Armor Storage Yelm_Preliminary Drainage Report PRELIMINARY DRAINAGE REPORT Armor Storage - Grove Road MC# ARMO-0001 8/28/2023 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report i PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Armor Storage - Grove Road 8/28/2023 Prepared for: Armor Storage Holdings, LLC Point of Contact: Camron McKinley Address: PO Box 430 Arlington, WA 98223 Email: camron@transweternresi.com Phone: 360-753-3100 Civil Engineer: Momentum Civil 1145 Broadway, Suite 115 Tacoma, WA 98402 Prepared by: Tony Callahan, P.E. Email: tonyc@momentumcivil.com Phone: 563-451-2623 Quality Assurance by: Marc Pudists, P.E. Email: marcp@momentumcivil.com Phone: 253-405-4474 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report ii PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Table of Contents Table of Figures......................................................................................................................................................................... iii Table of Appendices .............................................................................................................................................................. iii Section 1 - Project Overview ................................................................................................................................................ 1 Section 2 – Existing and Proposed Conditions Summary ............................................................................... 2 Existing Conditions ............................................................................................................................................................. 2 Soils Properties ................................................................................................................................................................. 2 Wells and Septic Tanks ................................................................................................................................................ 2 Floodplain Analysis ......................................................................................................................................................... 2 Critical Areas ....................................................................................................................................................................... 3 Proposed Conditions ......................................................................................................................................................... 5 Section 3 – Offsite Analysis.................................................................................................................................................. 7 Upstream Tributary Sub-basin .................................................................................................................................... 7 Downstream Analysis ........................................................................................................................................................ 7 Section 4 – Discussion of Minimum Requirements and Site Layout ....................................................... 8 Stormwater Minimum Requirements Summary ............................................................................................ 8 MR #1 – Preparation of Stormwater Site Plans ................................................................................................ 10 MR #2 – Construction Stormwater Pollution Prevention Plan (CSWPPP) .................................... 10 MR #3 – Source Control of Pollution ...................................................................................................................... 10 MR #4 – Preservation of Natural Drainage Systems and Outfalls ....................................................... 10 MR #5 – Onsite Stormwater Management ........................................................................................................ 10 MR #6 – Runoff Treatment ............................................................................................................................................ 12 MR #7 – Flow Control ........................................................................................................................................................ 12 MR #8 – Wetlands Protection ..................................................................................................................................... 