Yelm Forced Relocate - SR507 & 170th St. Permit plan set -CUSTOMER CONTACTS
ASTOUND CONTACTS
CUSTOMER CONTACT:
SITE CONTACT:
CONSTRUCTION LEAD:
PROJECT MANAGER:
SCOPE OF WORK
AERIAL CONSTRUCTION:
PERMITS:
UNDERGROUND CONSTRUCTION:
SITE CONSTRUCTION:
EASEMENTS:
OVERVIEW
VICINITY
GENERAL NOTES
PAGE INDEX
TITLE1
PAGE ID
1
2 - 3
4
DESCRIPTION
PLAN VIEW
TRAFFIC CONTROL PLAN
Yelm Forced Relocate - SR507 & 170th St. Yelm - Permit Plan Set
TITLE PAGE
PLAN DATA
* DRAWINGS ARE NOT TO BE SCALED, WRITTEN DIMENSIONS TAKE PRECEDENCE.
* THIS SET OF PLANS IS INTENDED TO BE USED FOR DIAGRAMMATIC PURPOSES ONLY.
* PLAN DATA & ROW LOCATIONS ARE APPROXIMATE.
STANDARDS
* COORDINATE WITH SITE CONTACT MINIMUM 24 HOURS PRIOR TO STARTING ANY WORK ON PRIVATE
PROPERTY.
* ALL WORK AREAS TO COMPLY WITH OSHA/WISHA SAFETY STANDARDS.
* ALL EFFORT TO PREVENT CONTAMINATION FROM CONSTRUCTION DEBRIS WILL BE TAKEN .
SITE CONSTRUCTION
* ALL CONSTRUCTION TO MEET NESC SAFETY STANDARDS .
* WORK AREA WILL BE RESTORED TO “AS IS” OR “BETTER THAN” CURRENT CONDITIONS.
* ALL EXTERIOR AND INTERIOR BUILDING PENETRATIONS TO BE WEATHER SEALED AND /OR FIRE CAULKED.
* EXISTING UNDERGROUND UTILITIES ARE TO BE LOCATED .
* FIELD VERIFICATION BY APPROVED METHODS REQUIRED BEFORE DIGGING OR TUNNELING COMMENCES .
* NEW UNDERGROUND FACILITIES ON PRIVATE PROPERTY WILL BE A MINIMUM OF 30" IN DEPTH.
* HARD SURFACE RESTORATION (ASPHALT OR CONCRETE) WILL BE RESTORED WITHIN 3 WEEKS OF JOB
COMPLETION OR AS WEATHER PERMITS.
* CONDUIT ENDS SHALL ONLY TERMINATE INSIDE WAVE OR CUSTOMER OWNED VAULTS .
* ALL CONDUIT WILL BE SEALED WITH EXPANDABLE FOAM OR DUCT PLUGS, IN LAST VAULT BEFORE THE
BUILDING
* ALL CONDUIT WILL HAVE A DEDICATED LOCATE WIRE AND ADDITIONAL PULLING LINE FOR FUTURE.
MATERIALS
*MATERIALS SPECIFICATIONS SHEETS CAN BE PROVIDED UPON PROPERTY OWNER REQUEST.
