WRF Presub Notes
The City of Yelm is an equal opportunity employer and provider
PRE-SUBMISSION NOTES
MAY 21, 2021
The City of Yelm proposes to upgrade the existing Yelm Water Reclamation Facility located at
931 Northern Pacific Road SW Parcel 64300900400. The proposed upgrades include an addition
to the current solids handling building and converting 2 of the 3 SBR basins to anoxic and
aeration tanks. New construction in the development include a generator set, transformer,
chemical building, headworks building, mechanical/electrical building, valve vault, and pump
stations.
PROCESS
The approval process from initial concept to final occupancy consists of three steps: land use
review, civil plan review, and building life/safety review.
LAND USE
As the proposal, as submitted, is an allowed use in the Industrial zoning district, the project
would be approved through the administrative site plan review process. An environmental
checklist will be needed.
The administrative site plan review process allows notification of the application to surrounding
property owners, but does not trigger a public hearing. A complete application will be routed
to the City Public Works Department, Thurston County, and other state agencies (including the
Department of Transportation) for comment.
After the review process, City staff will issue a threshold determination that the project will
have no significant impact to the environment and begin to craft the approval. A typical
approval includes conditions designed to ensure the proposal is consistent with the
development standards of the City. The project can only be denied if it will have significant
environmental impacts or is inconsistent with City, County, or State development regulations.
The administrative site plan review process typically takes between 8 to 12 weeks. The decision
may be appealed to the City's Hearing Examiner.
CIVIL PLAN REVIEW
Civil plans are required for the construction of driveways, parking areas, stormwater treatment
and public infrastructure. Civil plans must be provided to show compliance with the most
Page 2 of 4
current Stormwater Management Manual for Western Washington. See City of Yelm Civil Plan
Review Checklist for requirements.
BUILDING LIFE/SAFETY
Yelm has adopted the International Building Codes and reviews building plans for life/safety
and consistency per these codes, as adopted by Washington State. Electrical permits and
inspections are through the Washington State Department of Labor and Industries. Buildings
must be compliant with the City of Yelm development standards.
ENVIRONMENTAL
Based on the impacts of the development, the project as proposed requires a SEPA checklist
and environmental review.
Maps indicate the property contains soils more preferred as habitat for the Mazama Pocket
Gopher, a protected species listed on the Washington Priority Species and Habitat List as well as
the Federal Threatened Species List. Preliminary reconnaissance of pocket gopher activity is
required. If there is evidence of pocket gopher activity on the property, a critical areas report
would then be required before the permit is processed. If a critical areas report is required, it
must be prepared by a qualified professional.
Compliance with Yelm’s requirements under the Critical Areas Code does not ensure
compliance with the provisions of the Endangered Species Act, and a federal permit may be
required if pocket gophers are found on the property. This permit would be issued through the
US Fish and Wildlife Service (360.753.5823).
All of Yelm is considered a critical aquifer recharge area. Protection measures for development
within a critical aquifer recharge area are met through treating and disposing of stormwater
through an approved stormwater system.
While the site of the WRF is not in a flood zone, Flood Insurance Rate Maps (FIRM) published by
the Federal Emergency Management Agency (FEMA) indicate that a portion of the proposed
construction access is within the 100 year floodplain of Yelm Creek.
Recent documentation of best available science from FEMA indicate that the flood zone in this
area should be removed from the FIRM. The City anticipates that approval of construction in
the area shown on the FIRM would be allowed based on FEMA current findings.
TRANSPORTATION
Ingress and egress at the site shall be consistent with the Yelm Development Guidelines,
Section 2.10.100. Vehicular access into the site will need to be reviewed. The project will
require a commercial access per the Yelm Development Guidelines.
The main access to the facility is currently off of Northern Pacific Road NW. During
construction, the construction access road is proposed to go from Rhoton Rd SE through
adjoining Parcel 64300800304 to the site.
Page 3 of 4
Frontage improvements are required for all new development within the city. Northern Pacific
Road NW is not constructed to City standards. A signed agreement for deferral of frontage
improvements will be required as a condition of approval.
PARKING
Parking is required for City staff during the maintenance and operation of the facility.
Section 18.54.030 YMC requires industrial uses to provide one space per employee based on
the greatest number of employees on a single shift, plus one square foot parking per square
foot of display, and one space for each vehicle owned or operated by the company.
If existing parking does not meet the above regulations, additional parking is required.
SITE DESIGN
Building setbacks are 15 feet from the rear, front and side yards. The maximum building height
is forty (40) feet.
Existing landscaping meets the minimum requirements of Chapter 18.55 YMC. If any
landscaping is disturbed, it will need to be replaced.
Service areas and outdoor storage shall be located away from neighboring properties and
located behind the building. No refuse container shall be permitted between a street and the
front of a building.
Outdoor storage shall be maintained in an orderly manner consistent with good housekeeping
practices and shall be effectively fenced and screened from all residential areas and public
rights of way.
The proposal includes a power generator. Appropriate screening should be installed, and noise
levels must meet Chapter 173-60 WAC.
POTABLE WATER
The property is located in the City of Yelm’s water service area, and is currently connected to
City water service.
WASTE WATER
The property is located in the City of Yelm’s STEP sewer system service area, and is connected
to the City of Yelm’s STEP sewer system.
STORM WATER
Stormwater must be collected, treated, and infiltrated on the project site. The engineer
preparing the civil plans will determine the required level of treatment and will prepare a storm
water plan for the City to review as part of the civil plan review process. The City has adopted
the most recent version (2019) of the Washington State Department of Ecology Storm Water
Manual (SWMMWW).
Page 4 of 4
BUILDING
The building use will be reviewed for life/ safety, seismic design, accessibility and energy code
requirements for its particular use.
The site must provide Fire Department vehicle access. Access lane widths are determined by
building size and height. This includes driveway radius at Northern Pacific Road NW and
internally.
FEES & CHARGES
Fire Impact Fee (per new square foot) 0.36
These notes are based solely on the site plan and description submitted May, 2021. They are meant to map out
the process for approval and to point out any potential conflicts with City standards and are NOT meant to fully
review the proposal.