12 MR #9 – Operation and Maintenance .................................................................................................................... 12 List of Appendices .................................................................................................................................................................. 14 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report iii PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Table of Figures Figure 1: Vicinity Map ............................................................................................................................................................... 1 Figure 2: Existing Conditions and Topographic Survey Map ........................................................................ 4 Figure 3: Proposed Basin Map .......................................................................................................................................... 6 Figure 4: Flow Chart for Determining Requirements for New Development ................................... 9 Figure 5: Flow Chart for Determining MR #5 Requirements ........................................................................11 Figure 6: Flow Chart for Determining Wetland Protection Level Requirements ........................... 13 Table of Appendices Appendix A - Civil Engineering Plans ...................................................................................................................... A-1 Appendix B - Gravity Conveyance Calculations ................................................................................................ B-1 Appendix C - Infiltration and Water Quality WWHM Calculations ....................................................... C-1 Appendix D - Geotechnical Report ........................................................................................................................... D-1 Appendix E - Critical Areas Report ............................................................................................................................ E-1 Appendix F - Source Control BMPs ............................................................................................................................F-1 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 1 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Section 1 - Project Overview The project proponent, Armor Storage Holdings, LLC, is applying for permits for the construction of a self-storage facility. The project is located on Thurston County Parcel Number 64303400300 at 10403 Grove Road SE in Yelm, Washington. The parcel has a total lot size of 5.77 acres. Please refer to Figure 1 for the project Vicinity Map. For this project, a Right of Way Use permit, Civil Plan Review, and Building Permit will be required by the City of Yelm. No additional permits are anticipated for development at this time. The parameters and Minimum Requirements set forth in the 2019 Department of Ecology (DOE) Stormwater Management Manual (known herein as the “Manual”) will be adhered to for this project. The subject parcel is situated adjacent to Yelm Creek within the Nisqually River Watershed. Minimum Requirements #1-9 will be applied to this project and there are no Additional Protective Measures associated with this watershed. Figure 1: Vicinity Map MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 2 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Section 2 – Existing and Proposed Conditions Summary Existing Conditions The parcel is an undeveloped vacant lot and covered primarily with field grass and sparse trees. The site is bounded by Grove Road (Rd) SE on the east, Yelm Creek on the west, a single-family residence to the north, and a vacant field to the south. The existing topography slopes gently from east to west. The western half of the parcel contains a steep slope with approximately 11 feet of vertical relief from the main site down to Yelm Creek. Please see Figure 2 for representation of the existing conditions. Soils Properties Based on the site-specific geotechnical engineering report by South Sound Geotechnical Consultants (SSGC), dated November 2, 2022, onsite soils were described as: “Topsoil was observed below the surface in the test holes and extended to depths between about 1 to 1.5 feet. Soil below the topsoil principally consisted of native gravelly sand to sandy gravel with trace silt, and variable cobbles.” and “Native soil on the site is mapped as “Spanaway gravelly sandy loam” per the USDA