412 Yelm Ave Jekel (2)
City of Yelm
Community Development Department
105 Yelm Avenue West
Yelm, WA 98597
Pre-Application Meeting
May 9, 2012
These comments are preliminary in nature and are not intended to represent final comments and or
requirements for the City of Yelm. Until a complete application is made, the Community Development
Department can only attempt to inform the applicant of general requirements as they appear in the form
presented by the applicant at the time of pre-submission.
Proponent: Dave and Kari Jekel
Project Proposal: Convert Existing retail building into a Produce Market
Project Location: 412 Yelm Avenue East (tax parcel number 22719340500)
Zoning and Setbacks
The property is zoned Commercial (C-1) which is codified at Chapter 17.26 YMC. The
purpose of the Commercial zone is to provide for the location of business centers to
serve the needs of the community for convenience goods and services.
Land Use Approval
The proposed use is allowed in the C-1 zoning district and, provided there is no
expansion of the existing building, no land use permit approval is required. Prior to
occupancy, however, the site must be brought into conformance with current
development regulations as described in these notes.
Fees
Civil Plan Review Billed on a cost recovery basis
Building Plan Review Based on 1997 UBC fee Schedule
Building Permit Based on 1997 UBC fee Schedule
Critical Areas
All of Yelm is considered a critical aquifer recharge area. The City critical area maps
indicate that the property is located outside of wetlands, flood zones, landslide hazard
areas, and high ground water areas.
Pre-Application Meeting
Page 2 of 6
Landscaping
The purpose of landscaping requirements is to preserve the aesthetic character of
communities; to promote retention and protection of existing vegetation; and to reduce
the impacts of development on drainage systems and natural habitats.
Existing landscaping does not meet current requirements, but is adequate for a change
of use. The existing landscaping must be maintained and, if an irrigation system is
present and utilized, an irrigation meter will be required to be installed along with an
appropriate backflow prevention device. An irrigation budget will be established based
on the amount of area landscaped and the Washington Irrigation Guide. The City
monitors and limits irrigation usage to the established budget.
Design Considerations
A trash enclosure that fully screens required garbage and recycling bins is required if
not present currently. Refuse areas must be screened with an enclosure of a material
and design compatible with the overall architectural theme. A six foot wall or fence shall
enclose any outdoor refuse collection point. The fence shall be a solid material such as
wood or masonry.
Chain link fencing is not allowed in the Mixed Use Design Guideline District. Prior to
occupancy of the building, all chain link fencing must be removed. Solid wood fencing
or other ornate fencing is an appropriate component of landscaping within the Mixed
Use district.
Storage
Section 17.57.060 states “In the conduct of any business, the storage of merchandise,
raw materials, equipment, fixtures, scraps or solid wastes shall comply with the
following requirements:
A. Every reasonable effort shall be made by persons operating a business to store
all such materials within an enclosed building, with the following exceptions:
1. Where such inside storage is not practical or desirable for reasons related to
health, fire or safety codes;
2. Where the outside storage of merchandise, manufactured products or raw
materials is normal and standard practice, such as in the sale of automotive
equipment, mobile homes, lumber, gardening materials, nursery stock and
the like, or on the site on construction projects;
Pre-Application Meeting
Page 3 of 6
3. When materials or products are temporarily stored outside incidental to
shipping, delivery, loading or unloading thereof.
B. Outside storage shall be maintained in an orderly manner consistent with good
housekeeping practices and shall be:
1. Effectively fenced and screened from all residential areas and public rights-of-
way (an eight-foot solid fence is presumed to effectively screen outside
storage, not all outside storage requires an eight-foot solid fence);
2. Consistent with fire, safety, health and sanitary codes and industry practices.
Outdoor display of produce is not considered normal and standard practice as defined
above. On this site, the outdoor display of produce could occur under the covered eve
that extends out into the parking area, but cannot be located within required parking
areas, pedestrian pathways, or on the unimproved gravel area.
You have the option of applying for outdoor retail display through the Site Plan Review
process. This process requires the entire site to be brought into current code
standards, including, but not limited to additional paved parking and associated
stormwater treatment and disposal, updated landscaping, and road frontage
improvements.
Parking
The requirements for off-street parking and their design shall be regarded as the
minimum; however, the owner, developer, or operator of the premises for which the
parking facilities are intended shall be responsible for providing adequate amounts and
arrangement of space for the particular premises even though such space is in excess
of the minimum set forth. Parking shall be located off street.
Chapter 17.72 YMC requires retail uses to provide a minimum of one parking stall for
every 250 square feet of gross floor area. Based on a building size of 8,300 square
feet, 33 parking spaces would be required. There are currently less than 15 improved
parking spaces on the site.
