently with Site Plan Review two sets of building and accessory building elevations must be submitted for review of the building for consistency with the Design Guidelines.
Allow at least 8 to 12 weeks for Building Plan Review and 2 weeks for design guideline review.