Soil Conservation Service map of Thurston County.” As a part of the geotechnical investigation, SSGC conducted two pilot infiltration tests (PITs). Based on the testing results, SSGC’s findings were as follows: “The measured infiltration rate is considered appropriate for the soil tested and are similar to infiltration tests completed at other sites with similar soil throughout Thurston County. We recommend a design infiltration rate of 28 inches per hour (in/hr) for native outwash soils. However, groundwater was encountered at about 7 feet below the surface in this area and should be considered in the design of infiltration facilities.” The full geotechnical report can be found in Appendix D. Wells and Septic Tanks No wells or septic tanks are known to exist onsite. Floodplain Analysis According to FEMA flood plain FIRM map number 53067C0362E for Thurston County, the majority of the project site is located outside the 0.2% annual chance flood. However, along the west property line, Zone X – “Other Flood Areas” and Zone AE – “Floodway Areas” exist centered around Yelm Creek. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 3 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Zone X is described as: “Areas of 0.2% annual change flood; areas of 1% annual chance flood with average depths of less than 1 foot or with drainage areas less than 1 square mile; and areas protected by levees from 1% annual change flood.” Zone AE is described as, “The floodway is the channel of a stream plus any adjacent floodplain areas that must be kept free of encroachment so that the 1% annual chance flood can be carried without substantial increases in flood height”. Critical Areas A steep slope exists on the western part of the site. The slope is approximately 11 feet tall, with slopes averaging approximately 10-20%. A Critical Areas investigation was completed by EnviroVector. Their findings were summarized in a report dated December 2022. The results of their finding are: “Yelm Creek and one (1) wetland is mapped on the western portion of the subject property by the Thurston County Geodata Center Database.” EnviroVector refers to the mapped wetland as, Wetland ‘A’ and describes the wetland: “The Cowardin (1979) classification of Wetland A is a Palustrine Emergent Seasonally-flooded (PEMC) wetland (Figure 6; Table 4). Wetland A is associated with Yelm Creek, but water may impound during the wetter parts of the year.” and “Wetland A has been classified as a Category III wetland using the Department of Ecology (2014) Wetland Rating Form for Western Washington as required under Yelm Municipal Code (YMC) 18.21.060(B)---Wetlands-Wetland Ratings. Wetland A is a Depressional wetland under the Department of Ecology (2014) Wetland Rating System.” The full text and appendices of the Critical Areas Report are included with this submittal. TOPOGRAPHIC SURVEY HOGWIRE FENCE NA' S NOTE: THE EXISTING UTILITIES AS SHOWN ARE ONLY APPROXIMATE AND ARE BASED ON IPE BEST AVAILABLE INFORMATION IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO VERIFY THE SIZE. TYPE, LOCATION, AND DEPTH OF ALL EXISTING UTILITIES PRIOR TO STARTING CONSTRUCTION, AND INFORM THE DESIGN ENGINEER OF ANY DISCREPANCIES. Call Before You Dig 1-800-424-5555 NW COR SEC 29, 1y T17N, R2E, W.M. 20 FOUND BRASS 30 DISK WITH "X" 133 6 (RZJ BARBED WIDE ALUMINUM FOUND REBAR & CAP HOGWIRE FENCE FENCE 1.7' S SHED 2.6' N "E TRUE LS 24227" 1.5' S 565'52'13"W 447.03'(R 1) --CHAIN LINK FENCE 1.4' S--- -I ( 247;03' \ ' k n \ 200.00'(D)(R2) SA -11 \ T III I "' CHAIN LINK FENCE 6.7' E A-11 BARBED WIRE FENCE LEGAL DESCRIPTION 3.6' S LOT 3 IN TRACT 34 OF MCKENNA IRRIGATED TRACTS, AS RECORDED IN VOLUME 9 OF PLATS, FENCE POST PAGE 43. EXCEPT THAT PORTION LYING NORTHERLY OF THE FOLLOWING DESCRIBED LINE: BEGINNING AT THE NORTHEAST CORNER OF SAID LOT 3; THENCE SOUTHEASTERLY ALONG THE BARBED WIREFENCE EASTERLY LINE OF SAID LOT 3, 250 FEET TO THE TRUE POINT OF BEGINNING OF SAID LINE; 12.3' W THENCE SOUTHWESTERLY AT RIGHT ANGLES TO THE EASTERLY LINE OF SAID LOT 3, 200 FEET; 1!t I„IIi THENCE NORTHWESTERLY TO A POINT ON THE NORTHERLY LINE OF TRACT 3, 200 FEET / 1 \ SOUTHWESTERLY OF THE POINT OF BEGINNING AND THE TERMINUS OF SAID LINE. BARBED WIRE FENCE IN THURSTON COUNTY, WASHINGTON. 0.9' E SURVEYOR'S NOTES \ 1, THE PURPOSE OF THIS SURVEY IS TO DETERMINE THE LOCATION OF THE BOUNDARIES AND III/ I PROVIDE TOPOGRAPHIC INFORMATION OF THE PARCEL AS DESCRIBED HEREON. 