KLAYTON PIKE
425-229-3503
kpike@astound.com
SEE SITE PLAN SET
N/A
City of Yelm ROW
Aerial new attach = 0'
Aerial overlash = 0'
New riser = 20'
Existing riser = 0'
New underground conduit = 1132'
Existing underground conduit = 0'
TOTAL PROJECT ROW LINEAR FOOTAGE = 1132'
Permit Tech III
PROJECT NAME:
PROJECT NUMBER:
LOCATION:
AUTHOR: Christopher.Gibson@Astound.com
425-429-5052
Yelm Forced Relocate
N/A
46.933179 -122.579369
Install (1) 4" riser Trench / Bore (1) 4" conduit w/ (1) 144ct fiber
Install (1) 24" x 36" vault
Wreck out (2) existing vaults
KLAYTON PIKE
425-229-3503
kpike@astound.com
CONSTRUCTION STANDARDS5 - 6
DATE: 3/17/2023
LEGEND
CONSTRUCTION NOTES
PLAN VIEW2
Down guy proposed - New anchor
Permit Tech III
PROJECT NAME:
PROJECT NUMBER:
LOCATION:
AUTHOR: Christopher.Gibson@Astound.com
425-429-5052
Yelm Forced Relocate
N/A
46.933179 -122.579369
3
3
V
Aerial fiber / coax existing
Trench (1) 4" conduit proposed
Conduit existing
Vault existingV
Vault proposedV
Bore (1) 4" conduit proposed
Bore pit
2
1
3
2 1
Install (1) 24" x 36" vault
Install (1) 4" riser
Install (1) anchor and down guy
2 Trench (1) 4" conduit w/ (1) 144ct fiber
3 Bore existing road (1) 4" conduit w/ (1) 144ct fiber
V
V
4 Wreck out existing vault
45
5 Wreck out existing aerial strand & fiber
LEGEND
CONSTRUCTION NOTES
PLAN VIEW3
Permit Tech III
PROJECT NAME:
PROJECT NUMBER:
LOCATION:
AUTHOR: Christopher.Gibson@Astound.com
425-429-5052
Yelm Forced Relocate
N/A
46.933179 -122.579369
2
2
Aerial fiber / coax existing
Trench (1) 4" conduit proposed
Conduit existing
Vault existingV
Vault proposedV
Bore (1) 4" conduit proposed
Bore pit
V
V
1 Trench (1) 4" conduit w/ (1) 144ct fiber
2 Bore existing road (1) 4" conduit w/ (1) 144ct fiber
3 Dig & intercept existing conduit
Overset new 24"x36" vault
4 Wreck out existing vault
1 2
34
4
PROJECT NAME:
PROJECT NUMBER:
LOCATION:
Yelm Forced Relocate
N/A
46.933179 -122.579369
General Notes
* A copy of the permit shall be on site at all times.
* Where permits from state, county, city, railroad or government agencies are required all work performed will comply with these agencies standard specifications .
* Work areas to comply with OSHA/WISHA safety standards and traffic control plans approved in the permit.
* Wave reserves the right to inspect at any time the work being performed by the contractor . If the Wave representative determines that the work is not being performed to minimum quality standards , then the contractor shall provide
rework at his own cost.
* Any change in project scope, including but not limited to, conduit length, conduit path, aerial path etc., must be approved by Wave representative .
General Underground Construction Notes
* Contractor is responsible for locating all utilities 48 hours prior to construction activity. See local directory for contact telephone number of local call before you dig agency .
* Any and all underground utilities encountered are the responsibility of the contractor to locate , protect, and repair, if damaged.
* Bore depths shall be a minimum of 36" deep. If 36" depth is not attainable, you must get the written approval of the Wave Construction Lead/Manager and document, in detail, the path and depth variance.
* Conduit sweeps at the sides of structures (buildings or poles) shall be Sched 40 PVC 3ft radius with bell ends down .
* Sweeps at poles shall be a minimum of 5" from the pole and/or line up with an empty spot on any existing riser brackets .
* If no existing riser brackets are present, the conduit shall sweep up on the side of the pole with the 'butt gain' cut out.
* Sweeps at the side of a building shall be approximately 2" from the wall to accommodate uni-strut to secure the conduit to the wall vault or Wave riser (which ever is placed).
* All vaults shall be set on a 4" layer of drainable gravel material and conduit shall extend above the gravel surface .
* Conduit shall extend no more than 2" above gravel base inside of vaults or no more than 2" inside vault sidewall penetrations .
* Concrete vault wall penetrations shall be grouted , inside and out.
* Hard surface restoration (asphalt or concrete) must be restored within 3 weeks of job completion, or as weather permits.
* All buried infrastructure must be accompanied with warning tape and/or tracer wire – as called out.
* Locate wire to be exposed at the base of any riser .
* All conduit to be plugged with expandable foam or duct seal after fiber is placed.
* Bore depth profile shall include: - Detailed description of 0.00 start station. including GPS coordinates (can be obtained from Google Earth in Degrees/Decimal format) - Bore direction in Degree's-magnetic (can be
obtained from Google Earth measuring tool) - Bore vertical profile data at 20ft intervals with occasional detailed description of interval station , listed as x+xx ft. and xx in deep - Lateral alignment in relation to the road
curb or centerline listed as 0.00ft E-W-N or S of Curb, Fog line or Centerline.
General Aerial Construction Notes
* All work to be NESC compliant.
* All fiber cables to be double-lashed to strand.
* Install anchors before strand is tensioned and fiber installed .
* All risers shall be installed on the 'cut out' side of the pole where the 'Butt Gain' notch is.
