Loading...
JW301 Final Drainage Report v2 Wentworth Commercial Site Final Stormwater Control Plan Date Prepared 12/22/22 Subject Property 313 Yelm Ave W Yelm WA, 98597 TP #: 75300900100 Applicant Jennifer Wentworth wentworthje@gmail.com Reviewing Agency City of Yelm Community Development 106 2nd St SE Yelm, WA 98597 Project Engineer Nicholas D. Taylor, PE The Iris Group PLLC (360) 890-8955 ntaylor@irisgroupconsulting.com "I hereby certify that this Stormwater Control Plan has been prepared by me or under my supervision and meets minimum standards of The City of Yelm and normal standards of engineering practice. I hereby acknowledge and agree that the jurisdiction does not and will not assume liability for the sufficiency, suitability, or performance of drainage facilities designed by me." 12/22/22 Stormwater Control Plan 2 of 6 Wentworth Commercial Site Table of Contents Section 1 – Proposed Project Description ..................................................................................................................... 3 Minimum Requirements ............................................................................................................................................ 3 MR #1 – Preparation of Drainage Control Plans .................................................................................................... 3 MR #2 – Construction Stormwater Pollution Prevention (SWPP) ......................................................................... 3 MR #3 – Source Control of Pollution ..................................................................................................................... 3 MR #4 – Preservation of Natural Drainage Systems and Outfalls ......................................................................... 3 MR #5 – Onsite Stormwater Management ............................................................................................................ 3 MR #6 – Runoff Treatment .................................................................................................................................... 3 MR #7 – Flow Control ............................................................................................................................................ 3 MR #8 – Wetlands Protection ................................................................................................................................ 4 MR #9 – Operation and Maintenance ................................................................................................................... 4 Section 2 – Existing Conditions ...................................................................................................................................... 4 Section 3 – Soils Investigation ....................................................................................................................................... 4 Section 4 – Wells and Septic Systems ............................................................................................................................ 4 Section 5 – Fuel Tanks ................................................................................................................................................... 4 Section 6 – Subbasin Description .................................................................................................................................. 4 Section 7 – Floodplain Analysis ...................................................................................................................................... 4 Section 8 – Aesthetic Considerations for Facilities ........................................................................................................ 4 Section 9 – Facility Selection and Sizing ........................................................................................................................ 5 Section 10 – Conveyance System Analysis .................................................................................................................... 5 Section 11 – Offsite Analysis & Mitigation .................................................................................................................... 5 Section 12 – Utilities ...................................................................................................................................................... 5 Section 13 – Covenants, Dedications, Easements, Agreements .................................................................................... 6 Section 14 – Other Permits or Conditions Placed on the Project .................................................................................. 6 Appendices A. SMMWW Figures B. Site Improvement Plans C. WWHM Modeling Report D. Soils Report E. Bay Filter Design Specifications F. Construction Stormwater Pollution Prevention Plan (SWPPP) G. Facility Maintenance Requirements Stormwater Control Plan 3 of 6 Wentworth Commercial Site Section 1 – Proposed Project Description This Stormwater Control Plan (SCP) is associated with a civil permit application for approval to construct improvements on a 0.28-acre commercial site with service-oriented use within the City of Yelm. City zoning of the project site is Central Business District (CBD) in which the proposed use is a permitted use. This project proposes to add additional parking to the existing site and on Rice St. All onsite sidewalk, driveway, and lawn runoff will sheet flow to a proposed catch basin near the western corner of the proposed parking lot where it will be captured and conveyed to a proposed single-cartridge Bayfilter catch basin for treatment before being discharged to a proposed infiltration gallery. Roof runoff from the existing buildings will be captured and conveyed directly to the proposed infiltration gallery. Runoff from Rice St will be collected in proposed curb/gutter and catch basins then conveyed to the onsite Bayfilter catch basin for treatment before being discharged to the proposed onsite infiltration gallery. This SCP was prepared in accordance with the 2019 Stormwater Management Manual for Western Washington (SMMWW). Discussion of how the project will meet all applicable Minimum Requirements is provided below. Minimum Requirements Per SMMWW Volume 1, figure I-3.1, of which an annotated version is provided as Appendix A to this report, Minimum Requirements 1-5 apply to the new and replaced hard surfaces, as well as converted vegetation areas. MR #1 – Preparation of Drainage Control Plans Preparation of this SCP meets the intent of Minimum Requirement #1. MR #2 – Construction Stormwater Pollution Prevention (SWPP) A Construction SWPPP is included as Appendix E to this report. As there is currently no anticipated discharge from the site, it is anticipated that the project will not be required to obtain coverage under the Washington State Construction Stormwater General Permit. MR #3 – Source Control of Pollution A Pollution Source Control Program (PSCP) is not required. MR #4 – Preservation of Natural Drainage Systems and Outfalls In the existing condition there is no outfall at which concentrated flow enters or leaves the site. There is little to no offsite run-on to the development area. MR #5 – Onsite Stormwater Management Per SMMWW Volume 1, figure I-3.3, of which an annotated version is provided as Appendix A to this report, this project has chosen to meet the LID Performance standard through use of an infiltration gallery. MR #6 – Runoff Treatment Runoff treatment will be provided by a Bayfilter catch basin, sized per Section 9 below. The proposed filter unit has Ecology general use approval for basic treatment at 0.060 cfs flow rate for the single-cartridge 522 unit. MR #7 – Flow Control Flow control is categorically not required, as the project proposes less than 10,000 SF of new hard surface, it proposes to convert less then ¾ of an acre from forested to lawn, and the increase in the 100 year flow rate is negative, as all runoff will be infiltrated on the site. Stormwater Control Plan 4 of 6 Wentworth Commercial Site MR #8 – Wetlands Protection As this project does not discharge into a wetland, Minimum Requirement #8 is not applicable to this project. MR #9 – Operation and Maintenance Maintenance of the infiltration system shall be performed in accordance with SWMM Table V-A.1, V-A.2, and V-A.5, included in Attachment G (Facility Maintenance Requirements). Basins The entire limits of disturbance is modeled as a single basin. Section 2 – Existing Conditions The site is generally rectangular in shape, with all onsite surfaces sloping down toward the western corner of the site. Two building structures exist on the site, with paved parking space for 1 or 2 vehicles. The total topographic relief across the site is on the order of 2’ feet and is depicted on the Site Improvement Plans included as Appendix B). Vegetation across the site generally consists of deciduous and coniferous trees and lawn. No areas of surficial erosion, standing water, seeps, springs, or deep-seated slope movement were observed during site reconnaissance or questioning of the owner. Section 3 – Soils Investigation The USDA Natural Resource Conservation Service (NRCS) Web Soil Survey maps the site as being underlain by Spanaway gravelly sandy loam, 0 to 3 percent slopes (hydrologic soils group A). The project Geotechnical Engineer has indicated that a design infiltration rate of 6.0 in/hr should be used for designing the proposed infiltration facility. A soils report is included as Appendix D to this report. Section 4 – Wells and Septic Systems There are no known wells or septic systems onsite. Section 5 – Fuel Tanks There is no indication of existing above or below grade fuel tanks on the property. Section 6 – Subbasin Description There is no significant off-site drainage tributary to the project. Section 7 – Floodplain Analysis FEMA does not list the site as being within a flood zone. Section 8 – Aesthetic Considerations for Facilities The proposed facilities will be below grade and not visible. Stormwater Control Plan 5 of 6 Wentworth Commercial Site Section 9 – Facility Selection and Sizing The proposed Bayfilter catch basin is sized to meet the Western Washington Hydrology Model (WWHM) online treatment flow rate. The proposed filter unit has Ecology general use approval for basic treatment at 0.060 cfs flow rate for the single-cartridge unit. Per WWHM, the required online treatment flow rate is 0.0390 cfs. See Appendix E for Bayfilter design specifications. The proposed infiltration gallery will consist of Stormtech SC740 chambers and was sized using WWHM and a 6.0 in/hr infiltration rate for the basin areas listed in Table 1 below. The gallery was modeled as a gravel trench bed with 4’ total depth and a gravel void ratio of 40%, with 65% total voids where chambers are installed. For the proposed 15.75’ x 50.23’ infiltration facility, the required detention volume is 0.040 ac-ft, and the proposed detention volume is 0.0404 ac-ft. 100% of the inflow hydrograph is infiltrated, categorically meeting the LID performance standard. Basins Tabulation of basin areas is included in Table 1 below. There is one proposed basin. Area (SF) Disturbed Area 15,459 Existing Hard Surface 8,539 New Plus Replaced Hard Surface 5,505 Hard Surface After Project 9,721 Lawn and Landscape After Project 5,738 New + Replaced Pollution Generating Hard Surface 8,233 Proposed Effective Hard Surface 0 Table 1 – Surface Coverage Basin coverage types and areas used for WWHM modeling are included in Table 2 below. Area (SF) A/B Lawn/Landscaping (PGPS) 5,738 Roads/Driveways (PGPS) 9,721 Roof (NPGS) 1,488 Table 2 – Modeling Basins Section 10 – Conveyance System Analysis Subgrade conveyance for the emergency overflow drainage system will consist of SDR35 PVC pipe sized to convey the 100-year event flow. Section 11 – Offsite Analysis & Mitigation This section is not applicable as stormwater will not be discharged to an offsite conveyance. Section 12 – Utilities All proposed utilities will be installed in accordance with applicable code and required separation shall be provided. There are no anticipated utility conflicts with the proposed stormwater system. Stormwater Control Plan 6 of 6 Wentworth Commercial Site Section 13 – Covenants, Dedications, Easements, Agreements There are no proposed onsite facilities that would require covenants, dedications, easements, or agreements. Section 14 – Other Permits or Conditions Placed on the Project Civil permits will be required for the project. There are currently no known conditions of approval. Appendix A Appendix B FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM COVER SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC119123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 VICINITY MAPNTSSITE DATAPARCEL #:75300900100SITE ADDRESS: 313 YELM AVE WYELM, WA 98597GROSS ACREAGE: 0.28 AC (PER COUNTY DATA)ZONING:CBDPROPOSED USE: SERVICE ORIENTEDPRESIDING JURISDICTION:YELM, WASITE1.IT IS THE CONTRACTOR’S RESPONSIBILITY TO COMPLETE ALL WORKAND TO DISPOSE OF ALL DEMOLITION DEBRIS IN ACCORDANCE WITH ALLFEDERAL, STATE, AND LOCAL REGULATIONS. PRIOR TO ANY WORKCONTRACTOR SHALL COMPLETE ALL TESTING FOR HAZARDOUSMATERIALS AND SHALL ABATE ALL HAZARDOUS MATERIALS INACCORDANCE WITH ALL FEDERAL, STATE, AND LOCAL REGULATIONS.2. CONTRACTOR SHALL OBTAIN AND FULFILL THE REQUIREMENTS OF ANYPERMITS REQUIRED FOR ANY PROPOSED DEMOLITION ACTIVITY.3. CONTRACTOR SHALL COORDINATE WITH AND RECEIVE APPROVAL FROMANY PUBLIC OR PRIVATE UTILITIES AS REQUIRED FOR ABANDONMENTOF UTILITY SERVICES. CONTRACTOR SHALL APPLY FOR ANDCOORDINATE ANY WORK THAT MUST BE COMPLETED BY THE UTILITYPURVEYOR. CONTRACTOR SHALL ENSURE THAT ALL UTILITIES TO BEMODIFIED OR REMOVED ARE SHUT OFF PRIOR TO DEMOLITION ORCONSTRUCTION ACTIVITY.4. PRIOR TO ANY DEMOLITION OR REMOVAL/MODIFICATION OF EXISTINGUNDERGROUND UTILITY SERVICES, CONTRACTOR SHALL PERFORMBOTH A PRIVATE AND PUBLIC UTILITY LOCATE TO IDENTIFY THEHORIZONTAL AND VERTICAL