1 1 I SIA -6d A-61 2, THIS SURVEY WAS MADE BY FIELD TRAVERSE USING A GEOMAX ZOOM 90 2" ROBOTIC "E TRUE ITS 24227" TOTAL STATION AND TOPCON PIPER SR GPS WITH RESULTING CLOSURES EXCEEDING THE I I MINIMUM ACCURACY STANDARDS AS SET FORTH BY WAC 332-130. l 1 j� l I 3. THE BOUNDARY CORNERS AND LINES DEPICTED ON THIS MAP REPRESENT DEED LINES ONLY. I CONC PAD THEY DO NOT PURPORT TO SHOW OWNERSHIP LINES THAT MAY OTHERWISE BE DETERMINED \ BY A COURT OF LAW. \ 4. THE LEGAL DESCRIPTION IS PER RECORDS OF THURSTON COUNTY AUDITOR'S OFFICE, \I RECORDING NO. 494041, DATED AUGUST 31, 2022. A TITLE REPORT HAS NOT BEEN PROVIDED AT THIS TIME. BARBED WIRE FENCE 5, FIELD WORK FOR THIS PROJECT WAS PERFORMED IN OCTOBER, 2022 AND IS THEREFORE A 1.7 E REFLECTION OF THE CONDITIONS AT THAT TIME. ALL MONUMENTS WERE VISITED OR SET IN jSq_ % lA OCTOBER, 2022. THIS SITE CONTAINS IMPROVEMENTS NOT LOCATED OR SHOWN AS A PART M Ips I/% I I I I I I I lam; ( I III I I I OF THIS SURVEY. SAE® (rA-21 I I I I I I I 6. THIS SURVEY DOES NOT PURPORT TO SHOW ALL EASEMENTS OF RECORD. 6" 7. OVERHEAD UTILITY LINES SHOWN ON THIS MAP ARE INTENDED TO SHOW THE DIRECTION OF ✓�/��� / �� I I I I I THE OVERHEAD UTILITY LINES ONLY AND DO NOT REPRESENT THE ACTUAL WIDTH, NUMBER BARBED WIRE FENCE OR LOCATION OF LINE(S) ON THE UTILITY POLES. ON LINE BARBED WIRE & HOGWIRE FENCES 1.4' E HORIZONTAL DATUM NAD 1983(2011); SOUTH ZONE; PER RTK GPS TIES AND THE WASHINGTON STATE REFERENCE NETWORK (WSRN). UNITS OF MEASUREMENT ARE U.S. SURVEY FEET. VERTICAL DATUM NAVD 88 PER RTK GPS TIES AND THE WASHINGTON STATE REFERENCE NETWORK (WSRN). HOGWIRE & BARBED WIRE FENCES 4.2' E UNITS OF MEASUREMENT ARE U.S. SURVEY FEET. BARBED WIRE FENCE 1.2' E REFERENCE SURVEYS PIT THE PLAT OF MCKENNA IRRIGATED TRACTS, RECORDED IN VOLUME 9 OF PLATS, PAGE 43 R2)RECORD OF SURVEY, RECORDING NO 3438676 R3) RECORD OF SURVEY, RECORDING NO 1099341 R4) THE PLAT OF YELM VIEWS, RECORDED IN VOLUME 17 OF PLATS, PAGES 7-8 3 R5) BOUNDARY LINE ADJUSTMENT, RECORDING NO 94061700175 RECORDS OF THURSTON COUNTY AUDITOR'S OFFICE HOGWIRE FENCE NA' S NOTE: THE EXISTING UTILITIES AS SHOWN ARE ONLY APPROXIMATE AND ARE BASED ON IPE BEST AVAILABLE INFORMATION IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO VERIFY THE SIZE. TYPE, LOCATION, AND DEPTH OF ALL EXISTING UTILITIES PRIOR TO STARTING CONSTRUCTION, AND INFORM THE DESIGN ENGINEER OF ANY DISCREPANCIES. Call Before You Dig 1-800-424-5555 NW COR SEC 29, 1y T17N, R2E, W.M. 20 FOUND BRASS 30 DISK WITH "X" 133 6 (RZJ BARBED WIDE ALUMINUM FOUND REBAR & CAP HOGWIRE FENCE FENCE 1.7' S SHED 2.6' N "E TRUE LS 24227" 1.5' S 565'52'13"W 447.03'(R 1) --CHAIN LINK FENCE 1.4' S--- -I ( 247;03' \ ' k n \ 200.00'(D)(R2) SA -11 \ T III I "' CHAIN LINK FENCE 6.7' E A-11 \ � 1 �I EDGE OF / SA 01* 1 ,A-10 I I I ill II I \\ i( IIII l \I � \ II IIII II I 1 1 II 1111 II I \\ I I I I III IIII I ISA -9+ Id -91 I I I I I 'l l 1111 I I I 1!t I„IIi I II I I �I I IIII I I I I 11 : I 'I I IIII I I I sAieel n -'e IIII I I I II (IIII IIII II II II 11 11 II / 1 \ I II I� I I I I I BA I II I I II �I �li I I SA -7141 A-'7IF IIII I I 1 IIII I / 1 IIII I I 1 \ I '`II III/ I 1 1 I SIA -6d A-61 IIII "E TRUE ITS 24227" ^! I I V 9, PG 43 l 1 j� l I IIII I I CONC PAD APN 64303400300 \ SA-sflA-5IIII l l 1 N / III 1 I\ I \ 5.765 ACRES \I I ��//:i SAI 4f 1 A-4 / I 6" VERTICAL PIPE I A jSq_ % lA M Ips I/% I I I I I I I lam; ( I III I I I SAE® (rA-21 I I I I I I I 6" ✓�/��� / �� I I I I I 1-1 A-1 I m a o f HOGWIRE FENCE ON LINE HOGWIRE FENCE 1.0' S 3' S \ � 1 �I EDGE OF \ I I \ / I I \o I 1!t I„IIi \ I 1 I I I \ \ \\ 1 FOUND REBAR & CAP RBED WIRE FENCE "E TRUE ITS 24227" 1.7' W 0.2' N41'W V 9, PG 43 N65'52'1 3"E FOUND REBAR & CAP "E TRUE LS 24227' 0.2' N30V SHED 2.0' N I J \ � EDGE OF ASPHALT ✓/ \\8,h\ 1!t I„IIi \ I 1 \ A PORTION OF 1 MCKENTRA IRRIGATED V 9, PG 43 TRACT 34 I CONC PAD APN 64303400300 \ 251,161 SF \ 5.765 ACRES \I 6" VERTICAL PIPE / - _353- \/ I , SgBSO, / � �_ pp•13R 51 / R7•• JM � % s N 1/4 COR, SEC 29, g z T1 7N, R2E, W.M. FOUND REBAR (NO CAP) 91.01 I 20' I 20' 24"' 24-,' ` EDGE OF ASPHALT w Il wo l CENTERLINE X11 OF DITCH \ I I .I ' TRANSMISSION \\ \ LINES RIP RAP GRAVEL / DRIVEWAY / I y,/ ..