202 RailroadPre-Submission Notes
March 11, 2020
Michele Geyer wishes to convert an existing retail building located at 202 Railroad Avenue, from a lawn mower repair facility to a personal services establishment (Pilates Studio). (parcel
75301800300). The property is zoned Central Business District (C-1).
Process
The approval process from initial concept to final occupancy consists of three steps: land use review, civil plan review, and building life/safety review.
Land Use
The building is existing and previous use has been a lawn mower retail and repair facility. Converting the space to a personal services establishment is a change of use, and is subject
to the Ministerial Site Plan Review process. Review typically takes between 2 -4 weeks to receive approval. The decision may be appealed to the City's Hearing Examiner.
Civil Plan Review
Civil plans are required for the construction of driveways, parking areas, stormwater treatment and public infrastructure. Civil plans must be prepared by an engineer licensed in the
State of Washington.
Building Life/Safety
Yelm has adopted the International Building Codes and reviews building plans for life/safety and consistency per these codes, as adopted by Washington State. Electrical permits and
inspections are through the Washington State Department of Labor and Industries.
Consistency with Development Standards
Potable Water
Water connections are based on a consumption rate of 875 cubic feet a month. Based on the description of improvements, it is anticipated that the conversion would not require an additional
water connections. If you choose to add showers, food service or other types of business in addition to the Pilates studio space, it may require additional water connections.
All commercial buildings and irrigation systems are required to provide for cross-connection control through the provisions of a back flow prevention device (reduced pressure backflow
assembly) installed on the water services. A list of approved devices can be found at Chapter 246-290-490 WAC. The backflow device is required to be installed after the meter and
tested by a certified backflow tester.
Waste Water
S.T.E.P. tank sizing is governed by the Criteria for Sewage Works Design (Orange Book) published by the Washington State Department of Ecology
There is a 1,000 gallon STEP tank serving this building. It would be expected that this tank is adequately sized to serve the proposed use, unless additional water usage is expected.
Food preparation requires a grease interceptor to be installed. There are options for grease interceptor size and location, based on the size of the use. The grease interceptor must
be designed by a licensed engineer and reviewed by the City. If additional water connections are required, additional sewer connections will also be required.
Storm Water
Stormwater must be collected, treated, and infiltrated on the project site. The engineer preparing the civil plans will determine the required level of treatment and will prepare a storm
water plan to the City for review as part of the civil plan review process. The City has adopted the most recent version of the Washington State Department of Ecology Storm Water Manual.
Environmental
The project is exempt from SEPA pursuant to Section 18.20.020 YMC.
Transportation
Railroad Avenue is considered a local access commercial street which consists of an 11 foot traffic lane, a 7 foot parking lane, a 6 foot planter strip, and a 5 foot sidewalk. Railroad
Avenue is not
improved to City standards. Under certain circumstances the City may defer frontage improvements when the installation of improvements could be more safely, efficiently and effectively
implemented if done concurrently with other improvements along the same frontage. An agreement of deferral must be signed and recorded.
Parking
Places of assembly require one stall for each 10 occupants, based on the maximum occupant load per the international building code. On-site parking does not meet current development
standards. City development regulations require all parking areas to be surfaced with asphalt, concrete or similar surface. Ingress and egress at the site shall be consistent with
the Yelm Development Guidelines, Section 4B.140. Currently, the entire property frontage is open access. The creation of parking area and perimeter landscape will identify the driveway
location(s).
Site Design
The Unified Development Code includes standards for parking lot design and landscaping, requires adequately sized service areas. Features required include screening of outdoor storage
and service areas, landscaping including an internal perimeter landscape, and landscape requirements for above ground stormwater facilities. Refuse areas are to be enclosed and landscaped.
Perimeter and parking lot landscaping is required. Above ground stormwater facilities also require landscape. Trash enclosures are required to be screened and landscaped. Mailboxes
shall be cluster box units and be located on site. All buildings and site improvements must meet current Americans with Disabilities Act (ADA) requirements. Building elevations, site
utility screens and refuse pad wall showing compliance with City of Yelm Design Guidelines shall be submitted with the site plan review application.
Fees & Charges
Land Use Review
Ministerial Site Plan Review $250
Civil Plan Review
City Staff Review $250
Consultant Review Actual Cost
Building Permit Review
Sewer SDC (per ERU) $6,394
Water SDC (per ERU) $6,725
Traffic Impact Fee (per new Peak PM Trip) $1,497
Fire Impact Fee (per square foot of building) 0.36