LOCATIONS OF ALL EXISTINGUNDERGROUND UTILITIES.5. CONTRACTOR IS RESPONSIBLE FOR PROTECTION AND PRESERVATIONOF ANY EXISTING FEATURES TO REMAIN.6. CONTRACTOR IS RESPONSIBLE FOR DEMOLITION AND DISPOSAL OF ALLEXISTING FEATURES THAT CONFLICT WITH PROPOSED FEATURES.7. APPROVAL OF THIS SWPPP DOES NOT CONSTITUTE AN APPROVAL OFPERMANENT ROAD OR DRAINAGE DESIGN (E.G., SIZE AND LOCATION OFROADS, PIPES, RESTRICTORS, CHANNELS, RETENTION FACILITIES,UTILITIES, ETC.)8. THE IMPLEMENTATION OF THIS SWPPP AND THE CONSTRUCTION,MAINTENANCE, REPLACEMENT, AND UPGRADING OF THESE ESCFACILITIES IS THE RESPONSIBILITY OF THE APPLICANT/CONTRACTORUNTIL ALL CONSTRUCTION IS COMPLETED AND APPROVED ANDVEGETATION/LANDSCAPING IS ESTABLISHED.9. DURING THE CONSTRUCTION PERIOD, NO UNAUTHORIZED DISTURBANCEBEYOND THE PROPERTY BOUNDARY SHALL BE PERMITTED.10.THE ESC FACILITIES SHOWN ON THIS PLAN MUST BE CONSTRUCTED INCONJUNCTION WITH ALL CLEARING AND GRADING ACTIVITIES, AND INSUCH A MANNER AS TO INSURE THAT SEDIMENT AND SEDIMENT LADENWATER DO NOT ENTER THE DRAINAGE SYSTEM, ROADWAYS, ORVIOLATE APPLICABLE WATER STANDARDS.11.THE ESC FACILITIES SHOWN ON THIS PLAN ARE THE MINIMUMREQUIREMENTS FOR ANTICIPATED SITE CONDITIONS. DURING THECONSTRUCTION PERIOD, THESE ESC FACILITIES SHALL BE UPGRADEDAS NEEDED FOR UNEXPECTED STORM EVENTS AND TO ENSURE THATSEDIMENT AND SEDIMENT-LADEN WATER DO NOT LEAVE THE SITE.12.THE ESC FACILITIES SHALL BE INSPECTED DAILY BY THEAPPLICANT/CONTRACTOR AND MAINTAINED AS NECESSARY TO ENSURETHEIR CONTINUED FUNCTIONING.13.THE ESC FACILITIES ON INACTIVE SITES SHALL BE INSPECTED ANDMAINTAINED A MINIMUM OF ONCE A MONTH OR WITHIN THE 48 HOURSFOLLOWING A MAJOR STORM EVENT.14.AT NO TIME SHALL MORE THAN 1 FOOT OF SEDIMENT BE ALLOWED TOACCUMULATE WITHIN A TRAPPED CATCH BASIN. ALL CATCH BASINS ANDCONVEYANCE LINES SHALL BE CLEANED PRIOR TO PAVING. THECLEANING OPERATION SHALL NOT FLUSH SEDIMENT LADEN WATER INTOTHE DOWNSTREAM SYSTEM.15.STABILIZED CONSTRUCTION ENTRANCES SHALL BE INSTALLED AT THEBEGINNING OF CONSTRUCTION AND MAINTAINED FOR THE DURATION OFTHE PROJECT. ADDITIONAL MEASURES MAY BE REQUIRED TO ENSURETHAT ALL PAVED AREAS ARE KEPT CLEAN FOR THE DURATION OF THEPROJECT.1. THE CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR BEINGFAMILIAR WITH THE PROVISIONS AND REQUIREMENTS CONTAINEDIN JURISDICTIONAL STANDARD SPECIFICATIONS. THE CONTRACTORSHALL HAVE A COPY AVAILABLE AT THE JOB SITE AT ALL TIMES.2. THE CONTRACTOR SHALL NOTIFY THE PUBLIC WORKSDEPARTMENT AT LEAST 48 HOURS PRIOR TO COMMENCEMENT OFWORK.3. THE CONTRACTOR SHALL NOTIFY ALL PUBLIC OR PRIVATE UTILITYCOMPANIES 48 HOURS PRIOR TO COMMENCEMENT OF WORKADJACENT TO EXISTING UTILITY LINES UNLESS AN ENCROACHMENTPERMIT SPECIFIES OTHERWISE.4. THE CONTRACTOR SHALL PROVIDE EMERGENCY TELEPHONENUMBERS TO THE POLICE, FIRE, AND PUBLIC WORKSDEPARTMENTS AND KEEP THEM INFORMED DAILY REGARDINGSTREETS UNDER CONSTRUCTION AND DETOURS. DETOURS SHALLNOT BE PERMITTED UNLESS APPROVED IN WRITING BY THE PUBLICWORKS DIRECTOR.5. THE CONTRACTOR SHALL PROVIDE AND MAINTAIN SUFFICIENTBARRICADES TO PROVIDE FOR THE SAFETY OF THE GENERALPUBLIC TO THE SATISFACTION OF THE PUBLIC WORKS DIRECTOR.6. ALL MATERIALS SHALL BE FURNISHED AND INSTALLED BY THECONTRACTOR UNLESS OTHERWISE NOTED.7. THE CONTRACTOR SHALL CONFORM TO EXISTING STREETS,SURROUNDING LANDSCAPE AND OTHER IMPROVEMENTS WITH ASMOOTH TRANSITION IN PAVING, CURBS, GUTTERS, SIDEWALKS,GRADING, ETC., AND AVOID ANY ABRUPT OR APPARENT CHANGESIN GRADES OR CROSS SLOPES, LOW SPOTS OR HAZARDOUSCONDITIONS.8. THE CONTRACTOR SHALL COORDINATE ALL NECESSARY UTILITYRELOCATIONS, IF REQUIRED, WITH THE APPROPRIATE UTILITYCOMPANIES.9. THE CONTRACTOR SHALL CONDUCT ALL GRADING OPERATIONS INSUCH A MANNER AS TO PRECLUDE WIND BLOWN DIRT AND DUSTAND RELATED DAMAGE TO NEIGHBORING PROPERTIES. SUFFICIENTWATERING TO CONTROL DUST IS REQUIRED AT ALL TIMES. THECONTRACTOR SHALL ASSUME ALL LIABILITY FOR CLAIMS RELATEDTO WIND BLOWN MATERIAL. IF THE DUST CONTROL IS INADEQUATEAS DETERMINED BY THE PUBLIC WORKS DIRECTOR OR HISDESIGNATED REPRESENTATIVE, THE CONSTRUCTION WORK SHALLBE TERMINATED UNTIL SUCH CORRECTIVE MEASURES ARE TAKEN.10.THE CONTRACTOR SHALL NOTIFY THE APPROPRIATE AGENCIESAND DEPARTMENTS FOR ALL REQUIRED INSPECTIONS PRIOR TOPLACING ANY UTILITIES INTO SERVICE.11.THE DESIGN SHOWN IS BASED UPON THE ENGINEER'SUNDERSTANDING OF THE EXISTING CONDITIONS. THIS PLAN DOESNOT REPRESENT A DETAILED FIELD SURVEY.12.CAUTION - NOTICE TO CONTRACTOR THE CONTRACTOR ISSPECIFICALLY CAUTIONED THAT THE LOCATION OF EXISTINGUTILITIES AS SHOWN ON THESE PLANS IS BASED ON RECORDS OFTHE VARIOUS UTILITY COMPANIES AND, WHERE POSSIBLE,MEASUREMENTS TAKEN IN THE FIELD. THE INFORMATION IS NOT TOBE RELIED ON AS BEING EXACT OR COMPLETE, THE CONTRACTORMUST CALL THE APPROPRIATE UTILITY COMPANY AT LEAST 48HOURS BEFORE ANY EXCAVATION TO REQUEST EXACT FIELDLOCATION OF UTILITIES. IT SHALL BE THE RESPONSIBILITY OF THECONTRACTOR TO RELOCATE ALL EXISTING UTILITIES WHICHCONFLICT WITH THE PROPOSED IMPROVEMENTS SHOWN ONTHESE PLANS.13.ALL DETAILS PROVIDED IN THESE PLANS SHALL BE APPLIED TO ALLAPPLICABLE PROPOSED CONSTRUCTION, REGARDLESS OFWHETHER OR NOT SPECIFIC REFERENCES TO APPLICABLE DETAILSARE MADE.14.POST CONSTRUCTION SOIL QUALITY AND DEPTH BMP DETAIL 3/C1SHALL BE APPLIED TO ALL DISTURBED PERVIOUS AREAS.15.DO NOT COMPACT THE BOTTOM OF THE INFILTRATION GALLERYDURING EXCAVATIONEROSION CONTROL NOTESTHE WORK ON THIS PROJECT SHALL BE PERFORMED IN ACCORDANCE WITHTHE CITY OF YELM STANDARDS, AND THE STANDARD SPECIFICATIONS FORROAD, BRIDGE AND MUNICIPAL CONSTRUCTION, 2022 WASHINGTON STATEDEPARTMENT OF TRANSPORTATION (WSDOT) (HEREAFTER "STANDARDSPECIFICATIONS")ALSO INCORPORATED INTO THESE CONTRACT DOCUMENTS BYREFERENCE ARE:A. CITY OF YELM DEVELOPMENT GUIDELINES, CURRENT EDITIONB. WASHINGTON STATE DEPARTMENT OF ECOLOGY STORMWATER MANAGEMENT MANUAL FOR WESTERN WASHINGTON, 2019 EDITION ("DRAINAGE MANUAL")C. THE INTERNATIONAL BUILDING CODE (IBC) AND THE INTERNATIONAL RESIDENTIAL CODE (IRC), CURRENT EDITIONS, WITH CITY AMENDMENTSD. MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES FOR STREETS AND HIGHWAYS (MUTCD), CURRENT EDITION, WITH WSDOT MODIFICATIONSE. THE INTERNATIONAL FIRE CODE, CURRENT EDITIONF. UNIFORM PLUMBING CODE (UPC), 2012 EDITION, WITH CITY AMENDMENTS.G. NATIONAL ELECTRICAL CODE (NEC), CURRENT EDITION.CURRENT EDITlONS OF THESE STANDARDS SHALL BE USED WHICH EXIST ONTHE DATE OF CONTRACT ACCEPTANCE.CONTRACTOR SHALL OBTAIN COPIES OF THESE PUBLICATIONS.THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING ALL LABOR,MATERIALS, TOOLS, EQUIPMENT, TRANSPORTATION, SUPPLIES, ANDINCIDENTALS REQUIRED TO COMPLETE ALL WORK SHOWN ON THESEDRAWINGS AND TO OBTAIN ACCEPTANCE BY THE CITY AND THE PROJECTOWNER.THE INTENT OF THESE DRAWINGS IS TO PRESCRIBE A COMPLETE WORK.OMISSIONS FROM THE DRAWINGS OF DETAILS OF WORK WHICH ARENECESSARY TO CARRY OUT THE INTENT OF THE DRAWINGS SHALL NOTRELIEVE THE CONTRACTOR FROM PERFORMING THE OMITTED WORK.ANY PROPOSED ALTERATIONS BY THE CONTRACTOR AFFECTING THEREQUIREMENTS AND INFORMATION IN THESE DRAWINGS SHALL BE INWRITING AND WILL REQUIRE APPROVAL OF THE ENGINEER AND INSPECTOR.PROJECT SPECIFICATIONSCONTRACTOR SHALL OBTAIN A RIGHT OF WAY PERMIT PRIOR TOCOMMENCING ANY WORK LOCATED IN THE CITY'S RIGHTOF WAY. ALL WORK PERFORMED IN THE CITY'S RIGHT OF WAYSHALL ADHERE TO DRAWINGS, STANDARD SPECIFICATIONS, ANDREQUIREMENTS OUTLINED IN THE RIGHT OF WAY PERMIT.WORK IN CITY RIGHT OF WAYTHE IRIS GROUP IS REQUIRED BY THE CITY TO PROVIDE RECORDDRAWING CERTIFICATION PRIOR TO FINAL CITY ACCEPTANCE. THE IRISGROUP WILL NOT CERTIFY RECORD DRAWINGS WITHOUT INSPECTIONOF BELOW GRADE UTILITIES AND STRUCTURES. PRIOR TOBACKFILLING, CONTRACTOR SHALL NOTIFY THE IRIS GROUP OFNECESSARY INSPECTIONS. THE CONTRACTOR SHALL MAINTAIN ONESET OF APPROVED PLANS ONSITE AND SHALL MARK, IN RED, ANYCHANGES TO THE PLANS THAT OCCUR DURING CONSTRUCTION.RECORD DRAWINGSIF UNSUITABLE MATERIALS AS DEFINED BY THE STANDARDSPECIFICATIONS ARE ENCOUNTERED, THIS MATERIAL SHALL BEREMOVED TO THE DEPTH REQUIRED BY THE ENGINEER OR INSPECTORAND REPLACED WITH SUITABLE MATERIALS.UNSUITABLE MATERIAL SHALL BE REMOVED FROM THE SITE ANDHAULED TO A WASTE SITE OBTAINED BY THE CONTRACTOR. PRIOR TOREMOVAL, CONTRACTOR SHALL NOTIFY PROJECT OWNER.REMOVAL OF UNSUITABLE MATERIALSSEE GEOTECHNICAL STUDY PREPARED BY MUD BAY GEOTECHNICALSERVICES, DATED 12/18/2022.GEOTECHNICAL INFORMATIONNAD 1983(2011) SOUTH ZONE; PER RTK GPS TIES AND THE WASHINGTONSTATE REFERENCE NETWORK (WSRN). UNITS OF MEASUREMENT AREU.S. SURVEY FEET.HORIZONTAL DATUMTOPOGRAPHIC INFORMATION DEPICTED IN THESE DRAWINGS WASPROVIDED IN A SURVEY BY INFORMED LAND SURVEY, DATED10/25/22. ALL EXISTING FEATURES AND TOPOGRAPHY SHOWNSHALL BE VERIFIED PRIOR TO BEGINNING CONSTRUCTION. ANY ANDALL DISCREPANCIES FOUND BETWEEN ACTUAL EXISTINGCONDITIONS AND THE EXISTING CONDITIONS SHOWN HERE SHALLBE IDENTIFIED TO THE PROJECT ENGINEER PRIOR TO CONTINUANCEOF ANY WORK.TOPOGRAPHIC DATACONSTRUCTION NOTES1 - C1 COVER2 - C2 SITE AND HORIZONTAL CONTROL PLAN3 - C3 DEMOLITION AND TESC PLAN4 - C4 STORMWATER AND UTILITY PLAN5 - C5 GRADING PLAN6 - C6 DETAILS 17 - C7 DETAILS 28 - C8 DETAILS 3SHEET INDEXWENTWORTH COMMERCIALDEVELOPMENTYELM, WA1. THE CONTRACTOR SHALL OBTAIN ALL APPROVALS AND PERMITSREQUIRED BY THE CITY OF YELM (CITY) PRIOR TO THE START OFCONSTRUCTION. A GRADING PERMIT FOR STORM PONDCONSTRUCTION MAY BE REQUIRED.2. STORM DRAIN PIPE SHALL BE ON THE WSDOT QUALIFIEDPRODUCTS LIST FOR THE SPECIFICATION LISTED BELOW:A. PLAIN CONCRETE STORM SEWER PIPE OR REINFORCEDCONCRETE STORM SEWER PIPE PER WSDOT STANDARDSPECIFICATION 9-05.7.B. SOLID WALL PVC STORM SEWER PIPE PER WSDOT STANDARDSPECIFICATION 9- 05.12(1).C. DUCTILE IRON SEWER PIPE PER WSDOT STANDARDSPECIFICATION 9-05.13.D. HANCOR BLUE SEAL ™ AND ADVANCED DRAINAGE SYSTEMS(ADS/HANCOR) N-12 HDPE AND (ADS/HANCOR) SANITITE UP TO36" IN DIAMETER PER WSDOT STANDARD SPECIFICATIONS9-05.20 AND 9-05.24.E. CONTECH DUROMAXX STEEL RIB REINFORCED POLYETHYLENEPIPE, IN DIAMETERS FROM 24 INCH TO 60 INCH PER WSDOTSTANDARD SPECIFICATION 9-05.22.3. ALL STORM DRAINAGE SYSTEMS SHALL BE AIR TESTED AT 4 PSIEXCEPT CONCRETE PIPE, WHICH SHALL BE TESTED PERWSDOT/APWA STANDARD FOR CONCRETE STORM PIPE. ALLFLEXIBLE PIPE SHALL BE MANDREL TESTED PER WSDOT/APWASTANDARDS. TESTING SHALL BE DONE BY THE CONTRACTOR.4. TESTING OF THE STORM SEWER SHALL INCLUDE VIDEOTAPING OFTHE MAIN BY THE CONTRACTOR. IMMEDIATELY PRIOR TOVIDEOTAPING, ENOUGH WATER SHALL BE RUN DOWN THE LINESO IT COMES OUT THE LOWER CATCH BASIN. A COPY OF THEVIDEO TAPE SHALL BE SUBMITTED TO THE CITY. ACCEPTANCE OFTHE LINE WILL NOT BE MADE UNTIL AFTER THE TAPE HAS BEENREVIEWED AND APPROVED BY THE CITY. TESTING SHALL TAKEPLACE AFTER ALL UNDERGROUND UTILITIES ARE INSTALLED ANDCOMPACTION OF THE ROADWAY SUBGRADE IS COMPLETE.5. SPECIAL STRUCTURES, OIL/WATER SEPARATORS AND OUTLETCONTROLS SHALL BE INSTALLED PER PLANS ANDMANUFACTURERS' RECOMMENDATIONS. WHERE OIL/WATERSEPARATORS ARE CONNECTED TO A SEWER SYSTEM, THEYSHALL BE INSTALLED WITH A P-TRAP OR CHECK VALVE TOPREVENT ODORS.6. ALL DISTURBED AREAS SHALL BE STABILIZED IN ACCORDANCEWITH MINIMUM REQUIREMENT 2 OF THE LATEST EDITION OF THEDEPARTMENT OF ECOLOGY STORMWATER MANAGEMENTMANUAL FOR WESTERN WASHINGTON (SWMMWW). FOR SITESWHERE VEGETATION HAS BEEN PLANTED THROUGH HYDROSEEDING, THE FINANCIAL GUARANTEE WILL NOT BE RELEASEDUNTIL THE VEGETATION HAS BEEN THOROUGHLY ESTABLISHED.7. WHERE CONNECTIONS REQUIRE "FIELD VERIFICATION", THECONTRACTOR SHALL EXPOSE SUCH CONNECTION POINTS ANDFITTINGS 48 HOURS PRIOR TO DISTRIBUTING SHUTDOWNNOTICES.8. ANY CHANGES TO THE DESIGN SHALL FIRST BE REVIEWED ANDAPPROVED BY THE PROJECT ENGINEER AND THE CITY'S CIVILREVIEW ENGINEER.9. ALL STORM PIPE SHALL BE A MINIMUM OF 12-INCH DIAMETER FORMAINS AND CROSSINGS. WHEN PRIVATE STORMWATER (I.E. ROOF,LOT OR FOOTING DRAINS) CANNOT BE INFILTRATED ONINDIVIDUAL LOTS, THE MINIMUM STANDARD PIPING CONNECTIONTO THE PUBLIC SYSTEM SHALL BE 8-INCH PVC. THE 8-INCH MAINUSED FOR CONNECTION SHALL BEGIN AT THE RIGHT-OF-WAY,AND THE CONNECTION TO THE CATCH BASIN OR MANHOLESHALL BE CORED AND GROUTED.10. ALL STORM MAINS AND RETENTION/DETENTION AREAS SHALL BESTAKED FOR GRADE AND ALIGNMENT BY AN ENGINEERING ORSURVEY FIRM LICENSED TO PERFORM SUCH WORK.11. THE MINIMUM STAKING OF STORM SEWER SYSTEMS SHALL BE INACCORDANCE WITH SECTION 3.00.050 OF THESE STANDARDS,AND AS FOLLOWS:A. STAKE LOCATION OF ALL CATCH BASINS, MANHOLES ANDOTHER FIXTURES FOR GRADE AND ALIGNMENT.B. STAKE LOCATION, SIZE, AND DEPTH OF RETENTION/DETENTIONFACILITY.C. STAKE FINISHED GRADE OF ALL STORMWATER FEATURES,INCLUDING BUT NOT LIMITED TO CATCH BASIN/MANHOLE RIMELEVATIONS, OVERFLOW STRUCTURES, WEIRS, AND INVERTELEVATIONS OF ALL PIPES IN CATCH BASINS, MANHOLES, ANDPIPES THAT DAYLIGHT.12. PIPE MATERIALS USED FOR STORMWATER CONVEYANCE SHALLBE AS APPROVED BY THE CITY. PIPE SIZE, SLOPE, COVER, ETC.,SHALL BE AS SPECIFIED IN THE CITY OF YELM DEVELOPMENTGUIDELINES AND ENGINEERING STANDARDS.13. ALL DRIVEWAY CULVERTS SHALL BE OF SUFFICIENT LENGTH TOPROVIDE A MINIMUM 3:1 SLOPE FROM THE EDGE OF THEDRIVEWAY TO THE BOTTOM OF THE DITCH. CULVERTS SHALLHAVE BEVELED END SECTIONS TO MATCH THE SIDE SLOPE.14. IF DRAINAGE OUTLETS (STUB-OUTS) ARE TO BE PROVIDED FOREACH INDIVIDUAL LOT, THE STUB OUTS SHALL CONFORM TO THEFOLLOWING:A. EACH OUTLET SHALL BE LOCATED AT THE LOWEST ELEVATIONON THE LOT, TO SERVICE ALL FUTURE ROOF DOWNSPOUTS ANDFOOTING DRAINS, DRIVEWAYS, YARD DRAINS, AND ANY OTHERSURFACE OR SUBSURFACE. EACH OUTLET SHALL HAVEFREE-FLOWING, POSITIVE DRAINAGE TO AN APPROVED STORMWATER CONVEYANCE SYSTEM OR TO AN APPROVED OUTFALLLOCATION.B. OUTLETS ON EACH LOT SHALL BE LOCATED WITH A 5-FOOTHIGH, 2"X 4" STAKE MARKED "STORM" OR "DRAIN." THE STUB-OUTSHALL VISIBLY EXTEND ABOVE SURFACE LEVEL AND BE SECUREDTO THE STAKE.C. PIPE MATERIAL SHALL BE AS APPROVED BY THE CITY.D. DRAINAGE EASEMENTS ARE REQUIRED FOR DRAINAGESYSTEMS DESIGNED TO CONVEY FLOWS THROUGH INDIVIDUALLOTS.E. THE DEVELOPER AND/OR CONTRACTOR IS RESPONSIBLE FORCOORDINATING THE LOCATIONS OF ALL STUB-OUT CONVEYANCELINES WITH RESPECT TO THE UTILITIES (E.G., POWER, GAS,TELEPHONE, TELEVISION).F. ALL