✓1 CENTERLINE OF DITCH \ � I \ S I I �S 1 s \ Ir HOGWIRE FENCE 0.7' S \ HOGWIE FENCE ON LINE FOUNDREBAR & CAP \ I I ) "BEEHLER 17656" 0' S /oma �✓ FOUND REBAR &CAP li �r ✓ "BEEHLER 17656" d1 C.6' S32'E I 20' 20' / pr CHAIN LINK FENC0. E I TRANSMISSION LINES ti N W 2 y o> N �gw � M, ag� YOv V x o U O W O N LEGEND o Q v h FOUND SECTION CORNER (AS SHOWN) 4i FOUND SECTION QUARTER CORNER (AS SHOWN) O Q SET REBAR & CAP EMW LS /)44651 * FOUND REBAR & CAP (AS SHOWN) n FOUND WETLAND FLAG (AS SHOWN) �4oQ oN G FENCE POST 5F' COMMUNICATION PEDESTAL --- GUY ANCHOR 9 POWER POLE W/TRANSFORMER 41P117 POWER POLE W/TRANSFORMER & DROP 3 SEWER PULL BOX SEWER CLEANOUT L HIRE HYDRANT '.f. WATER METER Q WATER VALVE O Ll GAS VALVE LL.I O DECIDUOUS TREE "I` COTTONWOOD TREE Q T O DOUGLAS FIR TREE L � (,-) (D) DISTANCE PER DEED LU0 (R) DISTANCE OR ANGLE PER REFERENCE (M) DISTANCE AS MEASURED LS LICENSED LAND SURVEYOR O HOGWIRE FENCE LSV s J BARBED WIRE FENCE k x M J LL.I CHAIN LINKx FENCE x x x O LU / T -OH-OH-OH-OH- OVERHEAD OH OH OH OH -OVERHEAD UTILITY LINE --5----S----S----S--- Q SEWER FORCE MAIN PAINT LINE a --G----G_ _ _ _G----G--- GAS PAINT LINE --W----W----W_ _ _ _W_ _ WATER PAINT LINE _-T----T----T----T--- COMMUNICATION PAINT LINE L T M � p � 5 N � O a A O C a Z GRAPHIC SCALE � w h 0 25 50 700 � I" = 50 FEET EDGE OF ASPHALT ✓/ \\8,h\ 1!t I„IIi SEW MANE FAINTLINE 24"' 24-,' ` EDGE OF ASPHALT w Il wo l CENTERLINE X11 OF DITCH \ I I .I ' TRANSMISSION \\ \ LINES RIP RAP GRAVEL / DRIVEWAY / I y,/ ..✓1 CENTERLINE OF DITCH \ � I \ S I I �S 1 s \ Ir HOGWIRE FENCE 0.7' S \ HOGWIE FENCE ON LINE FOUNDREBAR & CAP \ I I ) "BEEHLER 17656" 0' S /oma �✓ FOUND REBAR &CAP li �r ✓ "BEEHLER 17656" d1 C.6' S32'E I 20' 20' / pr CHAIN LINK FENC0. E I TRANSMISSION LINES ti N W 2 y o> N �gw � M, ag� YOv V x o U O W O N LEGEND o Q v h FOUND SECTION CORNER (AS SHOWN) 4i FOUND SECTION QUARTER CORNER (AS SHOWN) O Q SET REBAR & CAP EMW LS /)44651 * FOUND REBAR & CAP (AS SHOWN) n FOUND WETLAND FLAG (AS SHOWN) �4oQ oN G FENCE POST 5F' COMMUNICATION PEDESTAL --- GUY ANCHOR 9 POWER POLE W/TRANSFORMER 41P117 POWER POLE W/TRANSFORMER & DROP 3 SEWER PULL BOX SEWER CLEANOUT L HIRE HYDRANT '.f. WATER METER Q WATER VALVE O Ll GAS VALVE LL.I O DECIDUOUS TREE "I` COTTONWOOD TREE Q T O DOUGLAS FIR TREE L � (,-) (D) DISTANCE PER DEED LU0 (R) DISTANCE OR ANGLE PER REFERENCE (M) DISTANCE AS MEASURED LS LICENSED LAND SURVEYOR O HOGWIRE FENCE LSV s J BARBED WIRE FENCE k x M J LL.I CHAIN LINKx FENCE x x x O LU / T -OH-OH-OH-OH- OVERHEAD OH OH OH OH -OVERHEAD UTILITY LINE --5----S----S----S--- Q SEWER FORCE MAIN PAINT LINE a --G----G_ _ _ _G----G--- GAS PAINT LINE --W----W----W_ _ _ _W_ _ WATER PAINT LINE _-T----T----T----T--- COMMUNICATION PAINT LINE L T M � p � 5 N � O a A O C a Z GRAPHIC SCALE � w h 0 25 50 700 � I" = 50 FEET MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 5 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Proposed Conditions The proposed project includes two new self-storage facilities and associated parking and drive aisles. Offsite frontage improvements on Grove Road SE include an 8-foot right-of-way dedication as well as roadway widening with new curb, gutter, and sidewalk to be constructed along the site frontage. Please see Figure 3 for representation of the proposed conditions. RISERRISERCOVEREDLOADINGDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSFMWWWWWWWWWWW W W W WWWWWWSSFIRE W RIDGE LINERIDGE LINEFIRECOTCOS18"24"24"40"48"36"62.5'187.5'32"112.50'345 350 341341 342 342 343 344 346 347 348 349 351 352 353 353 354354 345345 345 345 350 350350 350 341 342 342 342 342 342 342 342 342343343 3 4 3 3 4 3 344344 344 3 4 4 346346 346 346 347347 347 347 348348348 348 349 349349 349 351 351 351 351 352352 352 352 353 353 3 5 3 353353 353 353353353 353 3553523533 5 4 35 3 353 353353 3 5 3 353 354354354 354 354 354354 354 354354354354GROVE ROAD SE BIORETENTION CELL A BIORETENTION CELL C BIORETENTION CELL B 35450.00' STEEP SLOPE SETBACK (INFILTRATION) 355 351351352352353353353353353354354 354354356356 351 351352 352353353 353 354354 354355 353354 3 5 4 354 MA P P E D WE T L A N D E D G E 112.50'BUILDING A SUB-BASIN 1: SUB-BASIN 3: BUILDING B SUB-BASIN 2: SUB-BASIN 5: SUB-BASIN 4: 112.5 - F T R E D U C E D WE T L A N D B U F F E R 531.51'200.00'250.00'247.03'565.89'496.31'PROPOSED SURFACE COVERAGE SUMMARY SURFACE DESCRIPTION AREA (SQ. FT)AREA (ACRE)HATCH SUB-BASIN 1: BUILDING A NEW PGHS 0 SF 0.00 AC NEW NON-PGHS 25,501 SF 0.59 AC TOTAL HARD SURFACE 25,501 SF 0.59 AC TOTAL SOFTSCAPING 0 SF 0.00 AC SUB-BASIN 2: BUILDING B NEW PGHS 0 SF 0.00 AC NEW NON-PGHS 12,050 SF 0.28 AC TOTAL HARD SURFACE 12,050 SF 0.28 AC TOTAL SOFTSCAPING 0 SF 0.00 AC SUB-BASIN 3: NORTH PARKING LOT NEW PGHS 4,977 SF 0.11 AC NEW NON-PGHS 124 SF 0.00 AC TOTAL HARD SURFACE 5,101 SF 0.12 AC TOTAL SOFTSCAPING 2,194 SF 0.05 AC SUB-BASIN 4: SOUTH PARKING LOT NEW PGHS 25,930 SF 0.60 AC NEW NON-PGHS 580 SF 0.01 AC TOTAL HARD SURFACE 26,510 SF 0.61 AC TOTAL SOFTSCAPING 48,390 SF 1.11 AC SUB-BASIN 5: RIGHT-OF-WAY NEW PGHS 9,519 SF 0.22 AC NEW NON-PGHS 2,926 SF 0.07 AC TOTAL HARD SURFACE 12,445 SF 0.29 AC TOTAL SOFTSCAPING 5,619 SF 0.13 AC SUB-BASIN LIMITS TOTAL DISTURBED AREA 92,730 SF 2.13 AC NORTH NW 1/4, NW 1/4, SECTION 29, TOWNSHIP 17N, RANGE 2E, W.M.   