* Conduit on risers shall always have the bell end down .
Fiber Placement Notes
* If Wave is co-occupying developer installed conduit with other telecommunications facilities , we shall pull in a multi cell duct divider system, such as MaxCell and pull the Wave fiber in one of the cells.
* Fiber optic identification tags shall be placed at every work pole , manhole, fiber, storage loops, splice cases and where indicated by project manager. tags need to be placed so as to be read from the ground .
* All fiber in vaults and exposed in buildings shall have Wave 'ID Carrots' at input and output and at approx. 60ft intervals.
* Cable lubrication shall be used to reduce pulling tension. Lubricants must not contain any petroleum products.
* A 100 foot fiber coil must remain in all vaults unless otherwise noted.
* All risers will be capped at all times .
*All slack shall be marked with colored tape at the “ID carrots” to indicate direction to the next structure (vault or pole, Not snowshoe)
1.) The Center of the slack shall have the colored tape next to each other to indicate the center of the stored slack .
2.) RED tape for the next structure South (2) bands RED and West (1) RED - from current location .
3.) BLUE tape for the next structure – North (2) bands BLUE and East (1) band BLUE - from the current location.
* When preparing slack for a new splice closure, mark the center with colored tape to show direction.
* If there is traffic control required at the splice location , prep the splice tails for splicing.
* If excess cable is pulled off the reel, NEVER cut the excess off.
* Always distribute the excess along the project path as follows; Under 60ft –store at the nearest slack storage. Over 60ft –call the PM to determine how to distribute.
CONSTRUCTION
STANDARDS5
General Requirements and Information
* Work is expected to begin no less than 7 days upon issuance of work order and approved permits to Contractor unless otherwise agreed upon in writing by Wave project m anager.
* Contractor shall ensure they have and maintain valid Business Licenses as needed to perform the work .
* Contractor shall provide within 3 days of issuance a written schedule for anticipated completion time frames.
* Contractor shall place multiple crews on the project as needed to ensure completion of the project within the agreed upon pro ject schedule.
* Contractor shall ensure any and all subs they may elect to use, meet all Wave requirements as listed in this RFP or as agreed upon between WDH and Contractor .
* Contractor also agrees to be solely responsible for any and all activities performed by the sub and accepts all liabilities i mplicit and/or implied for those activities performed by the sub.
Materials
* Fiber shall be provided by Wave
* All other material shall be furnished by contractor, unless otherwise agreed upon with project manager.
Closeout Package
* Complete and submit Wave documentation forms.
* Submit as-built prints within 1-week of job completion, prior to submitting an invoice.
* As-Built documentation needs to include fiber sequential at all locations (i.e. vaults in/out, riser, pole, loops in/out, tails, etc.).
* Invoice needs to include fiber reel number and pre-construction sequential (Inside/Outside) and Post-Construction sequential (Inside/Outside).
* Send all Invoices to cpminvoices .wa@wavenotify.com, with the job name & number in the subject line
* New Underground As-built documentation will consist of an aerial overview detailing new facilities pathway , including structures (i.e.. vaults, risers, etc.) and where applicable, accompanied by a bore profile.
* Photos are required for all new vault and riser installations .
* Bore depth profile:
1.) Shall include: - Detailed description of 0.00 start station. including GPS coordinates (can be obtained from Google Earth in Degrees/Decimal format)
2.) Bore direction in Degree's-magnetic (can be obtained from Google Earth measuring tool )
3.) Bore vertical profile data at 20ft intervals with occasional detailed description of interval station , listed as x+xx ft. and xx in deep
4.) Lateral alignment in relation to the road curb or centerline listed as 0.00ft E-W-N or S of Curb, Fog line or Centerline.
* Wave reserves the right to request additional close out information on a per project basis . These specific requests will be agreed upon prior to work commencement .
All footages shall be listed on the invoice as such:
Reel # C024-0615
Inside footage: 0'
Outside footage:12,342'
End Footage: 19,998'
Numbers above are examples All invoices will be rejected if the footages are not listed as such and match the inventory of the reel on file .
Footages for invoicing purposes.
*Inside footage – This is the inner footage typically exiting center of reel – remains the same until all fiber is removed .
* Outside footage - This is the outside footage at the reel, as it comes off the reel after the job is complete.
* End footage - This is the end of the fiber at the far end of the job , after the job is complete.
CONSTRUCTION
STANDARDS6