INDIVIDUAL STUB-OUTS SHALL BE PRIVATELY OWNED ANDMAINTAINED BY THE LOT HOMEOWNER.15. THE STORM DRAINAGE SYSTEM SHALL BE CONSTRUCTEDACCORDING TO APPROVED PLANS ON FILE WITH THE CITY. ANYMATERIAL DEVIATION FROM THE APPROVED PLANS WILLREQUIRE WRITTEN APPROVAL FROM THE CITY.16. ALL DISTURBED AREAS SHALL BE SEEDED AND MULCHED ORSIMILARLY STABILIZED TO THE SATISFACTION OF THE CITY. FORSITES WHERE GRASS HAS BEEN PLANTED THROUGH HYDROSEEDING, THE PERFORMANCE BOND WILL NOT BE RELEASEDUNTIL THE GRASS HAS BEEN THOROUGHLY ESTABLISHED, UNLESSOTHERWISE APPROVED BY THE CITY.17. ALL BUILDING DOWNSPOUTS ON COMMERCIAL SITES SHALL BECONNECTED TO THE STORM DRAINAGE SYSTEM, UNLESSOTHERWISE APPROVED BY THE CITY.18. ALL EROSION CONTROL AND STORMWATER FACILITIES SHALL BEREGULARLY INSPECTED AND MAINTAINED BY THE CONTRACTORDURING THE CONSTRUCTION PHASE OF THE DEVELOPMENTPROJECT.19. NO FINAL CUT OR FILL SLOPE SHALL EXCEED TWO (2)HORIZONTAL TO ONE (1) VERTICAL WITHOUT STABILIZATION BYROCKERY OR BY A STRUCTURAL RETAINING WALL.20. THE PROJECT ENGINEER SHALL VERIFY THE LOCATIONS, WIDTHS,THICKNESSES, AND ELEVATIONS OF ALL EXISTING PAVEMENTSAND STRUCTURES, INCLUDING UTILITIES AND OTHER FRONTAGEIMPROVEMENTS, THAT ARE TO INTERFACE WITH NEW WORK,AND PROVIDE ALL TRIMMING, CUTTING, SAW CUTTING, GRADING,LEVELING, SLOPING, COATING, AND OTHER WORK, INCLUDINGMATERIALS NECESSARY TO CAUSE THE INTERFACE WITHEXISTING WORKS TO BE PROPER, WITHOUT CONFLICT,ACCEPTABLE TO THE PROJECT ENGINEER AND THE CITY'S CIVILREVIEW ENGINEER, COMPLETE IN PLACE, AND READY TO USE.21. COMPACTION OF ALL FILL AREAS SHALL BE PER CURRENT APWASPECIFICATIONS. FILL SHALL BE PROVIDED IN 6" MAXIMUM LIFTSAND SHALL BE COMPACTED TO 95 PERCENT OF ITS MAXIMUMRELATIVE DENSITY.STORMWATER GENERAL NOTES (CITY)NAVD 88 PER RTK GPS TIES AND THE WASHINGTON STATE REFERENCENETWORK (WSRN). UNITS OF MEASUREMENT ARE U.S. SURVEY FEET.VERTICAL DATUMLOTS 1 AND 2 IN BLOCK 9 OF SOLBERG'S FIRST ADDITION TO YELM, ASRECORDED IN VOLUME 9 OF PLATS, PAGE 31; IN THURSTON COUNTY,WASHINGTON.LEGAL DESCRIPTION1.ALL WORKMANSHIP AND MATERIALS SHALL BE IN ACCORDANCEWITH CITY OF YELM STANDARDS, AND THE MOST CURRENT COPYOF THE STATE OF WASHINGTON STANDARD SPECIFICATIONS FORROAD, BRIDGE, AND MUNICIPAL CONSTRUCTION.2.THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL TRAFFICCONTROL IN ACCORDANCE WITH MUTCD. PRIOR TO DISRUPTIONOF ANY TRAFFIC, TRAFFIC CONTROL PLANS SHALL BE PREPAREDAND SUBMITTED TO THE CITY FOR APPROVAL. NO WORK SHALLCOMMENCE UNTIL ALL APPROVED TRAFFIC CONTROL IS IN PLACE.3.ALL CURB AND GUTTER, STREET GRADES, SIDEWALK GRADES,AND ANY OTHER VERTICAL AND/OR HORIZONTAL ALIGNMENTSHALL BE STAKED BY AN ENGINEERING OR SURVEYING FIRMCAPABLE OF PERFORMING SUCH WORK.4.WHERE NEW ASPHALT JOINS EXISTING, THE EXISTING ASPHALTSHALL BE CUT TO A NEAT VERTICAL EDGE AND TACKED WITHASPHALT EMULSION TYPE CSS1 IN ACCORDANCE WITH THESTANDARD SPECIFICATIONS. THE NEW ASPHALT SHALL BEFEATHERED BACK OVER EXISTING TO PROVIDE FOR A SEAL ATTHE SAW CUT LOCATION AND THE JOINT SEALED WITH GRADEAR-4000W PAVING ASPHALT.5.COMPACTION OF SUBGRADE, ROCK, AND ASPHALT SHALL BE INACCORDANCE WITH THE STANDARD SPECIFICATIONS.6.SUBGRADE INSPECTION SHALL BE PERFORMED BY AN APPROVEDTESTING FIRM AND FORMS SHALL BE INSPECTED FOR LINE ANDGRADE BY AN ENGINEER BEFORE POURING CONCRETE.7.CERTIFICATION AS TO CONFORMANCE SHALL BE PROVIDED TOTHE CITY PRIOR TO ACCEPTANCE OF WORK.8.THE CONTRACTOR/DEVELOPER SHALL FURNISH AND INSTALL ALLPERMANENT SIGNING.STREET CONSTRUCTION NOTESUTILITY LOCATE NOTETHE LOCATION OF EXISTING UTILITIES SHOWN HEREON AREAPPROXIMATE AND ARE BASED ON INFORMATION PROVIDED BY THESURVEYOR AND FROM COUNTY RECORDS. OLYMPIC ENGINEERINGASSUMES NO RESPONSIBILITY FOR THE EXACT LOCATION OF EXISTINGUTILITIES SHOWN OR NOT SHOWN HEREON CONTRACTOR SHALLVERIFY THE EXACT SIZE, DEPTH, AND LOCATION OF EXISTING UTILITIESAND CALL FOR UNDERGROUND LOCATE AT 811 A MINIMUM OF48-HOURS PRIOR TO CONSTRUCTION START. CONTRACTOR SHALL BEFULLY RESPONSIBLE FOR ANY AND ALL DAMAGES RESULTING FROMFAILURE TO LOCATE EXISTING UTILITIES. COCOPMTPMT0.2'0.6'5.6'6.4'S49° 29' 55"E100.01'S40° 30' 51"W120.00'N49° 30' 11"W100.02'N40° 31' 05"E 120.00'N:594289.55E:1113365.82N:594337.44E:1113406.75N:594312.39E:1113436.07N:594301.06E:1113454.03N:594274.85E:1113375.32N:594250.72E:1113355.76N:594232.94E:1113376.29N:594266.95E:1113455.68N:594364.78E:1113408.03N:594208.60E:1113406.123+00 4+00 4+10STA: 3+80.30OFF: 17.76STA: 3+59.63OFF: 11.00STA: 3+36.63OFF: 11.00STA: 3+16.63OFF: 18.00STA: 2+89.08OFF: 18.00STA: 2+61.53OFF: 18.00STA: 4+10.01OFF: 0.00N40° 31' 05"E 310.01'FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM SITE AND HORIZONTAL CONTROL PLAN SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC229123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 9' TYP20' TYP23' 11.1'9' 5' 8' 8'8'8'6'5' 9'8.8'18'KEY NOTES1.PROPOSED ASPHALT CEMENT CONCRETE PER PAVEMENT NOTES2.PROPOSED REVEGETATION TO LAWN. REMOVE GRAVEL. SCARIFYSUBGRADE TO 4" DEPTH, AND APPLY THE POST CONSTRUCTION SOILQUALITY AND DEPTH DETAIL 2/C63.PROPOSED PORTLAND CEMENT CONCRETE PAVEMENT PERPAVEMENT NOTES. SIDEWALKS SHALL BE PER DETAIL 1/C6.4.PROPOSED MONUMENT SIGN TO BE REPLACED UNDER SEPARATEPERMIT (42 SF EACH SIDE)5.PROPOSED WHEEL STOP PER DETAIL 2/C8 (TYP)6.PROPOSED ADA STALL AND SIGN PER DETAILS 3,4/C67.PROPOSED PARKING STALL MARKING. 4" DOUBLE-COATED WHITELINES. (TYP)8.PROPOSED 45-DEGREE DIAGONAL 4" DOUBLE-COATED WHITE LINESAT 24" ON CENTER9.PROPOSED PARKING LOT LANDSCAPING PER SEPARATE LANDSCAPEPLANS. 309 SF10.PROPOSED WOOD ADA RAMP. ASSUMED 30" RISE OVER 30' RUN. SEESEPARATE BUILDING PLANS.11.PROPOSED DECK REPLACEMENT. SEE SEPARATE BUILDING PLANS.12.PROPOSED STAIRS. SEE SEPARATE BUILDING PLANS.13.PROPOSED PERIMETER LANDSCAPING. SEE SEPARATE LANDSCAPINGPLANS.14.EXISTING ASPHALT PAVEMENT TO REMAIN.15.PROPOSED SINGLE-DIRECTION CURB RAMP WITH TRUNCATED DOMESPER DETAILS 1,2/C816.PROPOSED CONCRETE BARRIER CURB AND GUTTER PER DETAIL 1/C817.INSTALL 4" WIDE PAINTED WHITE STRIPING LINES FOR ON-STREETPARALLEL PARKING STALLS (2 TOTAL) AS SHOWN.#PAVEMENT NOTESONSITE ASPHALT CEMENT CONCRETE (ACC) PAVEMENT SECTION SHALL BE12" OF COMPACTED SUBGRADE UNDER 6" OF CRUSHED SURFACING BASECOURSE (CSBC) UNDER 3" OF CRUSHED SURFACING TOP COURSE (CSTC)UNDER 3" OF ACC.OFFSITE ACC SECTION SHALL BE PER DETAIL 3/C7PORTLAND CEMENT CONCRETE (PCC) SECTION FOR SIDEWALKS SHALL BE 6"OF COMPACTED SUBGRADE UNDER 6" OF CSBC UNDER 4" OF PCCPROVIDE EMULSIFIED ASPHALT GRADE CSS-1 TACK COAT ALONG SAWCUTEDGE WHERE APPLICABLE. MATCH TO EXISTING ASPHALT GRADES.SW RICE ST YELM AVE SEALLEY112334SCALE IN FEET201006789101112131313144'EXISTINGBUILDINGCHANGING TOSERVICE-ORIENTEDUSE(1 STORY)(483 SF)EXISTINGSERVICE-ORIENTEDBUILDINGTO BE IMPROVED(2 STORIES)(990 SF)5.5'0.5'5.6'20'30'R35'NAD 1983(2011) SOUTH ZONE; PER RTK GPS TIES AND THE WASHINGTON STATEREFERENCE NETWORK (WSRN). UNITS OF MEASUREMENT ARE U.S. SURVEYFEET.HORIZONTAL DATUM1515163C711'517 WWWWWWWWWWWWWWWWWWW W W W W W W W W W W W W W W W W W W W W W WCO COPMTPMTCONC WALKEXISTINGBUILDINGEXISTINGGARAGECONC WALKGRAVELGRAVELGRAVELASPHALTDRIVECONCCONCBLOCKWALLCONCBLOCKWALLEXISTINGBUILDINGEDGE OF ASPHALTCURBEDGE OF ASPHALTEDGE OF ASPHALT EDGE OF ASPHALTEDGE OF ASPHALTROOF PEAKEL==372.18'F.F.E.=353.29'EXISTINGSHED0.2'0.6'5.6'6.4'SSFILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM DEMOLITION & TESC PLAN SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC339123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 1234567KEY NOTES1.EXISTING ASPHALT CEMENT CONCRETE (ACC) DRIVEWAY. USE ASCONSTRUCTION ENTRANCE.2.DEMOLISH AND DISPOSE OF EXISTING PORTLAND CEMENT CONCRETE(PCC) SIDEWALK3.DEMOLISH AND DISPOSE OF EXISTING PCC SIDEWALK4.PROTECT EXISTING PCC SIDEWALK5.DEMOLISH AND DISPOSE OF EXISTING SIGN AND ASSOCIATEDCONCRETE BLOCKS6.PROTECT EXISTING TREE TO REMAIN (TYP)7.SAWCUT, REMOVE, AND DISPOSE OF EX. ASPHALT AS SHOWN.REMOVE EXISTING ROAD SECTION AS NEEDED TO ACCOMMODATENEW 4" DEPTH OF PAVEMENT. SEE RICE ST. SECTION DETAIL 3/C8.CONTRACTOR SHALL CONTACT THE GEOTECHNICAL ENGINEER ANDCITY PUBLIC WORKS INSPECTOR TO INSPECT EXISTING SUBGRADEPRIOR TO INSTALLATION OF THE ROADWAY SECTION. CONTRACTORSHALL PROVIDE A MIN. 48-HOUR NOTICE.(TYP)8.PROPOSED LIMITS OF DISTURBANCE9.PROTECT EXISTING WATER MAIN10.PROTECT EXISTING GAS LINE#SCALE IN FEET201008SW RICE ST YELM AVE SEALLEY773910INSTALL AND MAINTAIN INLET PROTECTION SILT SOCK AT ALLPROPOSED CATCH BASINS.NOTES WWWWWWWWWWWWWWWWWWW W W W W W W W W W W W W W W W W W WCOCO PMTPMT0.2'0.6'5.6'6.4'SSRD RD RD RD RDRDRDRDRDRD RD RDRDRDRDRD SD SDOHPOHPOHPOHPOHPOHP SSSSSSSSSSSSSSSSSS SS WWWWWWW WSD SD SD SD SDSDSD3523513503503513 5 2 352350350350349350 351 3523493503493503493503513403453503553403453503552+202+252+50350.02+75350.4350.26 3+00351.0 350.60 3+25351.4 351.09 3+50351.8 351.52 3+75351.62 4+001.87%1.43%1.60%1.92%1.79%2.14%1.94%1.45%1.91%0.43%0.34%FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM STORMWATER & UTILITY PLAN SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC449123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 SW RICE ST YELM AVE SEALLEYKEY NOTES1.PROPOSED INFILTRATION GALLERY PER DETAILS 5/C6 AND 1,2/C72.PROPOSED BAY FILTER CATCH BASIN PER DETAIL 3/C7RIM: 348.6212" IE (NE): 342.8812" IE (NW): 344.8812" IE (SE): 345.903.PROPOSED 3 LF 12" SDR35 PVC STORM DRAIN AT 0.005 FT/FT4.PROPOSED 20LF 6" SDR35 PVC STORM DRAIN AT 0.020 FT/FT5.PROPOSED FLOWLINE PROFILE6.IE: 342.867.PROPOSED INSPECTION PORT PER DETAIL 4/C78.PROPOSED ROOF DRAIN CLEANOUT PER DETAIL 6/C6 AND STORM DRAIN NOTES.9.PROPOSED ROOF DRAIN LINE PER DETAIL 6/C6 AND ROOF AND STORM DRAIN NOTES.10.EXISTING OVERHEAD POWER TO BE RELOCATED11.PROPOSED OVERHEAD POWER12.PROPOSED 1.25" CL200 PVC OR HDPE GRINDER PUMP LINE TO BE 18" DEEPER THAN PARALLEL ORCROSSING WATER LINE. IF THIS SEPARATION CANNOT BE MET, THE GRINDER PUMP LINE AND WATER LINESHALL BE BACKFILLED WITH CONTROLLED DENSITY FILL 6" ALL SIDES.13.PROPOSED 3/4" CL200 PVC WATER LINE14.PROPOSED GRINDER PUMP (DESIGN BY OTHERS)15.PROPOSED POWER POLE16.EXISTING WATER METER17.EXISTING GRAVITY SEWER CLEANOUT18.EXISTING GAS LINE. DEPTH AND MATERIAL UNKNOWN. DO NOT DAMAGE DURING CONSTRUCTION.19.EXISTING ROOF AREA (484 SF)20.EXISTING ROOF AREA (1,003 SF)21.EXISTING 10" WATER MAIN; DEPTH TO CROWN ASSUMED TO BE 3'. VERIFY 3' BURIAL DEPTH PRIOR TOCONSTRUCTION.22.PROPOSED TYPE 1 CATCH BASIN W/ GRATE PER DETAIL 4/C8RIM: 350.1212" IE (NE): 347.6223.PROPOSED 42 LF 12" SDR35 PVC STORM DRAIN AT 0.005 FT/FT24.PROPOSED 48" TYPE 2 CATCH BASIN W/ GRATE PER DETAIL 3/C9RIM: 350.6912" IE (SW): 347.4012" IE (SE): 345.0725.PROPOSED 42 LF 12" SDR35 PVC STORM DRAIN AT 0.005 FT/FT26.EXISTING CENTERLINE GRADE27.MAINTAIN 6" VERTICAL SEPARATION BETWEEN WATER MAIN AND PROPOSED STORM DRAIN. PROVIDEASTM C33 SAND CUSHION.28.PROPOSED TYPE 1 CATCH BASIN W/ GRATE PER DETAIL 4/C8RIM: 348.5912" IE (NW): 346.00#123467891011121314151617·EXISTING HARD SURFACE: 8,539 SF·NEW PLUS REPLACED HARD SURFACE:5,505 SF·HARD SURFACE AFTER PROJECT:9,721 SF·NEW + REPLACED POLLUTION GENERATING HARD SURFACE:8,233 SF·LAWN + LANDSCAPE AFTER PROJECT:5,738 SF·PROPOSED EFFECTIVE HARD SURFACE:0 SF·DISTURBED AREA:15,459 SFSITE COVERAGE DATA (WITHIN LOD)ROOF AND STORM DRAIN NOTES1.ROOF DRAIN PIPE SHALL BE SDR 35 PVC AND SHALL BE AT A MINIMUM 2% GRADE TO DRAIN TO DISCHARGELOCATION2.PIPE TRENCHING AND BACKFILL SHALL BE PER PIPE MANUFACTURER SPECIFICATIONS3.ALL PIPE SHALL BE CLEANED VIA FLUSHING PRIOR TO CONNECTION TO DISCHARGE LOCATION4.DRAIN FITTINGS SHALL BE SDR 35 PVC FITTINGS5.ROOF AND STORM DRAIN PIPE SHALL BE LAID STRAIGHT WITH NO SAGS OR BENDS IN PIPE. BENDS SHALLBE CONSTRUCTED WITH WATERTIGHT FITTINGS. 45-DEGREE WYE CLEANOUTS SHALL BE INSTALLEDUPSTREAM OF ALL BENDS AND SHALL BE PER DETAIL 6/C66.CONNECT ALL DOWNSPOUTS TO ROOF DRAINS WITH SDR 35 PVC FITTINGS PER DETAIL 6/C67.DO NOT CONNECT ROOF DRAIN PIPE TO FOOTING DRAIN PIPE18SCALE IN FEET2010019202122232425RICE ST PROFILEHORIZTONTAL 1"=20'VERTICAL 1"=5'12223242126272C76.5'13.2'NAD 1983(2011) SOUTH ZONE; PER RTK GPS TIES AND THEWASHINGTON STATE REFERENCE NETWORK (WSRN). UNITS OFMEASUREMENT ARE U.S. SURVEY FEET.HORIZONTAL DATUMNAVD 88 PER RTK GPS TIES AND THE WASHINGTON STATEREFERENCE NETWORK (WSRN). UNITS OF MEASUREMENT AREU.S. SURVEY FEET.VERTICAL DATUM285FLOWLINE ELEVATIONCENTERLINE ELEVATION COCOPMTPMT352.39351.00350.02350.02350.02349.08349.07349.06348.92348.76348.84350.61350.52350.67350.58350.34350.43350.17350.15348.82348.99349.08348.59351.16351.06350.94351.03351.19351.28351.51351.60351.83351.933523513503503513 5 2 352350350350349350 351 352349350349350349350351350.66349.41349.43349.37349.41349.78349.82349.77349.73349.62349.96349.96351.68FL: 351.63TC: 352.13FL: 351.62TC: 352.12FL: 351.59TC: 352.09FL: 351.32TC: 351.82FL: 350.94TC: 351.44FL: 350.47TC: 350.97FL: 350.09TC: 350.59FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM GRADING PLAN SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC559123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 SW RICE ST YELM AVE SEALLEYSCALE IN FEET20100NAD 1983(2011) SOUTH ZONE; PER RTK GPS TIES AND THEWASHINGTON STATE REFERENCE NETWORK (WSRN). UNITS OFMEASUREMENT ARE U.S. SURVEY FEET.HORIZONTAL DATUMNAVD 88 PER RTK GPS TIES AND THE WASHINGTON STATEREFERENCE NETWORK (WSRN). UNITS OF MEASUREMENT AREU.S. SURVEY FEET.VERTICAL DATUMFL = FLOW LINE ELEVATIONTC = TOP OF CURB ELEVATION FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM DETAILS 1 SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC669123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 DETAILNOT TOSCALE1POST CONSTRUCTION SOIL QUALITY AND DEPTH DETAILNOT TOSCALE2ADA SIGNDETAILNOT TOSCALE3ADA SYMBOL DETAILNOT TOSCALE4NOT TOSCALEROOF DRAIN DETAILNOT TOSCALEFINISHED GRADEINSERT INJECTION MOLDED,GASKETED SPIGOT BY BELL REDUCERTEE4" SDR35 PVC PIPE (TYP)90° BEND45° BENDDOWNSPOUT ADAPTERINSERTED IN RISERPIPEBUILDINGFACE6" SDR35 PVC PIPE45° WYECLEANOUT W/ THREADED CAP6515.75'50.23'12" x 12" ADS N-12 MANIFOLDINSPECTION PORTINSTALL ADSPLUS125 WOVEN GEOTEXTILE OVER BEDDING STONE AND UNDERCHAMBER FEET FOR