ARMO-0001 FIG3 1 OF 1 YELM, WA08/28/2023ARMOR STORAGEARMOR STORAGE HOLDINGS LLCPROPOSED BASIN MAP - ARMO0110403 GROVE RD SENAD83 NAVD88                                   T. CALLAHAN T. CALLAHAN MAP KEY MAP - PROPERTY LINE GROVE RD SE10403 G R O V E R D S E PROJECT NO. DRAWN BY: DESIGNED BY:DATENO.REVISION DESCRIPTIONCKBYDATE: SHEET NO.Save Date: Plot Date: 8/28/2023 5:49 PM8/28/2023 5:59 PMBy: DaveDiazP:\A\armo0001-yelm\0400CAD\Sheets\Exhibits\Proposed Basin Map - ARMO01.dwgTony CallahanBy: File:CHECKED BY: 1145 BROADWAY, SUITE 115 TACOMA, WA 98402 PHONE: 253.319.1504 VERT. DATUM: HORZ. DATUM: REFERENCE NO.  MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 7 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Section 3 – Offsite Analysis Upstream Tributary Sub-basin The existing site topography is gently sloped and minimal, if any, upstream runoff comes onto the site. Downstream Analysis The existing site is tributary to Yelm Creek and ultimately the Nisqually River. No downstream drainage complaints are known to exist. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 8 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Section 4 – Discussion of Minimum Requirements and Site Layout Stormwater Minimum Requirements Summary The existing site is undeveloped and is therefore subject to the “New Development” requirements of the Manual. The Project will result in more than 10,000 sf of new impervious surface and more than 5,000 sf of pollution generating hard surface (PGHS); therefore, all Minimum Requirements apply to new and replaced hard surfaces and converted vegetation areas. See Figure 4 for the Department of Ecology flow chart for determining the Minimum Requirements applicable for this project. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 9 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Figure 4: Flow Chart for Determining Requirements for New Development MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 10 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx MR #1 – Preparation of Stormwater Site Plans A stormwater Site Plan has been prepared in accordance with the DOE requirements. This storm drainage report and the associated civil engineering plans fulfill this requirement. MR #2 – Construction Stormwater Pollution Prevention Plan (CSWPPP) A Temporary Erosion and Sediment Control Plan will be prepared as a part of the civil plans for this project which describes project specific measures to take based on the Department of Ecology’s Best Management Practices. Control measures shall conform to the requirements as set forth established in the 2019 Department of Ecology (DOE) Stormwater Management Manual. The Construction Stormwater Pollution Prevention Plan will be available as a stand- alone document as part of the future site development permit submittal. Since this project will disturb more than 1.0 acres of land, coverage under the DOE’s General Permit for Construction-Related Stormwater Discharges will be required. MR #3 – Source Control of Pollution Construction phase Best Management Practices (BMPs) will be detailed in the final Construction Drawings. These BMPs represent the minimum expected control measures for the interim construction site conditions. The contractor shall be responsible for adjusting and maintaining these BMPs are required by the site conditions. MR #4 – Preservation of Natural Drainage Systems and Outfalls All stormwater runoff within the disturbed areas will be collected and infiltrated via roof downspout infiltration trenches and bioretention cells. This meets the requirements of MR #4 to maintain natural drainage patterns. MR #5 – Onsite Stormwater Management The LID Performance standard will be met by utilizing bioretention cells to treat and infiltrate 100% of the new pollution generating hard surfaces, as well as roof downspout infiltration trenches that will infiltrate 100% of the stormwater tributary to the roofs. BMP T5.13: Post Construction Soil Quality and Depth will be applied to all converted vegetated areas. See Figure 5 for the Department of Ecology flow chart for determining the MR #5 Requirements for this project. