1ST ST SW PROJECT - Schedule 2016-12-30 - LFTaskBegins OnDuration (Cal. Days)Ends On1Authorization to ProceedCompleted2Send out Utility Map Requests/ Call for LocatesCompleted3Topographical Survey (Window)Completed4Prepare 30% Concept PlanCompleted5Draft SEPA for CityCompleted6Send 30% Plan to City/Parks Master Plan ArchitectCompleted7City reviews 30% Concept Plan (incorporate Park Master Plan/Architect)Completed8QA/QC Concept 30% with CityCompleted9Send 30% Plans to WSDOT For ReviewCompleted10Prepare 60% PS&ECurrent11Prepare 60% Plans and SpecificationsCompleted12Send 60% to City / WSDOT for reviewCompleted13ROW Acquisition / Easement Acquisition December 30, 2016 60 February 28, 201714WSDOT Reviews 60%December 30, 2016 7 January 6, 201715City Reviews 60%December 30, 2016 14 January 13, 201716QA/QC (60%) meeting with City January 13, 2017 1 January 13, 201717Prepare 90% PS&EJanuary 13, 2017 10 January 23, 201718Submit 90% Plans to City January 23, 2017 1 January 23, 201719City Review of 90%January 23, 2017 7 January 30, 201720WSDOT Review of 90%January 23, 2017 14 February 6, 201721Prepare Final January 30, 2017 22 February 21, 201722Submit Final to CityFebruary 21, 2017 7 February 28, 201723TIB Approval to AdvertiseFebruary 21, 2017 7 February 28, 201724Advertise ProjectFebruary 28, 2017 14 March 14, 201725Open BidsMarch 14, 2017 1 March 14, 201726Council awards projectMarch 14, 2017 14 March 28, 201727Contracts are signed by Contractor & City March 28, 2017 14 April 11, 201728Notice to Proceed & Preconstruction Meeting April 11, 2017 10 April 21, 2017City of Yelm1st Street Sidewalk ProjectG&O Project # 16490Project Schedule - Updated: 12/30/2016