SCOUR PROTECTION AT ALL CHAMBER INLET ROWSFROM BAY FILTERCATCH BASININ-SITU INFILTRATION TESTING OF THE NATIVE SUBGRADE AT THE BASE OF THE STORMWATER INFILTRATION/DETENTIONSYSTEM IS REQUIRED AFTER EXCAVATION TO SUBGRADE, AT THE OWNER'S EXPENSE. A CORRECTED/DESIGN INFILTRATIONRATE LESS THAN 6.5 INCHES PER HOUR WILL REQUIRE RE-SIZING OF THE INFILTRATION/DETENTION SYSTEM. CONTRACTORSHALL CONTACT AN INFILTRATION TESTING FIRM 7 DAYS PRIOR TO REACHING SUBGRADE TO SCHEDULE THE INFILTRATIONTESTING.INFILTRATION/DETENTION FACILITYDETAIL FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM DETAILS 2 SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC779123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 DETAILNOT TOSCALE1 DETAILNOT TOSCALE3 DETAILNOT TOSCALE2INSPECTION PORT DETAILNOT TOSCALE4BOTTOM ELEV = 342.36NOTE:SEE WSDOT STANDARD PLANS B-10.20-01B-30.90-01 FOR ACCESS AND STEP/LADDERLOCATION/ORIENTATION AND DETAILS.INLET ELEVATION: 345.90, 344.88OUTLET ELEVATION: 342.88RIM ELEVATION: 348.62344.8812" FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM DETAILS 3 SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC889123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 DETAILNOT TOSCALE1 DETAILNOT TOSCALE3 DETAILNOT TOSCALE2 DETAILNOT TOSCALE430' FILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM DETAILS 4 SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC999123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 DETAILNOT TOSCALE1 DETAILNOT TOSCALE3 DETAILNOT TOSCALE2 Appendix C JW301 WWHM 12/22/2022 11:18:03 AM Page 2 General Model Information Project Name:JW301 WWHM Site Name:Wentworth Site Address: City: Report Date:12/22/2022 Gage:Lake Lawrence Data Start:1955/10/01 Data End:2008/09/30 Timestep:15 Minute Precip Scale:0.857 Version Date:2021/08/18 Version:4.2.18 POC Thresholds Low Flow Threshold for POC1:50 Percent of the 2 Year High Flow Threshold for POC1:50 Year Low Flow Threshold for POC2:50 Percent of the 2 Year High Flow Threshold for POC2:50 Year JW301 WWHM 12/22/2022 11:18:03 AM Page 3 Landuse Basin Data Predeveloped Land Use Entire Limits of Disturbance Bypass:No GroundWater:No Pervious Land Use acre A B, Forest, Flat 0.389 Pervious Total 0.389 Impervious Land Use acre Impervious Total 0 Basin Total 0.389 Element Flows To: Surface Interflow Groundwater JW301 WWHM 12/22/2022 11:18:03 AM Page 4 Basin 2 Bypass:No GroundWater:No Pervious Land Use acre A B, Forest, Flat 0.389 Pervious Total 0.389 Impervious Land Use acre Impervious Total 0 Basin Total 0.389 Element Flows To: Surface Interflow Groundwater JW301 WWHM 12/22/2022 11:18:03 AM Page 5 Mitigated Land Use Onsite and Offsite Infiltration Sizing Basin Bypass:No GroundWater:No Pervious Land Use acre A B, Lawn, Flat 0.1317 Pervious Total 0.1317 Impervious Land Use acre ROOF TOPS FLAT 0.0341 DRIVEWAYS FLAT 0.2232 Impervious Total 0.2573 Basin Total 0.389 Element Flows To: Surface Interflow Groundwater Gravel Trench Bed 1 Gravel Trench Bed 1 JW301 WWHM 12/22/2022 11:18:03 AM Page 6 Treatment Sizing Basin Bypass:No GroundWater:No Pervious Land Use acre A B, Lawn, Flat 0.13 Pervious Total 0.13 Impervious Land Use acre DRIVEWAYS FLAT 0.223 Impervious Total 0.223 Basin Total 0.353 Element Flows To: Surface Interflow Groundwater JW301 WWHM 12/22/2022 11:18:03 AM Page 7 Routing Elements Predeveloped Routing JW301 WWHM 12/22/2022 11:18:03 AM Page 8 Mitigated Routing Gravel Trench Bed 1 Bottom Length:43.00 ft. Bottom Width:15.75 ft. Trench bottom slope 1:0 To 1 Trench Left side slope 0:0 To 1 Trench right side slope 2:0 To 1 Material thickness of first layer:0.5 Pour Space of material for first layer:0.4 Material thickness of second layer:2.5 Pour Space of material for second layer:0.65 Material thickness of third layer:0.5 Pour Space of material for third layer:0.4 Infiltration On Infiltration rate:6 Infiltration safety factor:1 Total Volume Infiltrated (ac-ft.):45.168 Total Volume Through Riser (ac-ft.):0 Total Volume Through Facility (ac-ft.):45.168 Percent Infiltrated:100 Total Precip Applied to Facility:0 Total Evap From Facility:0 Discharge Structure Riser Height:4 ft. Riser Diameter:6 in. Element Flows To: Outlet 1 Outlet 2 Gravel Trench Bed Hydraulic Table Stage(feet)Area(ac.)Volume(ac-ft.)Discharge(cfs)Infilt(cfs) 0.0000 0.015 0.000 0.000 0.000 0.0556 0.015 0.000 0.000 0.094 0.1111 0.015 0.000 0.000 0.094 0.1667 0.015 0.001 0.000 0.094 0.2222 0.015 0.001 0.000 0.094 0.2778 0.015 0.001 0.000 0.094 0.3333 0.015 0.002 0.000 0.094 0.3889 0.015 0.002 0.000 0.094 0.4444 0.015 0.002 0.000 0.094 0.5000 0.015 0.003 0.000 0.094 0.5556 0.015 0.003 0.000 0.094 0.6111 0.015 0.004 0.000 0.094 0.6667 0.015 0.005 0.000 0.094 0.7222 0.015 0.005 0.000 0.094 0.7778 0.015 0.006 0.000 0.094 0.8333 0.015 0.006 0.000 0.094 0.8889 0.015 0.007 0.000 0.094 0.9444 0.015 0.007 0.000 0.094 1.0000 0.015 0.008 0.000 0.094 1.0556 0.015 0.008 0.000 0.094 1.1111 0.015 0.009 0.000 0.094 1.1667 0.015 0.010 0.000 0.094 1.2222 0.015 0.010 0.000 0.094 1.2778 0.015 0.011 0.000 0.094 JW301 WWHM 12/22/2022 11:18:03 AM Page 9 1.3333 0.015 0.011 0.000 0.094 1.3889 0.015 0.012 0.000 0.094 1.4444 0.015 0.012 0.000 0.094 1.5000 0.015 0.013 0.000 0.094 1.5556 0.015 0.014 0.000 0.094 1.6111 0.015 0.014 0.000 0.094 1.6667 0.015 0.015 0.000 0.094 1.7222 0.015 0.015 0.000 0.094 1.7778 0.015 0.016 0.000 0.094 1.8333 0.015 0.016 0.000 0.094 1.8889 0.015 0.017 0.000 0.094 1.9444 0.015 0.017 0.000 0.094 2.0000 0.015 0.018 0.000 0.094 2.0556 0.015 0.019 0.000 0.094 2.1111 0.015 0.019 0.000 0.094 2.1667 0.015 0.020 0.000 0.094 2.2222 0.015 0.020 0.000 0.094 2.2778 0.015 0.021 0.000 0.094 2.3333 0.015 0.021 0.000 0.094 2.3889 0.015 0.022 0.000 0.094 2.4444 0.015 0.023 0.000 0.094 2.5000 0.015 0.023 0.000 0.094 2.5556 0.015 0.024 0.000 0.094 2.6111 0.015 0.024 0.000 0.094 2.6667 0.015 0.025 0.000 0.094 2.7222 0.015 0.025 0.000 0.094 2.7778 0.015 0.026 0.000 0.094 2.8333 0.015 0.026 0.000 0.094 2.8889 0.015 0.027 0.000 0.094 2.9444 0.015 0.028 0.000 0.094 3.0000 0.015 0.028 0.000 0.094 3.0556 0.015 0.028 0.000 0.094 3.1111 0.015 0.029 0.000 0.094 3.1667 0.015 0.029 0.000 0.094 3.2222 0.015 0.030 0.000 0.094 3.2778 0.015 0.030 0.000 0.094 3.3333 0.015 0.030 0.000 0.094 3.3889 0.015 0.031 0.000 0.094 3.4444 0.015 0.031 0.000 0.094 3.5000 0.015 0.031 0.000 0.094 3.5556 0.015 0.032 0.000 0.094 3.6111 0.015 0.033 0.000 0.094 3.6667 0.015 0.034 0.000 0.094 3.7222 0.015 0.035 0.000 0.094 3.7778 0.015 0.036 0.000 0.094 3.8333 0.015 0.036 0.000 0.094 3.8889 0.015 0.037 0.000 0.094 3.9444 0.015 0.038 0.000 0.094 4.0000 0.015 0.039 0.000 0.094 4.0556 0.015 0.040 0.068 0.094 4.1111 0.015 0.041 0.184 0.094 4.1667 0.015 0.042 0.297 0.094 4.2222 0.015 0.042 0.369 0.094 4.2778 0.015 0.043 0.415 0.094 4.3333 0.015 0.044 0.454 0.094 4.3889 0.015 0.045 0.491 0.094 4.4444 0.015 0.046 0.524 0.094 4.5000 0.015 0.047 0.556 0.094 JW301 WWHM 12/22/2022 11:18:03 AM Page 10 4.5556 0.015 0.048 0.586 0.094 4.6111 0.015 0.049 0.615 0.094 4.6667 0.015 0.049 0.642 0.094 4.7222 0.015 0.050 0.669 0.094 4.7778 0.015 0.051 0.694 0.094 4.8333 0.015 0.052 0.718 0.094 4.8889 0.015 0.053 0.742 0.094 4.9444 0.015 0.054 0.765 0.094 5.0000 0.015 0.055 0.787 0.094 JW301 WWHM 12/22/2022 11:18:03 AM Page 11 Analysis Results POC 1 + Predeveloped x Mitigated Predeveloped Landuse Totals for POC #1 Total Pervious Area:0.389 Total Impervious Area:0 Mitigated Landuse Totals for POC #1 Total Pervious Area:0.1317 Total Impervious Area:0.2573 Flow Frequency Method:Log Pearson Type III 17B Flow Frequency Return Periods for Predeveloped. POC #1 Return Period Flow(cfs) 2 year 0.00059 5 year 0.001637 10 year 0.003019 25 year 0.006165 50 year 0.010122 100 year 0.016191 Flow Frequency Return Periods for Mitigated. POC #1 Return Period Flow(cfs) 2 year 0 5 year 0 10 year 0 25 year 0 50 year 0 100 year 0 Annual Peaks Annual Peaks for Predeveloped and Mitigated. POC #1 Year Predeveloped Mitigated 1956 0.002 0.000 1957 0.000 0.000 1958 0.000 0.000 1959 0.000 0.000 1960 0.000 0.000 1961 0.001 0.000 1962 0.000 0.000 1963 0.000 0.000 1964 0.000 0.000 1965 0.000 0.000 JW301 WWHM 12/22/2022 11:18:31 AM Page 12 1966 0.000 0.000 1967 0.001 0.000 1968 0.000 0.000 1969 0.000 0.000 1970 0.000 0.000 1971 0.003 0.000 1972 0.004 0.000 1973 0.000 0.000 1974 0.001 0.000 1975 0.000 0.000 1976 0.000 0.000 1977 0.000 0.000 1978 0.000 0.000 1979 0.000 0.000 1980 0.000 0.000 1981 0.001 0.000 1982 0.001 0.000 1983 0.000 0.000 1984 0.000 0.000 1985 0.000 0.000 1986 0.001 0.000 1987 0.001 0.000 1988 0.000 0.000 1989 0.000 0.000 1990 0.002 0.000 1991 0.003 0.000 1992 0.000 0.000 1993 0.000 0.000 1994 0.000 0.000 1995 0.002 0.000 1996 0.005 0.000 1997 0.003 0.000 1998 0.001 0.000 1999 0.000 0.000 2000 0.000 0.000 2001 0.000 0.000 2002 0.002 0.000 2003 0.000 0.000 2004 0.020 0.000 2005 0.003 0.000 2006 0.014 0.000 2007 0.006 0.000 2008 0.000 0.000 Ranked Annual Peaks Ranked Annual Peaks for Predeveloped and Mitigated. POC #1 Rank Predeveloped Mitigated 1 0.0197 0.0000 2 0.0142 0.0000 3 0.0061 0.0000 4 0.0047 0.0000 5 0.0041 0.0000 6 0.0034 0.0000 7 0.0032 0.0000 8 0.0031 0.0000 9 0.0025 0.0000 10 0.0022 0.0000 11 0.0020 0.0000 JW301 WWHM 12/22/2022 11:18:31 AM Page 13 12 0.0019 0.0000 13 0.0019 0.0000 14 0.0014 0.0000 15 0.0011 0.0000 16 0.0008 0.0000 17 0.0007 0.0000 18 0.0007 0.0000 19 0.0007 0.0000 20 0.0007 0.0000 21 0.0005 0.0000 22 0.0004 0.0000 23 0.0004 0.0000 24 0.0004 0.0000 25 0.0003 0.0000 26 0.0003 0.0000 27 0.0003 0.0000 28 0.0003 0.0000 29 0.0003 0.0000 30 0.0003 0.0000 31 0.0003 0.0000 32 0.0003 0.0000 33 0.0003 0.0000 34 0.0003 0.0000 35 0.0003 0.0000 36 0.0003 0.0000 37 0.0003 0.0000 38 0.0003 0.0000 39 0.0003 0.0000 40 0.0003 0.0000 41 0.0003 0.0000 42 0.0003 0.0000 43 0.0003 0.0000 44 0.0003 0.0000 45 0.0003 0.0000 46 0.0003 0.0000 47 0.0003 0.0000 48 0.0003 0.0000 49 0.0003 0.0000 50 0.0003 0.0000 51 0.0003 0.0000 52 0.0003 0.0000 53 0.0003 0.0000 JW301 WWHM 12/22/2022 11:18:31 AM Page 14 Duration Flows The Facility PASSED Flow(cfs)Predev Mit Percentage Pass/Fail 0.0003 687 0 0 Pass 0.0004 148 0 0 Pass 0.0005 120 0 0 Pass 0.0006 98 0 0 Pass 0.0007 80 0 0 Pass 0.0008 61 0 0 Pass 0.0009 51 0 0 Pass 0.0010 48 0 0 Pass 0.0011 44 0 0 Pass 0.0012 38 0 0 Pass 0.0013 37 0 0 Pass 0.0014 33 0 0 Pass 0.0015 32 0 0 Pass 0.0016 30 0 0 Pass 0.0017 29 0 0 Pass 0.0018 27 0 0 Pass 0.0019 26 0 0 Pass 0.0020 22 0 0 Pass 0.0021 19 0 0 Pass 0.0022 18 0 0 Pass 0.0023 16 0 0 Pass 0.0024 16 0 0 Pass 0.0025 14 0 0 Pass 0.0026 13 0 0 Pass 0.0027 11 0 0 Pass 0.0028 9 0 0 Pass 0.0029 9 0 0 Pass 0.0030 9 0 0 Pass 0.0031 9 0 0 Pass 0.0032 8 0 0 Pass 0.0033 6 0 0 Pass 0.0034 5 0 0 Pass 0.0035 5 0 0 Pass 0.0036 5 0 0 Pass 0.0037 5 0 0 Pass 0.0038 5 0 0 Pass 0.0039 5 0 0 Pass 0.0040 5 0 0 Pass 0.0041 5 0 0 Pass 0.0042 4 0 0 Pass 0.0043 4 0 0 Pass 0.0044 4 0 0 Pass 0.0045 4 0 0 Pass 0.0046 4 0 0 Pass 0.0047 4 0 0 Pass 0.0048 3 0 0 Pass 0.0049 3 0 0 Pass 0.0050 3 0 0 Pass 0.0051 3 0 0 Pass 0.0052 3 0 0 Pass 0.0053 3 0 0 Pass 0.0054 3 0 0 Pass 0.0055 3 0 0 Pass JW301 WWHM 12/22/2022 11:18:31 AM Page 15 0.0056 3 0 0 Pass 0.0057 3 0 0 Pass 0.0058 3 0 0 Pass 0.0059 3 0 0 Pass 0.0060 3 0 0 Pass 0.0061 3 0 0 Pass 0.0062 2 0 0 Pass 0.0063 2 0 0 Pass 0.0064 2 0 0 Pass 0.0064 2 0 0 Pass 0.0065 2 0 0 Pass 0.0066 2 0 0 Pass 0.0067 2 0 0 Pass 0.0068 2 0 0 Pass 0.0069 2 0 0 Pass 0.0070 2 0 0 Pass 0.0071 2 0 0 Pass 0.0072 2 0 0 Pass 0.0073 2 0 0 Pass 0.0074 2 0 0 Pass 0.0075 2 0 0 Pass 0.0076 2 0 0 Pass 0.0077 2 0 0 Pass 0.0078 2 0 0 Pass 0.0079 2 0 0 Pass 0.0080 2 0 0 Pass 0.0081 2 0 0 Pass 0.0082 2 0 0 Pass 0.0083 2 0 0 Pass 0.0084 2 0 0 Pass 0.0085 2 0 0 Pass 0.0086 2 0 0 Pass 0.0087 2 0 0 Pass 0.0088 2 0 0 Pass 0.0089 2 0 0 Pass 0.0090 2 0 0 Pass 0.0091 2 0 0 Pass 0.0092 2 0 0 Pass 0.0093 2 0 0 Pass 0.0094 2 0 0 Pass 0.0095 2 0 0 Pass 0.0096 2 0 0 Pass 0.0097 2 0 0 Pass 0.0098 2 0 0 Pass 0.0099 2 0 0 Pass 0.0100 2 0 0 Pass 0.0101 2 0 0 Pass JW301 WWHM 12/22/2022 11:18:31 AM Page 16 Water Quality Water Quality BMP Flow and Volume for POC #1 On-line facility volume:0 acre-feet On-line facility target flow:0 cfs. Adjusted for 15 min:0 cfs. Off-line facility target flow:0 cfs. Adjusted for 15 min:0 cfs. JW301 WWHM 12/22/2022 11:18:31 AM Page 17 LID Report JW301 WWHM 12/22/2022 11:19:00 AM Page 18 POC 2 + Predeveloped x Mitigated Predeveloped Landuse Totals for POC #2 Total Pervious Area:0.389 Total Impervious Area:0 Mitigated Landuse Totals for POC #2 Total Pervious Area:0.13 Total Impervious Area:0.223 Flow Frequency Method:Log Pearson Type III 17B Flow Frequency Return Periods for Predeveloped. POC #2 Return Period Flow(cfs) 2 year 0.00059 5 year 0.001637 10 year 0.003019 25 year 0.006165 50 year 0.010122 100 year 0.016191 Flow Frequency Return Periods for Mitigated. POC #2 Return Period Flow(cfs) 2 year 0.096911 5 year 0.137457 10 year 0.168846 25 year 0.214078 50 year 0.252087 100 year 0.294028 Annual Peaks Annual Peaks for Predeveloped and Mitigated. POC #2 Year Predeveloped Mitigated 1956 0.002 0.078 1957 0.000 0.154 1958 0.000 0.102 1959 0.000 0.095 1960 0.000 0.134 1961 0.001 0.069 1962 0.000 0.071 1963 0.000 0.140 1964 0.000 0.090 1965 0.000 0.101 1966 0.000 0.077 JW301 WWHM 12/22/2022 11:19:22 AM Page 19 1967 0.001 0.092 1968 0.000 0.058 1969 0.000 0.061 1970 0.000 0.072 1971 0.003 0.070 1972 0.004 0.095 1973 0.000 0.070 1974 0.001 0.142 1975 0.000 0.096 1976 0.000 0.082 1977 0.000 0.117 1978 0.000 0.095 1979 0.000 0.125 1980 0.000 0.071 1981 0.001 0.130 1982 0.001 0.095 1983 0.000 0.167 1984 0.000 0.095 1985 0.000 0.084 1986 0.001 0.117 1987 0.001 0.089 1988 0.000 0.049 1989 0.000 0.062 1990 0.002 0.283 1991 0.003 0.130 1992 0.000 0.092 1993 0.000 0.055 1994 0.000 0.088 1995 0.002 0.124 1996 0.005 0.113 1997 0.003 0.096 1998 0.001 0.150 1999 0.000 0.081 2000 0.000 0.093 2001 0.000 0.084 2002 0.002 0.100 2003 0.000 0.067 2004 0.020 0.263 2005 0.003 0.315 2006 0.014 0.152 2007 0.006 0.121 2008 0.000 0.153 Ranked Annual Peaks Ranked Annual Peaks for Predeveloped and Mitigated. POC #2 Rank Predeveloped Mitigated 1 0.0197 0.3150 2 0.0142 0.2830 3 0.0061 0.2632 4 0.0047 0.1670 5 