All parking areas must be surfaced with asphalt or concrete, and shall be striped and
landscaped to the standards of the development guidelines.
The design details for parking lot construction can be found in the Yelm Development
Guidelines.
Prior to occupancy, a parking plan showing the required number of improved spaces will
be required.
Pre-Application Meeting
Page 4 of 6
Transportation
The existing ingress and egress at the site is consistent with the Yelm Development
Guidelines and should be maintained.
The City of Yelm has adopted a Transportation Facility Charge (TFC) of $1,321.00 per
PM peak trip generated by new development. The code provides a default table that the
applicant can use to determine the number of new PM trips generated by a proposal.
The TFC charges are based on the type of use proposed. The proposed use does not
generate more traffic than the previous use so, unless the building is expanded, no TFC
is due.
Water
The site is currently connected to the City of Yelm water system. There is an existing 6”
asphaltic concrete water line located near the middle of the property which will need to
be protected during any construction. No structures may be located within 15 feet of
this water line.
If there is an irrigation system currently operating, an irrigation meter will be required be
installed with an approved backflow prevention device.
The property is currently not protected for potential cross-connection contamination as
required by Section 246-290-490 WAC. Prior to occupancy of the building, an approved
backflow prevention device will be required to be installed and tested by the applicant
and approved by the City of Yelm.
Sewer
The proposed site is currently connected to the City of Yelm’s STEP sewer system and
is served by a 1,000 gallon STEP Tank adequate to provide service for a retail store.
Any change of use or expansion would require a re-evaluation of the STEP tank size.
Stormwater
The existing stormwater system must be maintained to accommodate stormwater runoff
from existing impervious surfaces on the property. If additional paved parking is
provided, or the impervious area is changed in any way, a stormwater report prepared
by a licensed engineer will be required.
Pre-Application Meeting
Page 5 of 6
Civil Plan Review
If additional paved parking is constructed, Civil Plans prepared by a licensed engineer
will be required. The Yelm Development Guidelines contain standard details for all
infrastructure requirements, including parking lot layout, sewer and water lines, STEP
tank design, and stormwater control.
Fire Protection
All projects need to have fire protection for the buildings. The International Building
Code (IBC) provides occupancy ratings for different types of uses. The fire coverage
and sprinkler system for the proposed use must meet IBC requirements.
ADA Requirements
Sites, buildings, structures, facilities, elements and spaces, temporary or permanent,
shall be accessible to persons with physical disabilities. The Site Plan Review
Committee will review all improvements for accessibility and compliance with relevant
sections of Chapter 11 of the International Building Code.
Building Permit Process
Building Plan review, permitting and inspections will be based on Title 15 Yelm
Municipal Code, adopting the International Codes, Uniform Plumbing Code and
Washington State Energy Code. By resolution, the City of Yelm re-adopted the 1997
UBC, UMC and UPC Fee schedules. Additions, alterations, repairs and change of
occupancy will be based on Chapter 34 of the International Building Code or the
International Existing Building Code. New and existing buildings will be reviewed for life/
safety, seismic design, accessibility and energy code requirements. Some, but not all
factors reviewed will be:
1. Interior alterations and improvements will be reviewed under chapter 34 of the
International Building Code or the International Existing Building Code.
2. New or revised plumbing and HVAC shall meet the requirements of the Uniform
Plumbing Code and International Mechanical Code.
3. All new construction shall meet the 2009 Washington Energy Code. Alterations
where practical shall meet the 2009 WEC
4. A minimum of two exits separated by code minimum shall be maintained. Both
exists must be accessible and open during hours of operation. Emergency
lighting shall illuminate access to the exits.
5. Electrical alterations will be permitted and reviewed by Labor and Industries
Pre-Application Meeting
Page 6 of 6
6. Condensation from coolers and ice machines shall be air gapped for cross
connection control
Building Plans showing conformance to the above requirements and any other items
deemed necessary may be submitted after Site Plan Review approval. Five(5) sets of
plans, one of which may be half scale, two (2) sets of engineering calculations, energy
calculations and specifications will be required. An integrated sprinkler and fire alarm
system may be required. These plans may be submitted at a later date along with any
required kitchen suppression systems. All fire related items 5’ outside the building will
be subject to civil review along with domestic water, waste, and storm water.
Concurrently with Site Plan Review two sets of building and accessory building
elevations must be submitted for review of the building for consistency with the Design
Guidelines.
Allow at least 8 to 12 weeks for Building Plan Review and 2 weeks for design guideline
review.