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 11 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Figure 5: Flow Chart for Determining MR #5 Requirements MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 12 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx MR #6 – Runoff Treatment The development associated with this project will introduce more than 5,000 sf of pollution-generating hard surface (PGHS), therefore Runoff Treatment is required for all PGHS. Bioretention cells will be implemented to treat and infiltrate all PHGS introduced. Results from the sizing calculations can be found in Appendix C. MR #7 – Flow Control More than 10,000 sf of effective impervious surface will be introduced as a result of the proposed project; therefore, Flow Control is required. The requirements of MR #7 will be met by meeting the LID Performance standard. Bioretention cells will treat and infiltrate 100% of the new pollution generating hard surfaces, and roof downspout infiltration trenches will infiltrate 100% of the stormwater tributary to the roofs. BMP T5.13: Post Construction Soil Quality and Depth will be applied to all converted vegetated areas. MR #8 – Wetlands Protection Based on the findings by EnviroVector in their report dated December 2022, Wetland ‘A’ is Category III wetland with a habitat score of 5, and is not a habitat for rare, endangered, threatened, or sensitive species, and does not contain a breeding population of any native amphibians, therefore only General Protection and Protection from Pollutants apply to this project. The sections on MR #1-7 and #9 describe in greater detail how those requirements are being met. See Figure 6 on the following page for the Department of Ecology flow chart for determining the MR #8 Requirements for this project and Appendix E for the full Critical Areas Report. MR #9 – Operation and Maintenance The Operation and Maintenance Manual will be available as a stand-alone document as part of the final permit submittal. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 13 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Figure 6: Flow Chart for Determining Wetland Protection Level Requirements MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page 14 of 14 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx List of Appendices Appendix A - Civil Engineering Plans ........................................................................................................ A-1 Appendix B - Gravity Conveyance Calculations ................................................................................. B-1 Appendix C - Infiltration and Water Quality WWHM Calculations ......................................... C-1 Appendix D - Geotechnical Report ............................................................................................................ D-1 Appendix E - Critical Areas Report .............................................................................................................. E-1 Appendix F - Source Control BMPs ............................................................................................................ F-1 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page A-1 of 1 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Appendix A - Civil Engineering Plans © 2023 Microsoft Corporation © 2023 TomTom COCO GR O V E R D SE 192019 20AC1.0COTCOS18"24"24"40"48"36"62.5' 187.5'32"RISERRISERGROVE RD SE (LOCAL COLLECTOR)COVEREDLOADINGDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSBUILDING A 23,964 SF FOOTPRINT BUILDING B 11,970 SF FOOTPRINT FMWWWWWWWWWWW W W W WWWWWWSSFIRE W RIDGE LINERIDGE LINEFIRE355355353 353 3 5 3 354 354354354354355 345 350 342342 343 344 346 347 348 349 351 352 353 354 345 350 342 3 4 2 3 4 3 344 346 347 348 349 351 352 353 345 350 341341 342 342 343 344 346 347 348 349 351 352 353 3 5 2 3533533 5 3 354 354 354 354 354355 353 353 354353352351353351352353354351351352352353353354354354354 353352 3543548.00'ROWDEDICATION8.00'ROWDEDICATIONBIORETENTION CELL A BIORETENTION CELL B BIORETENTION CELL C-2 FRONTAGE OVERFLOW TRENCH C-2 BIORETENTION CELL C-1 FRONTAGE OVERFLOW TRENCH C-1R26.00'TYP.R52.00' TYP.26.00'EVA ROUTE40.00'EXISTINGROW48.00'FURUTEROW40.00'EXISTINGROW48.00'FURUTEROW36.00'26.00' 49.85'26.00'EVA ROUTER26.00'TYP.15.00'26.00'EVAROUTE35.38' 11.00' CLEAR 11.00' CLEAR 10.00' CLEAR MAPPED WETLAND EDGE FLOOD PLAIN ELEVATION 112.50' REDUCED WETLAND BUFFER112.50' REDUCED WETLAND BUFFERA C1.0 950 GALLON STEP TANK - H25 RATED 28.50' CIVIL LEGEND BUILDING FOOTPRINT PROPERTY BOUNDARY EXISTING MINOR CONTOUR EXISTING MAJOR