0.0041 0.1535 6 0.0034 0.1528 7 0.0032 0.1516 8 0.0031 0.1500 9 0.0025 0.1422 10 0.0022 0.1395 11 0.0020 0.1338 12 0.0019 0.1299 JW301 WWHM 12/22/2022 11:19:22 AM Page 20 13 0.0019 0.1298 14 0.0014 0.1245 15 0.0011 0.1237 16 0.0008 0.1214 17 0.0007 0.1172 18 0.0007 0.1166 19 0.0007 0.1131 20 0.0007 0.1023 21 0.0005 0.1009 22 0.0004 0.0997 23 0.0004 0.0959 24 0.0004 0.0957 25 0.0003 0.0955 26 0.0003 0.0952 27 0.0003 0.0951 28 0.0003 0.0947 29 0.0003 0.0945 30 0.0003 0.0935 31 0.0003 0.0920 32 0.0003 0.0917 33 0.0003 0.0900 34 0.0003 0.0890 35 0.0003 0.0884 36 0.0003 0.0843 37 0.0003 0.0841 38 0.0003 0.0819 39 0.0003 0.0810 40 0.0003 0.0779 41 0.0003 0.0771 42 0.0003 0.0715 43 0.0003 0.0714 44 0.0003 0.0706 45 0.0003 0.0699 46 0.0003 0.0698 47 0.0003 0.0694 48 0.0003 0.0671 49 0.0003 0.0616 50 0.0003 0.0611 51 0.0003 0.0576 52 0.0003 0.0546 53 0.0003 0.0487 JW301 WWHM 12/22/2022 11:19:22 AM Page 21 Duration Flows Flow(cfs)Predev Mit Percentage Pass/Fail 0.0003 687 352736 51344 Fail 0.0004 148 329134 222387 Fail 0.0005 120 310363 258635 Fail 0.0006 98 295310 301336 Fail 0.0007 80 282301 352876 Fail 0.0008 61 271150 444508 Fail 0.0009 51 261114 511988 Fail 0.0010 48 252008 525016 Fail 0.0011 44 243830 554159 Fail 0.0012 38 236211 621607 Fail 0.0013 37 229520 620324 Fail 0.0014 33 222830 675242 Fail 0.0015 32 216883 677759 Fail 0.0016 30 211122 703740 Fail 0.0017 29 205918 710062 Fail 0.0018 27 200900 744074 Fail 0.0019 26 195882 753392 Fail 0.0020 22 191236 869254 Fail 0.0021 19 186961 984005 Fail 0.0022 18 182743 1015238 Fail 0.0023 16 178654 1116587 Fail 0.0024 16 174844 1092775 Fail 0.0025 14 171313 1223664 Fail 0.0026 13 167764 1290492 Fail 0.0027 11 164400 1494545 Fail 0.0028 9 161185 1790944 Fail 0.0029 9 158174 1757488 Fail 0.0030 9 155293 1725477 Fail 0.0031 9 152357 1692855 Fail 0.0032 8 149495 1868687 Fail 0.0033 6 146707 2445116 Fail 0.0034 5 144087 2881740 Fail 0.0035 5 141522 2830440 Fail 0.0036 5 139087 2781740 Fail 0.0037 5 136616 2732320 Fail 0.0038 5 134181 2683620 Fail 0.0039 5 131839 2636780 Fail 0.0040 5 129516 2590320 Fail 0.0041 5 127361 2547220 Fail 0.0042 4 125205 3130125 Fail 0.0043 4 123105 3077625 Fail 0.0044 4 121060 3026500 Fail 0.0045 4 119146 2978650 Fail 0.0046 4 117139 2928475 Fail 0.0047 4 115188 2879700 Fail 0.0048 3 113329 3777633 Fail 0.0049 3 111508 3716933 Fail 0.0050 3 109724 3657466 Fail 0.0051 3 108051 3601700 Fail 0.0052 3 106360 3545333 Fail 0.0053 3 104706 3490200 Fail 0.0054 3 103145 3438166 Fail 0.0055 3 101584 3386133 Fail 0.0056 3 100078 3335933 Fail JW301 WWHM 12/22/2022 11:19:22 AM Page 22 0.0057 3 98554 3285133 Fail 0.0058 3 97123 3237433 Fail 0.0059 3 95711 3190366 Fail 0.0060 3 94261 3142033 Fail 0.0061 3 92905 3096833 Fail 0.0062 2 91585 4579250 Fail 0.0063 2 90321 4516050 Fail 0.0064 2 89076 4453800 Fail 0.0064 2 87831 4391550 Fail 0.0065 2 86549 4327450 Fail 0.0066 2 85303 4265150 Fail 0.0067 2 84114 4205700 Fail 0.0068 2 82980 4149000 Fail 0.0069 2 81791 4089550 Fail 0.0070 2 80657 4032850 Fail 0.0071 2 79542 3977100 Fail 0.0072 2 78427 3921350 Fail 0.0073 2 77331 3866550 Fail 0.0074 2 76290 3814500 Fail 0.0075 2 75212 3760600 Fail 0.0076 2 74227 3711350 Fail 0.0077 2 73242 3662100 Fail 0.0078 2 72257 3612850 Fail 0.0079 2 71309 3565450 Fail 0.0080 2 70417 3520850 Fail 0.0081 2 69525 3476250 Fail 0.0082 2 68614 3430700 Fail 0.0083 2 67741 3387050 Fail 0.0084 2 66812 3340600 Fail 0.0085 2 65957 3297850 Fail 0.0086 2 65102 3255100 Fail 0.0087 2 64266 3213300 Fail 0.0088 2 63485 3174250 Fail 0.0089 2 62705 3135250 Fail 0.0090 2 61887 3094350 Fail 0.0091 2 61088 3054400 Fail 0.0092 2 60363 3018150 Fail 0.0093 2 59564 2978200 Fail 0.0094 2 58802 2940100 Fail 0.0095 2 58077 2903850 Fail 0.0096 2 57352 2867600 Fail 0.0097 2 56627 2831350 Fail 0.0098 2 55903 2795150 Fail 0.0099 2 55215 2760750 Fail 0.0100 2 54546 2727300 Fail 0.0101 2 53895 2694750 Fail The development has an increase in flow durations from 1/2 Predeveloped 2 year flow to the 2 year flow or more than a 10% increase from the 2 year to the 50 year flow. The development has an increase in flow durations for more than 50% of the flows for the range of the duration analysis. JW301 WWHM 12/22/2022 11:19:22 AM Page 23 Water Quality Water Quality BMP Flow and Volume for POC #2 On-line facility volume:0.0328 acre-feet On-line facility target flow:0.039 cfs. Adjusted for 15 min:0.039 cfs. Off-line facility target flow:0.0221 cfs. Adjusted for 15 min:0.0221 cfs. JW301 WWHM 12/22/2022 11:19:22 AM Page 24 LID Report JW301 WWHM 12/22/2022 11:19:22 AM Page 25 Model Default Modifications Total of 0 changes have been made. PERLND Changes No PERLND changes have been made. IMPLND Changes No IMPLND changes have been made. JW301 WWHM 12/22/2022 11:19:22 AM Page 26 Appendix Predeveloped Schematic JW301 WWHM 12/22/2022 11:19:23 AM Page 27 Mitigated Schematic Appendix D 1001 Cooper Point Rd SW, STE 140 PMB 108 | Olympia, WA 98502 | 360.481.9784 | CHeathman@MudBayGeotech.com December 18, 2022 Job: 2102-THU Page 1 Subject: Stormwater Infiltration Geotechnical Report 313 Yelm Ave W, Yelm, WA 98597 Parcel # 75300900100 Dear Jennifer Wentworth, This report presents the results of our geotechnical investigation and contains stormwater infiltration rate recommendations for the site development project located at 313 Yelm Ave W in Yelm, Washington. The analyses, conclusions, and recommendations in this report are based on the information available. These informational resources include: one (1) excavated test pit and one (1) small pilot infiltration test (Small PIT) completed specifically for the subject project, as well as published geologic information for the site and vicinity and our experience with similar geologic materials. The conditions observed in the exploration are assumed to be representative of the subsurface conditions throughout the project area. If during construction, subsurface conditions differ from those described in the exploration, we should be advised immediately so that we may reevaluate our recommendations and provide further assistance. SITE CONDITIONS AND PROJECT DESCRIPTION Parcel # 75300900100 consists of a total of 0.28 acres in Yelm, Washington. The parcel location has been given the situs address of 313 Yelm Ave W, and is identified on the Site Location Map included as Figure 1 attached to this report. The property is located off the southwestern side of Yelm Ave W, and can be accessed via a paved driveway along the northeastern margin of the subject parcel. The site can also be accessed via a gravel alleyway parallel to the southwestern 2 102-T H U : 3 1 3 Y e l m A v e W , Y e l m WA 9 8 5 9 7 P a g e |2 parcel boundary, and from a gravel driveway off of Rice St SW. The site is currently being re- developed with a renovated two-story structure, detached two-car garage, and an associated paved parking area. Several large cedar trees exist across the parcel. The property consists of a generally flat topography, along with the surrounding region. The purpose of this report is to provide subsurface conditions and geotechnical recommendations in regards to stormwater design within the subject parcel. The scope of the project is to re-develop the parcel with a renovated two-story structure and garage along with an associated paved parking area. A proposed site plan has not been provided and is currently unavailable at the time of this report. Stormwater infiltration facilities are proposed as a flow control and treatment BMP for the new impervious surface generated as part of the development. The parcel is located within the jurisdiction of the City of Yelm; therefore, the stormwater and infiltration design requirements of the Department of Ecology’s 2019 Stormwater Management Manual for Western Washington must be satisfied. To meet the requirements for that method, we performed one (1) Small PIT to characterize the infiltration rate of the site soils. This infiltration test was performed within the upper ~2 to 3 feet based on the assumption shallow infiltration trenches, basins, swales, or rock galleries will be used for treatment and flow control. SITE GEOLOGY AND SOILS As part of this project, we reviewed available geologic data and prepared a site-specific geologic map. The project vicinity geologic map is attached as Figure 2, WA DNR Geologic Map. This figure indicates the project vicinity consists of Pleistocene continental glacial drift. The DNR describes these deposits as follows: Recessional and proglacial, stratified pebble, cobble, and boulder gravel deposited in meltwater streams and their deltas; locally contains ice-contact deposits. Conditions observed at the site are generally consistent with the mapped geology at the site. In addition to the site geology, site-specific soil data made available by the United States Department of Agriculture was consulted. The USDA Soil Map is attached to this report as Figure 3. This figure suggests that the parcel is underlain by No. 110 – Spanaway gravelly sandy loam, 0 to 3 percent slopes. The USDA classifies the Spanaway series as follows: a somewhat excessively draining, gravelly sandy loam to extremely gravelly sand sourced from volcanic ash over gravelly outwash and deposited over terraces and outwash plains. The soils observed in- situ are generally consistent with the mapped soils on-site. It should be noted that the slope percentages displayed on the map are estimates and do not necessarily reflect true surface topography. 2 102-T H U : 3 1 3 Y e l m A v e W , Y e l m WA 9 8 5 9 7 P a g e |3 SUBSURFACE EXPLORATION To characterize the surface and subsurface conditions, Mud Bay Geotechnical Services, LLC performed one (1) excavated test pit. This test pit was designated ITP-1-22, and was completed on October 5, 2022. The excavated test pit was completed from the existing ground surface at the approximate location shown on Figure 4, Site Exploration Map. The test pit was completed using a Kubota KX040-0 compact excavator with Mud Bay Geotechnical Services, LLC personnel onsite to perform and observe excavation, log the soils encountered in the pit and collect samples. The soil samples were classified visually in the field in general accordance with ASTM D2488, the Standard Practice for Description and Identification of Soils (Visual-Manual Procedure). Once transported back to the office, the samples were re-examined, and the field classifications were modified accordingly. A summary log of the excavated test pit is included in Appendix A. Note the soil descriptions and interfaces shown on the log is interpretive, and actual changes may be gradual. Upon completion, the test pit was backfilled to the original ground surface using excavated material from the spoil piles. SUBSURFACE SOIL AND GROUNDWATER CONDITIONS Findings in the excavated test pit suggest the subsurface consists of approximately: an upper 6- inches of moist, grey, crushed surfacing base coarse (CSBC), underlain by a moist, brown, silty sand with gravel (SM) to a depth of 24-inches. Immediately below this was a final unit of moist, tan, well-graded sand with silt and gravel (SW-SM) encountered to a depth of 84-inches below ground surface. This final SW-SM soil unit appeared to be fairly compact as harder digging condition were encountered, and is interpreted as native undisturbed glacial drift deposits. The excavated test pit performed is assumed to be representative of the project area subsurface conditions, however, the true nature of glacial deposits can be difficult to ascertain as they are highly variable units. If conditions vary significantly during construction, we should be contacted to reassess the recommendations included in this report. Groundwater was not encountered during our subsurface exploration of the site on October 5, 2022. As a part of this project, well logs made available by the Washington State Department of Ecology for the surrounding region were consulted. These well logs suggest that the depth to groundwater in the area surrounding the subject property is greater than 20-feet below ground surface and will not be encountered within the excepted limits of construction excavation. 2 102-T H U : 3 1 3 Y e l m A v e W , Y e l m WA 9 8 5 9 7 P a g e |4 FIELD MEASURED INFILTRATION TESTING As part of the geotechnical investigation, a site reconnaissance and subsurface investigation was performed on October 5, 2022, and a total of (1) one small pilot infiltration test (PIT) was completed. This test pit, designated ITP-1-22 was excavated the day of testing to a depth near the bottom of the proposed infiltration facility. A summary of the infiltration testing geometry for the Small PIT is provided in Table 1 below. Table 1: Small PIT Geometry Small PIT Depth (in.) Top Width (in.) Top Length (in.) Basal Width (in.) Basal Length (in.) ITP-1-22 24 48 80 36 48 The infiltration testing was performed on October 5, 2022 following the general guidelines established by the Department of Ecology’s 2019 Stormwater Management Manual for Western Washington. A vertical measuring stick of 3 ft height was placed within the center of the test pit to provide measurements within ½” accuracy. The measuring stick was embedded a depth of 4 to 6 inches into the infiltration subgrade to maintain stability during the testing. Water was introduced into the pit using a garden hose. The bottom surface and sides of the pit were protected with a geotextile fabric to reduce the potential for erosion and turbidity. The water was poured into the pit near the original ground surface. After the pit was initially filled to a minimum depth of 12 inches, water was introduced to the pit at a rate to maintain a water level of at least 12 inches above the base of the pit during the 6-hour pre-soak period. The depth of water was recorded at selected times during this period. A summary of the water level measurements is presented in Table 2. Table 2: Pre -Soak Water Level Measurements Approximate Time ITP-1-22 (in.) 8:20 12.0 9:20 13.0 10:20 12.0 11:20 11.5 12:20 12.0 13:20 12.0 14:20 12.0 The six-hour pre-soak period was concluded by one hour of steady state instantaneous flow measurements. Cumulative volume and instantaneous flow rates (gallons/minute) were recorded at time intervals of 15 minutes while attempting to maintain a stable water depth of 12 inches. The 2 102-T H U : 3 1 3 Y e l m A v e W , Y e l m WA 9 8 5 9 7 P a g e |5 instantaneous flow measurements were performed using a stopwatch and recording the time required to fill up one gallon with water. The water flow rate was adjusted slightly in between flow rate measurements to maintain as close to a steady state head of 12 inches in the pit as possible. A summary of results from the one-hour steady state period are presented in Table 3. Table 3: I TP-1-22 Steady State Measurements ITP-1-21 Water Depth (in.) Flow Rate (gal/min.) Cumulative Volume (gal) Infiltration Rate (in./hr.) 14:30 12.0 ------ ----- ----- 14:45 12.0 1.94 29.03 15.52 15:00 12.0 1.92 57.88 15.42 15:15 12.0 1.94 86.91 15.52 15:30 12.0 1.91 115.57 15.33 Water was then shut off to perform the falling head portion of the testing and an infiltration rate (inches/hour) was recorded at 15-minute increments for a period of one hour. Results from the falling head portion of the testing are presented in Table 4. Table 4: I TP-1-22 Falling Head Measurements Approximate Time Water Depth (in.) Infiltration Rate (in./hr.) 15:30 12.0 ----- 15:45 9.0 12.0 16:00 6.0 12.0 16:15 3.0 12.0 16:30 0.0 12.0 After the falling head period was concluded, the pit was excavated below the bottom of the infiltration pit to investigate the infiltrating soil conditions, to observe the depth of saturation, to look for natural groundwater, and to look for a non-infiltrating hardpan. The immediate underlying soil conditions consisted of moist, tan, well-graded sand with silt and gravel (SW-SM). Mottling was absent within the unit and the induration of the sediment was noted to be moderately indurated. A glacial hardpan layer was encountered at approximately 78-inches below ground surface in the subject parcel. This unit was comprised of a moist, tan, well-graded sand with silt and gravel (SW-SM), and was noted to be highly indurated with large cobbles and boulders. Groundwater seepage was observed horizontally at the geologic contact between the upper less dense and underlying dense SW-SM soil unit from the previous infiltration testing. We interpret the looser overlying SW-SM as native glacial outwash, exhibiting well-draining soil 2 102-T H U : 3 1 3 Y e l m A v e W , Y e l m WA 9 8 5 9 7 P a g e |6 characteristics.The excavation beyond the base of the test pit appears to indicate that any surface water will infiltrate vertically through the overlying less compacted glacial outwash before encountering the underlying, glacially overridden till where it will then travel horizontally along the unit contact boundary. GEOLOGIC HAZARD ASSESSMENT Liquefaction Susceptibility A map of liquefaction susceptibility developed by the Department of Natural Resources is attached as Figure 5, Liquefaction Hazard Map. Soil liquefaction is a phenomenon whereby saturated soil deposits temporarily lose strength and behave as a viscous fluid in response to cyclic loading. These behaviors are most common in saturated, loose, sandy soils with lesser impacts occurring in silty soils. Figure 5 indicates that the glacial deposits mapped across the parcel are at very low risk of soil liquefaction, and MBGS concurs with this assessment. Landslide Hazard We performed a cursory review of the available online site information to determine the potential for landslide hazards at the site. The Landslide Map available from the Washington State Department of Natural Resources revealed no mapped landslide deposits near the project vicinity. No indications of deep-seated landslide activity, past or present, were observed during our on- site investigation nor during our review of online resources. It is our interpretation that the site is underlain by competent glacial material at a relatively shallow depth. The landslide hazard map has been omitted from this report. The geomorphology (shape of the land) was analyzed during the site evaluation and compared to the Light Detection and Ranging images (LiDAR) from the Washington State LiDAR portal. LiDAR is a remote sensing method were light is pulsed down to the surface of the Earth and back to a sensor. This methodology enables bare earth images of the surface to be analyzed for the presence of geologic landforms. The most recent available LiDAR imagery of this site is included as Figure 6 attached to this report, WA DNR LiDAR Map. The bare earth imagery highlights the gently graded topography of the parcel and surrounding region, along with urban grading activities. We conclude the onsite landslide hazard risk to be very low. 2 102-T H U : 3 1 3 Y e l m A v e W , Y e l m WA 9 8 5 9 7 P a g e |7 GEOTECHNICAL RECOMMENDATIONS Stormwater Infiltration Using the infiltration data collected during the steady state and the falling head infiltration testing, a base rate of approximately 12.0 inches per hour was determined based on the average infiltration rate recorded during the Small PIT. A correction factor of 0.5 was applied to this value to determine the final recommended design infiltration rate of 6 inches per hour, which should be used in the design of infiltration facilities at the site. This correction factor assumes a moderate amount of maintenance over the lifetime of the infiltration facility. Based on the infiltration rates within the Small PIT, onsite soil conditions, and our experience with similar geologic conditions, we conclude that the site is well-draining, and that on-site infiltration is feasible. RECOMMENDED ADDITIONAL SERVICES Before construction begins, we recommend a copy of the draft plans and specifications prepared for the project are made available for review so that we can ensure that the geotechnical recommendations in this report are included in the Contract. Mud Bay Geotechnical Services, LLC is also available to provide geotechnical engineering and construction monitoring services throughout the remainder of the design and construction of the project. The integrity of the geotechnical elements of a project depend on proper site preparation and construction procedures. In addition, engineering decisions may need to be made in the field if conditions are encountered that differ from those described in this report. During the construction phase of the project, we recommend that Mud Bay Geotechnical Services, LLC be retained to review construction proposals and submittals, excavation and fill placement, drainage installation, foundation subgrade preparation, and provide recommendations for any other geotechnical considerations that may arise during construction. INTENDED USE AND LIMITATIONS This report was prepared based on observations of the surface and subsurface conditions at the site, review of geology and other information available for the site, and conversations with the property owner about the soil and surface water conditions on the property and the nature of the proposed development. The geotechnical recommendations in this report are based on the current site conditions and understanding of the proposed development as described previously. Any modification of the current property conditions or the nature of the proposed development beyond what is described in this report would render these geotechnical recommendations invalid. 2 102-T H U : 3 1 3 Y e l m A v e W , Y e l m WA 9 8 5 9 7 P a g e |8 It should not be used, in part or in whole for other purposes without contacting Mud Bay Geotechnical Services, LLC for a review of the applicability of such reuse. We have enjoyed the opportunity to work with you and serve your geotechnical needs for the permitting phase of this project. Please contact me at your earliest convenience if you have any questions or would like to discuss any of the content of this report. Sincerely, Chris Heathman, P.E. Mud Bay Geotechnical Services, LLC Legend Approximate Site Location Figure 1: Site Map 313 Yelm Ave W, Yelm, WA 98597 Infiltration - Geotechnical Report JOB #: 2102-THU Date: Dec. 2022 Approximate Parcel Boundary Legend Figure 2: WA DNR Geologic Map 313 Yelm Ave W, Yelm, WA 98597 Infiltration - Geotechnical Report JOB #: 2102-THU Date: Dec. 2022 Geologic Units 100k Pleistocene continental glacial drift Sources: Esri, USGS | WA State Parks GIS, Esri, HERE, Garmin, FAO, NOAA, USGS, Bureau of Land Management, EPA, NPS | Washington Geological Survey, 2019, Surface geology, 1:24,000--GIS data, November 2019: Washington Geological Survey Digital Data Series DS-10, version 3.1. N Approximate Parcel Boundary Legend Figure 3: USDA Soil Map 313 Yelm Ave W, Yelm, WA 98597 Infiltration - Geotechnical Report JOB #: 2102-THU Date: Dec. 2022 Approximate Parcel Boundary Legend Approximate Test Pit Location ITP-1-22 Figure 4: Site Exploration Map 313 Yelm Ave W, Yelm, WA 98597 Infiltration - Geotechnical Report JOB #: 2102-THU Date: Dec. 2022 Approximate Parcel Boundary Figure 5: Liquefaction Hazard Map 313 Yelm Ave W, Yelm, WA 98597 Infiltration - Geotechnical Report JOB #: 2102-THU Date: Dec. 2022 Legend Approximate Parcel Boundary Liquefaction Susceptibility Moderate Low to Moderate Moderate to High Low High Very Low to Low Very Low Bedrock Peat Sources: Esri, USGS | WA State Parks GIS, Esri, HERE, Garmin, FAO, NOAA, USGS, Bureau of Land Management, EPA, NPS | Palmer, Stephen P.; Magsino, Sammantha L.; Bilderback, Eric L.; Poelstra, James L.; Folger, Derek S.; Niggemann, Rebecca A., 2007, Liquefaction susceptibility and site class maps of Washington State, by county: Washington Division of Geology and Earth Resources Open File Report 2004-20, [78 plates, 45 p. text]. N Figure 6: WA DNR LiDAR Map 313 Yelm Ave W, Yelm, WA 98597 Infiltration - Geotechnical Report JOB #: 2102-THU Date: Dec. 2022 Sources: Esri, USGS | WA State Parks GIS, Esri, HERE, Garmin, FAO, NOAA, USGS, Bureau of Land Management, EPA, NPS | Washington Geological Survey N Legend Approximate Parcel Boundary APPENDIX A – FINAL TEST PIT LOGS Completed:Hammer Type: Hammer Weight: Groundwater Depth: Lithology Moist, grey, crushed surfacing base coarse (CSBS). Transition: Moist, brown, silty sand with gravel (SM). Transition: Moist, tan, well-graded sand with silt and gravel (SW-SM). Moist, tan, well-graded sand with silt and gravel (SW-SM). Base of Small PIT 24". Continued excavation after testing. Very hard digging encountered. Water seepage from sidewalls of pit. Grain size increasing with depth. Cobbles and boulders 2+ feet in size. Interpreted as glacial drift hardpan. Test pit terminated. Test Pit and Boring Log Symbols Standard Penetration Slit Spoon Sampler (SPT) California Sampler Blows/3/4"Density Shelby Tube 0-4 Very Loose CPP Sampler 5-10 Loose StabIlized Ground water 11-24 Medium Dense Groundwater At time of Drilling 25-50 Dense Bulk/ Bag Sample REF Very Dense Helper:Elevation: n/a n/a Fluid: Backfilled: Total Depth of Test Pit: Address:DateStarted:Bit Type:Diameter: 313 Yelm Ave W, Yelm, WA 98597 10/5/2022 10/5/2022 n/a n/a Logged By: Hannah Anderson 10/5/2022 n/a n/a Hammer Drop: Project:Client:Test Pit No. 1 of 1: Stormwater Infiltration Jennifer Wentworth ITP-1-22 Project Number: Contractor: Equipment: 2102-THU Keystone Masonry INC.Kubota KX040-4 Tim Gollan n/a Existing Surface 84 inches Depth (in.)Sample TypeSample NumberBlow Counts (blows/3/4")Graphic LogDry Density (pcf)Moisture Content (%)Additional TestSoil Group Name: modifier, color, moisture, density/consistency, grain size, other descriptors Rock Description: modifier, color, hardness/degree of concentration, bedding and joint characteristics, solutions, void conditions. GPS Method: n/a >60 Very Hard 5-8 Medium Stiff 9-15 Stiff 16-30 Very Stiff 31-60 Hard GPS Coordinates: (± __ ft.) GPS Elevation: (± __ ft.) 2-4 Soft Soil Density Modifiers Blows/3/4"Consistency 0-1 Very Soft Gravel, Sand, Non-Plastic Silt Elastic Silts and Clays Moist, tan, well-graded sand with silt and gravel (SW-SM). 24"S-1 78'' n/a 48'' 84'' S-2 n/a Appendix E 5 configuration of the BayFilter maximizes a media filter’s area potential. The particle size of the media is also important with respect to pollutant interception and adsorption. A tightly packed, fine media (fig 2) captures a greater percentage of fine and dissolved pollutants when compared to a loosely packed, coarse media or a membrane media. A fine and tightly packed media not only minimizes the interstitial spaces between the media particles to optimize interception of pollutants, it also maximizes the amount of surface area in a given volume provided by the media for ion exchange. The quantity of sediment a filter is capable of capturing is a significant component to filter longevity. A filter must be able to treat large quantities of sediment while maintaining claimed flow rates and removal efficiencies. The sediment loading capacity of the BayFilter is 350 pounds (158.7 kg) for the 45 gpm (170.3 lpm) and 30 gpm (113.6 lpm) cartridges. Surface area and loading rate contribute significantly to filter longevity. Greater filter surface area (sf) allows for a reduced loading rate (gpm/sf of filter media), which in turn increases the service life of the filter. For example, a 10 square foot (0.9 m2) filter with a loading rate of 1 GPM (3.8 l/min) per square foot of filter area will pass 10 GPM (37.9 l/min). A 20 ft2 filter with a loading rate of 0.5 GPM (1.9 l/min) per square foot of filter area will also pass 10 GPM (37.9 l/min). If one gallon of treated water will occlude one square foot of filter area every 10 days, a 10 ft2 (0.9 m2) filter flowing at one GPM (3.8 l/min) will be expired in 100 days. A 20 ft2 (1.9 m 2) filter flowing at 0.5 GPM (1.9 l/min) will be expired in 400 days. Increasing media area and reducing flow rate has a beneficial impact on pollutant removal and filter longevity and these are some of the core engineering principles on which the BayFilter design is based. BaySaver Technologies is committed to the purpose of protecting public waterways. Permanently capturing pollutants, effectively backwashing media, allowing media to drain between storm events, and providing an economically reasonable maintenance interval are key design parameters for properly functioning stormwater filtration systems. The BayFilter cartridge system helps meet and exceed these key requirements needed to protect our water resources. Bottom of Cartridge Top of Cartridge Appendix F 1 Wentworth Commercial Development Construction Stormwater Pollution Prevention Plan Date of Preparation 11/5/22 Project Location 313 Yelm Ave W Yelm, WA 98597 Thurston County TPN: 75300900100 Applicant/Owner Jennifer Wentworth wentworthje@gmail.com Project engineer Nicholas Taylor, PE Iris Group PLLC (360) 890-8955 ntaylor@irisgroupconsulting.com Contractor/Contact Steve Borman 253-405-6206 steveb@keystonemasonryinc.com 2 Project Engineer’s Certification: "I hereby state that this Construction SWPPP for the Wentworth Commercial Development has been prepared by me or under my supervision and meets the standard of care and expertise which is usual and customary in this community for professional engineers. I understand that the City of Yelm does not and will not assume liability for the sufficiency, suitability, or performance of drainage facilities prepared by me." 11/5/2022 3 Contents Project Description .............................................................................................................................................. 4 Existing Site Conditions ...................................................................................................................................... 4 Soils ..................................................................................................................................................................... 4 Critical Areas ..................................................................................................................................................... 4 Existing Encumbrances .................................................................................................................................. 4 13 Elements of Construction Stormwater Pollution Prevention .............................................................. 4 Inspections ............................................................................................................................................................ 7 4 Project Description The project proposes construction of a parking lot, sidewalk, and stormwater system for a commercial development as depicted on the Stormwater Site Plan, Attachment A. The site is a 0.28-acre parcel. The project proposes 1,261 SF of new hard surface, and 14,562 SF of disturbed area. Existing Site Conditions The site is generally rectangular in shape, with all onsite surfaces sloping down toward the western corner of the site. The site functions as a pothole. Two building structures exist on the site, with paved parking space for 1 or 2 vehicles. The total topographic relief across the site is on the order of 2’ feet Soils The USDA Natural Resource Conservation Service (NRCS) Web Soil Survey maps the site as being underlain by Spanaway gravelly sandy loam, 0 to 3 percent slopes (hydrologic soils group A). Critical Areas No critical areas have been identified onsite. Existing Encumbrances There are no known existing encumbrances affecting the site. 13 Elements of Construction Stormwater Pollution Prevention 1. Preserve Vegetation/Mark Clearing Limits a. Clearly mark limits of disturbance with high visibility flagging. 2. Establish Construction Access a. Utilize only the existing paved driveway for construction access in accordance with the Stormwater Site Plan. b. If sediment is tracked off site, clean the affected roadway thoroughly at the end of each day, or more frequently as necessary (for example during wet weather) to prevent sediment from entering waters of the state. Remove sediment from roads by shoveling or pickup sweeping and transport to a controlled sediment disposal area. Street washing is allowed only after sediment is removed in this manner. 3. Control Flow Rates a. Ensure that runoff from all disturbed surfaces is directed only to the existing on- site pothole, which is where all site runoff flows to in the existing condition. The TESC plan assumes no offsite discharge. 4. Install Sediment Controls a. Sediment controls will include inlet protection. 5. Stabilize Soils a. Use mulch to stabilize all exposed and un-worked soils; protect the soil from the erosive forces of raindrop impact, flowing water, and wind. 5 b. From October 1 through April 30, no soils shall remain exposed and un-worked for more than 2 days. From May 1 to September 30, no soils shall remain exposed and un-worked for more than 7 days. This condition applies to all soils on site, whether at final grade or not. c. Stabilize soils with mulch at the end of the shift before a holiday or weekend if the weather forecast calls for precipitation. d. Minimize the amount of soil exposed during construction activity. e. Minimize soil compaction and, unless infeasible, preserve topsoil. f. Permanently stabilize soils using the soil quality and depth BMP included in the Stormwater Site Plan. 6. Protect Slopes a. There are no proposed or existing slopes that require protection. No slopes greater than 3:1 shall be created permanently or temporarily during construction. 7. Protect Drain Inlets a. Inlet protection shall be installed and maintained at the proposed Perk Filter catch basin. 8. Stabilize Channels and Outlets a. There are no proposed channels or outlets that require stabilization. 9. Control Pollutants a. Handle and dispose all pollutants, including waste materials and demolition debris that occur on-site, in a manner that does not cause contamination of stormwater. Woody debris may be chipped, ground, or chopped and spread on site. b. Provide cover, containment, and protection from vandalism for all chemicals, liquid products, petroleum products, and other materials that have the potential to pose a threat to human health or the environment. On-site fueling tanks shall include secondary containment. Secondary containment means placing tanks or containers within an impervious structure capable of containing 110% of the volume contained in the largest tank within the containment structure. Doublewalled tanks do not require additional secondary containment. c. Use spill prevention and control measures when conducting fueling, maintenance and repair of heavy equipment and vehicles including oil changes, hydraulic system drain down, solvent and de-greasing cleaning operations, fuel tank drain down and removal, and other activities which may result in discharge or spillage of pollutants to the ground or into stormwater runoff. Clean contaminated surfaces immediately following any discharge or spill incident. Emergency repairs may be performed on-site using temporary plastic placed beneath and, if raining, over the vehicle. d. Apply agricultural chemicals, including fertilizers and pesticides, in a manner and at application rates that will not result in loss of chemical to stormwater runoff. 6 Follow manufacturers’ recommendations for application rates and procedures shall be followed. e. Washout of concrete trucks shall be performed off-site or in designated concrete washout areas only. Do not wash out concrete trucks onto the ground, or into storm drains, open ditches, streets, or streams. Do not dump excess concrete on site, except in designated concrete washout areas. Concrete spillage or concrete discharge to surface waters of the State if prohibited. Do not use upland land applications for discharging wastewater from concrete washout areas. 10. Control De-Watering a. There are no proposed de-watering activities. If de-watering becomes necessary, contact project engineer for direction prior to proceeding with de- watering activities. 11. Maintain BMPs a. Maintain and repair all temporary and permanent erosion and sediment control BMPs as needed to assure continued performance of their intended function. Conduct maintenance and repair in accordance with BMP specifications. b. Remove all temporary erosion and sediment control BMPs not designed to remain in place following construction within 30 days after final site stabilization is achieved or after the temporary BMPs are no longer needed. c. Permanently stabilize disturbed soil resulting from removal of BMPs or vegetation. Protect all BMPs installed for the permanent control of stormwater from sediment and compaction. All BMPs that are to remain in place following completion of construction shall be examined and placed in full operating condition. If sediment enters the BMPs during construction, it shall be removed and the facility shall be returned to the conditions specified in the construction documents. 12. Manage the Project Phasing of Construction a. Phase development project and take into account seasonal work limits in order to prevent soil erosion and, to reduce to the maximum extent practicable, the transport of sediment from the site during construction. b. All BMPs shall be inspected, maintained, and repaired as needed to assure continued performance of their intended function. Site inspections shall be conducted at least weekly and immediately following any substantial rainfall event by a person who is knowledgeable in the principles and practices of erosion and sediment control. The inspector must have the skills to assess the site conditions and construction activities that could impact the quality of stormwater, and assess the effectiveness of erosion and sediment control measures used to control the quality of stormwater discharges. c. The inspector must examine stormwater visually for the presence of suspended sediment, turbidity, discoloration, and oil sheen. They must evaluate the effectiveness of BMPs and determine if it is necessary to install, maintain, or repair BMPs to improve the quality of stormwater discharges. 7 d. Implement appropriate BMPs or design changes as soon as possible whenever inspection and/or monitoring reveals that the BMPs identified in the Construction SWPPP are inadequate, due to the actual discharge of or potential to discharge a significant amount of any pollutant. e. Based on the results of the inspection, construction site operators must correct the problems identified by: i. Reviewing the SWPPP for compliance with the 13 construction SWPPP elements and making appropriate revisions within 7 days of the inspection. ii. Immediately beginning the process of fully implementing and maintaining appropriate source control and/or treatment BMPs as soon as possible, addressing the problems no later than within 10 days of the inspection. If installation of necessary treatment BMPs is not feasible within 10 days, the construction site operator may request and extension from the County within the initial 10-day response period. iii. Documenting BMP implementation and maintenance in the site log book. iv. The inspector must inspect all areas disturbed by construction activities, all BMPs, and all stormwater discharge points at least once every calendar week and within 24 hours of any discharge from the site. (For purposes of this condition, individual discharge events that last more than one day do not require daily inspections. For example, if a stormwater pond discharges continuously over the course of a week, only one inspection is required that week). The inspector may reduce the inspection frequency for temporarily stabilized, inactive sites to once every calendar month. v. The Construction SWPPP shall be retained on-site or within reasonable access to the site. vi. The SWPPP shall be modified whenever there is a change in the design, construction, operation, or maintenance at the construction site that has, or could have, a significant effect on the discharge of pollutants to waters of the state. vii. The SWPPP shall be modified if, during inspections or investigations conducted by the owner/operator, Pierce County or a state regulatory authority, it is determined that the SWPPP is ineffective in eliminating or significantly minimizing pollutants in stormwater discharges from the site. The SWPPP shall be modified as necessary to include additional or modified BMPs designed to correct problems identified. Revisions to the SWPPP shall be completed within seven (7) days following the inspection. 13. Protect Low Impact Development BMPs a. There are no proposed LID BMPs Inspections 8 As the project does not propose a discharge to waters of the state, site inspections shall be conducted by a person who is knowledgeable in the principles and practices of erosion and sediment control. Inspections shall conform to the guidelines provided under Element #12 above. Attachment A Stormwater Site Plan w/ SWPPP Elements WWWWWWWWWWWWWWWWWWW W W W W W W W W W W W W W W W W W W W W W WCO COPMTPMTCONC WALKEXISTINGBUILDINGEXISTINGGARAGECONC WALKGRAVELGRAVELGRAVELASPHALTDRIVECONCCONCBLOCKWALLCONCBLOCKWALLEXISTINGBUILDINGEDGE OF ASPHALTCURBEDGE OF ASPHALTEDGE OF ASPHALT EDGE OF ASPHALTEDGE OF ASPHALTROOF PEAKEL==372.18'F.F.E.=353.29'EXISTINGSHED0.2'0.6'5.6'6.4'SSFILE NAME:Z:\P\JW301\CAD\Sheets\JW301 Final Plans.dwg DATE/TIME:12/22/2022 9:58:40 AM DEMOLITION & TESC PLAN SEC19, TWN17, R2E WM THURSTON CO TPN 75300900100 313 YELM AVE W YELM, 98597 JENNIFER WENTWORTH COMMERCIAL DEVELOPMENT NDTRCB12-22-2022JW301NDTC339123456789101112131415ABCDEFGHIJ3 6 0 -8 9 0 -8 9 5 5 | 2 9 9 N M a r k e t B l v d , C h e h a l i s , W A 9 8 5 3 2DESIGNED BY:DRAWN BY:DATE:PROJ. NO:OFREVIEWED BY:Know what's BELOWCall 811 before you dig.NICH O L ASDAVIDAYLORSTAT E OFWASHINGTONREGISTEREDPROFESSIONALENG INEER T461131 2 - 2 2-2022 1234567KEY NOTES1.EXISTING ASPHALT CEMENT CONCRETE (ACC) DRIVEWAY. USE ASCONSTRUCTION ENTRANCE.2.DEMOLISH AND DISPOSE OF EXISTING PORTLAND CEMENT CONCRETE(PCC) SIDEWALK3.DEMOLISH AND DISPOSE OF EXISTING PCC SIDEWALK4.PROTECT EXISTING PCC SIDEWALK5.DEMOLISH AND DISPOSE OF EXISTING SIGN AND ASSOCIATEDCONCRETE BLOCKS6.PROTECT EXISTING TREE TO REMAIN (TYP)7.SAWCUT, REMOVE, AND DISPOSE OF EX. ASPHALT AS SHOWN.REMOVE EXISTING ROAD SECTION AS NEEDED TO ACCOMMODATENEW 4" DEPTH OF PAVEMENT. SEE RICE ST. SECTION DETAIL 3/C8.CONTRACTOR SHALL CONTACT THE GEOTECHNICAL ENGINEER ANDCITY PUBLIC WORKS INSPECTOR TO INSPECT EXISTING SUBGRADEPRIOR TO INSTALLATION OF THE ROADWAY SECTION. CONTRACTORSHALL PROVIDE A MIN. 48-HOUR NOTICE.(TYP)8.PROPOSED LIMITS OF DISTURBANCE9.PROTECT EXISTING WATER MAIN10.PROTECT EXISTING GAS LINE#SCALE IN FEET201008SW RICE ST YELM AVE SEALLEY773910INSTALL AND MAINTAIN INLET PROTECTION SILT SOCK AT ALLPROPOSED CATCH BASINS.NOTES Appendix G Maintenance Com- ponent Defect Conditions When Maintenance Is Needed Results Expected When Maintenance Is Performed Liner (if Applic- able) Liner is visible and has more than three 1/4-inch holes in it. Liner repaired or replaced. Liner is fully covered.  Ponds Berms (Dikes)      Settlements    Any part of berm which has settled 4 inches lower than the design elevation  If settlement is apparent, measure berm to determine amount of settlement Settling can be an indication of more severe problems with the berm or outlet works. A  licensed engineer in the state of Washington should be consulted to determine the source of  the settlement. Dike is built back to the design elevation.   Piping   Discernable water flow through pond berm. Ongoing erosion with potential for erosion to con- tinue. (Recommend a Goethechnical engineer be called in to inspect and evaluate condition and  recommend repair of condition. Piping eliminated. Erosion potential resolved.  Emergency Overflow/  Spillway and Berms  over 4 feet in height     Tree Growth     Tree growth on emergency spillways creates blockage problems and may cause failure of the  berm due to uncontrolled overtopping. Tree growth on berms  over 4 feet in height may lead to piping through the berm which could  lead to failure of the berm. Trees should be removed. If root system is small (base less than 4 inches) the root system may  be left in  place. Otherwise the roots  should be removed and the berm restored. A licensed engineer in the state of  Washington should be consulted for proper berm/spillway  restoration.  Piping   Discernable water flow through pond berm. Ongoing erosion with potential for erosion to con- tinue. (Recommend a Geotechnical engineer be called in to inspect and evaluate condition and  recommend repair of condition. Piping eliminated. Erosion potential resolved.   Emergency Over- flow/Spillway   Emergency Over- flow/Spillway   Only one layer of rock  exists above native soil in area five square feet or larger, or any  expos- ure of native soil at the top of out flow path of spillway. (Rip-rap on inside slopes need not be replaced.) Rocks  and pad depth are restored to design standards.   Erosion See "Side Slopes  of Pond"   Table V-A.1: Maintenance Standards - Detention Ponds (continued) Maintenance Component Defect Conditions When Maintenance Is Needed Results Expected When Maintenance Is Per- formed General Trash & Debris See Table V-A.1: Maintenance Standards - Detention Ponds See Table V-A.1: Maintenance Standards - Deten- tion Ponds  Poisonous/Noxious   Vegetation See Table V-A.1: Maintenance Standards - Detention Ponds See Table V-A.1: Maintenance Standards - Deten- tion Ponds Contaminants and  Pol- lution See  Table V-A.1: Maintenance Standards - Detention Ponds See Table V-A.1: Maintenance Standards - Deten- tion Ponds Rodent Holes See Table V-A.1: Maintenance Standards - Detention Ponds See  Table V-A.1: Maintenance Standards - Deten- tion Ponds Storage Area Sediment Water ponding in  infiltration pond after rainfall ceases and appropriate time allowed for  infiltration. Treatment basins should infiltrate  Water Quality Design Storm  Volume within 48 hours, and empty within 24 hours after cessation of most  rain events. Sediment is  removed and/or facility is cleaned so  that infiltration system works  according to design. Table V-A.2: Maintenance Standards - Infiltration 2019 Stormwater Management Manual for Western Washington Volume V -Appendix A -Page 1006 Maintenance Component Defect Conditions When Maintenance Is Needed Results Expected When Maintenance Is Per- formed (A percolation  test pit or test of facility indicates facility is only working at 90% of its  designed capabilities. Test every 2 to 5 years. If  two inches or more  sediment is present, remove).  Filter Bags (if  applicable)Filled with  Sediment and  Debris Sediment and  debris fill bag more than 1/2 full.Filter bag is  replaced or system is redesigned. Rock Filters Sediment and  Debris By visual  inspection, little or no water flows through filter during heavy rain storms.Gravel in rock  filter is replaced. Side Slopes of  Pond Erosion See Table V-A.1: Maintenance Standards - Detention Ponds See  Table V-A.1: Maintenance Standards - Deten- tion Ponds Emergency Overflow  Spillway  and Berms over 4 feet in height. Tree Growth See  Table V-A.1: Maintenance Standards - Detention Ponds See Table V-A.1: Maintenance Standards - Deten- tion Ponds Piping See Table V-A.1: Maintenance Standards - Detention Ponds See  Table V-A.1: Maintenance Standards - Deten- tion Ponds Emergency Overflow  Spillway Rock Missing See  Table V-A.1: Maintenance Standards - Detention Ponds See Table V-A.1: Maintenance Standards - Deten- tion Ponds Erosion See  Table V-A.1: Maintenance Standards - Detention Ponds See Table V-A.1: Maintenance Standards - Deten- tion Ponds Pre-settling Ponds  and Vaults Facility or sump  filled  with Sediment and/or  debris 6" or  designed sediment trap depth of sediment.Sediment is  removed. Table V-A.2: Maintenance Standards - Infiltration (continued) Maintenance Component Defect Conditions When Maintenance is Needed Results Expected When Maintenance is Per- formed Storage Area       Plugged Air Vents One-half of the  cross section of a vent is blocked at any point or the vent is damaged. Vents open and  functioning. Debris and  Sediment Accumulated  sediment depth exceeds 10% of the diameter of the storage area for 1/2 length  of storage vault or any point  depth exceeds 15% of diameter.  (Example: 72-inch  storage tank would require cleaning when sediment reaches depth of 7 inches  for more than 1/2 length of  tank.) All sediment and  debris removed from storage  area. Joints Between  Tank/Pipe Section Any openings or  voids allowing material to be transported into facility. (Will require  engineering analysis to determine structural stability). All joint between  tank/pipe sections are sealed. Tank Pipe Bent Out  of Shape Any part of  tank/pipe is bent out of shape more than 10% of its design shape. (Review  required by engineer to determine  structural stability).Tank/pipe repaired  or replaced to design. Vault Structure  Includes Cracks in Wall, Bottom,  Damage to Frame and/or Top Slab Cracks wider than  1/2-inch and any evidence of soil particles entering the structure through  the cracks, or main- tenance/inspection personnel determines that the vault is  not structurally sound. Cracks wider than  1/2-inch at the joint of any inlet/outlet pipe or any evidence of soil  particles entering the vault through the  walls. Vault replaced or  repaired to design spe- cifications and is structurally sound. No cracks more  than 1/4-inch wide at the joint of  the inlet/outlet pipe. Table V-A.3: Maintenance Standards - Closed Detention Systems (Tanks/Vaults) 2019 Stormwater Management Manual for Western Washington Volume V -Appendix A -Page 1007 Maintenance Component Defect Conditions When Maintenance is Needed Results Expected When Maintenance is Per- formed Manhole       Cover Not in Place Cover is missing  or only partially in place. Any open manhole requires maintenance.Manhole is closed. Locking Mechanism  Not Working Mechanism cannot  be opened by one maintenance person with proper tools. Bolts into frame have  less than 1/2 inch of  thread (may not apply to self-locking lids). Mechanism opens  with proper tools. Cover Difficult to  Remove One maintenance  person cannot remove lid after applying normal lifting pressure. Intent is to  keep cover from sealing off  access to maintenance. Cover can be  removed and reinstalled by one  maintenance person. Ladder Rungs  Unsafe Ladder is unsafe  due to missing rungs, misalignment, not securely attached to structure wall,  rust, or cracks.Ladder meets  design standards. Allows main- tenance person safe access. Catch Basins See Table V-A.5: Maintenance Standards - Catch  Basins See Table V-A.5: Maintenance Standards - Catch Basins See Table V-A.5: Maintenance Standards -  Catch Basins Table V-A.3: Maintenance Standards - Closed Detention Systems (Tanks/Vaults) (continued) Maintenance Com- ponent Defect Condition When Maintenance is Needed Results Expected When Maintenance is Performed General   Trash and Debris  (Includes Sediment)Material exceeds  25% of sump depth or 1 foot below orifice plate.Control structure  orifice is not blocked. All trash and debris removed. Structural Damage Structure is not  securely attached to manhole wall.  Structure is not  in upright position (allow  up to 10% from plumb). Connections to  outlet pipe are not watertight and show signs of rust. Any holes - other  than designed holes - in the structure. Structure securely  attached to wall and outlet pipe. Structure in correct  position. Connections to  outlet pipe are water tight; structure repaired or replaced and  works as  designed. Structure has no  holes other than designed holes. Cleanout Gate Damaged or Missing Cleanout gate is  not watertight or is missing. Gate cannot be  moved up and down by one maintenance person. Chain/rod leading  to gate is missing or damaged. Gate is rusted  over 50% of its surface area. Gate is watertight  and works as designed. Gate moves up and down  easily and is watertight. Chain is in place  and works as designed. Gate is repaired  or replaced to meet design standards. Orifice Plate   Damaged or Missing Control device is  not working properly due to missing, out of place, or  bent orifice plate.Plate is in place  and works as designed. Obstructions Any trash, debris,  sediment, or vegetation blocking the plate.Plate is free of  all obstructions and works as designed. Overflow Pipe Obstructions Any trash or  debris blocking (or having the potential of blocking) the  overflow pipe.Pipe is free of  all obstructions and works as designed. Manhole See Table V-A.3: Maintenance Standards - Closed Detention Systems  (Tanks/Vaults) See Table V-A.3: Maintenance Standards - Closed Detention Systems  (Tanks/Vaults) See Table V-A.3: Maintenance Standards - Closed Detention Systems (Tank- s/Vaults) Catch Basin See Table V-A.5: Maintenance Standards - Catch Basins See Table V-A.5: Maintenance Standards - Catch Basins See Table V-A.5: Maintenance Standards - Catch Basins Table V-A.4: Maintenance Standards - Control Structure/Flow Restrictor 2019 Stormwater Management Manual for Western Washington Volume V -Appendix A -Page 1008 BAYSAVER TECHNOLOGIES, INC. 22 Maintenance of the BayFilter™ System The BayFilter™ system requires periodic maintenance to continue operating at the design efficiency. The maintenance process comprises the removal and replacement of each BayFilter™ cartridge and drain down module and the cleaning of the vault or manhole with a vacuum truck. BayFilter™ maintenance should be performed by a BaySaver Technologies, Inc. certified maintenance contractor. The maintenance cycle of the BayFilter™ system will be driven mostly by the actual solids load on the filter. The system should be periodically monitored to be certain it is operating correctly. Since stormwater solids loads can be variable, it is possible that the maintenance cycle could be more or less than the projected duration. The BayFilter systems in New Development applications are designed to treat the WQv in 24 hours initially. Later in the cycle these cartridges will flow at a slower rate, and when the WQv does not drain down within +/- 40 hours after the storm event, the system must be maintained. When a BayFilter™ system is first installed, it is recommended that it be inspected every six (6) months. When the filter system exhibits flows below design levels the system should be maintained. Filter cartridge replacement should also be considered when sediment levels are at or above the level of the 4 inch manifold system. Please contact the BaySaver Technologies Inc. Engineering Department for maintenance cycle estimations or assistance at 1.800.229.7283. Chapter 4 BAYSAVER TECHNOLOGIES, INC. 23 Maintenance Procedures 1. Remove the manhole covers and open all access hatches. 2. Before entering the system make sure the air is safe per OSHA Standards or use a breathing apparatus. Use low O2, high CO, or other applicable warning devices per regulatory requirements. 3. Using a vacuum truck remove any liquid and sediments that can be removed prior to entry. 4. Using a small lift or the boom of the vacuum truck, remove the used cartridges by lifting them out. 5. Any cartridges that cannot be readily lifted directly out of the vault should be removed from their location and carried to the lifting point using the Trolley system installed in the Vault (if applicable). 6. When all cartridges and drain down modules are removed, remove the balance of the solids and water; then loosen the stainless clamps on the Fernco couplings in the pipe manifold; remove the drain pipes as well. Carefully cap the manifold and the Fernco’s and rinse the floor removing the balance of the collected solids. 7. Clean the manifold pipes, inspect, and reinstall. 8. Install the exchange cartridges and close all covers. 9. The used cartridges must be sent back to BaySaver Technologies, Inc. for exchange/recycling and credit on undamaged units.