CONTOUR PROPOSED MINOR CONTOUR PROPOSED MAJOR CONTOUR WATER SERVICE LINE GRAVITY SEWER LINE PRESSURE SEWER LINE SANITARY SEWER CLEANOUT AND PUMP VAULT STORM DRAINAGE CLEANOUT / TYPE 1 CATCH BASIN FIRE HYDRANT/FDC/FITTINGS SITE FENCING WETLAND EDGE 112.50' REDUCED WETLAND BUFFER FLOOD PLAIN ELEVATION EMERGENCY VEHICLE ACCESS ROUTE HMA PAVING CEMENT CONCRETE SIDEWALK LANDSCAPING/TOPSOIL AMENDMENT BOTTOM OF BIORETENTION CELL INFILTRATION TRENCH MAPPED WETLAND UNDISTURBED WETLAND BUFFER AREA WETLAND BUFFER INCURSION/COMPENSATORY PLANTINGS 19 20 W W SS 19 20 FM 531.51' 200.00' 250.00'247.03'565.89'496.31'BLDG. BBLDG. ANORTH SITE INFORMATION ENVIRONMENTAL SOILS STREET STANDARDS SEWER CONCEPTDRAINAGE CONCEPT THURSTON COUNTY PN: 64303400300 ADDRESS: 10403 GROVE RD SE, YELM, 98597 CURRENT ZONING: LARGE LOT COMMERCIAL (C-3) PARCEL SIZE: 251, 161 SF/ 5.77 AC ·INFILTRATION TRENCHES FOR BUILDING A ·INFILTRATION TRENCHES FOR BUILDING B ·BIORETENTION CELL FOR ONSITE PAVING ·BIORETENTION CELL FOR FRONTAGE IMPROVEMENTS ·THERE IS AN EXISTING WETLAND LOCATED ON THE WESTERN EDGE OF THE SITE WITH A 112.50' REDUCED WETLAND BUFFER ·A PORTION OF THE SITE TO THE WEST IS LOCATED WITHIN THE 100-YEAR FLOOD PLAIN ·SOIL TYPE: OUTWASH ·MEASURED INFILTRATION RATE: 62 INCHES PER HOUR ·CORRECTED INFILTRATION RATE: 28 INCHES PER HOUR ·GROUNDWATER WAS ENCOUNTERED ABOUT 7 FEET BELOW THE SURFACE IN TESTED AREAS. FRONTAGE STREET: GROVE RD SE (LOCAL COLLECTOR) FRONTAGE IMPROVEMENTS: ·HALF STREET IMPROVEMENTS REQUIRED ·ROADWAY WIDENING TO 16.00' LANE ·NEW CURB & GUTTER ·6.50' AMENITY/LANDSCAPING ·5.00' NEW SIDEWALK ·8.00' OF FRONTAGE IS REQUIRED TO BE DEDICATED TO R.O.W. ·SEPTIC TANK EFFLUENT PUMPING (STEP) SYSTEM FOR BUILDING A. VICINITY MAP NORTH   ARMO-0001 C1.0 1 OF 1 YELM, WA08/28/2023ARMOR STORAGEARMOR STORAGE HOLDINGS LLCPRELIMINARY SITE PLAN10403 GROVE RD SENAD83 NAVD88                                   T. CALLAHAN T. CALLAHAN MAP WATER CONCEPT ·WATER MAIN EXTENSION AND MAIN LOOPING ONSITE ·2 NEW FIRE HYDRANTS ·DOMESTIC AND FIRE SERVICE FOR BUILDING A ·FIRE SERVICE FOR BUILDING B PROJECT SITE SCALE: NTS COMMERCIAL COLLECTER TYPICAL SECTION(HALF STREET ONLY)A KEY MAP - PROPERTY LINE GROVE RD SE10403 G R O V E R D S E PROJECT NO. DRAWN BY: DESIGNED BY:DATENO.REVISION DESCRIPTIONCKBYDATE: SHEET NO.Save Date: Plot Date: 8/28/2023 5:56 PM8/28/2023 6:00 PMBy: LiamAyersP:\A\ARMO0001-Yelm\0400CAD\Sheets\Exhibits\Prelim Plan - ARMO01.dwgLiam AyersBy: File:CHECKED BY: 1145 BROADWAY, SUITE 115 TACOMA, WA 98402 PHONE: 253.319.1504 VERT. DATUM: HORZ. DATUM: REFERENCE NO. 467 SF WETLAND BUFFER INCURSION 55 SF WETLAND BUFFER INCURSION 522 SF COMPENSATORY BUFFER PLANTINGS MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page B-1 of 1 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Appendix B - Gravity Conveyance Calculations To be provided with the final engineering submittal. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-1 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Appendix C - Infiltration and Water Quality WWHM Calculations MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-2 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx WWHM2012 PROJECT REPORT ___________________________________________________________________ Project Name: Subbasin 1: Bldg A-Roof Infil Site Name: Armor Storage & RV Site Address: 10403 Grove Road SE City : Yelm Report Date: 8/28/2023 Gage : Lake Lawrence Data Start : 1955/10/01 Data End : 2008/09/30 Precip Scale: 0.86 Version Date: 2023/01/27 Version : 4.2.19 ___________________________________________________________________ Low Flow Threshold for POC 1 : 50 Percent of the 2 Year ___________________________________________________________________ High Flow Threshold for POC 1: 50 year ___________________________________________________________________ PREDEVELOPED LAND USE Name : Basin 1 Bypass: No GroundWater: No Pervious Land Use acre A B, Forest, Flat .275 Pervious Total 0.275 Impervious Land Use acre Impervious Total 0 Basin Total 0.275 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater ___________________________________________________________________ MITIGATED LAND USE Name : Bldg A - Roof Bypass: No GroundWater: No MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-3 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Pervious Land Use acre Pervious Total 0 Impervious Land Use acre ROOF TOPS FLAT 0.55 Impervious Total 0.55 Basin Total 0.55 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater Gravel Trench Bed 1 Gravel Trench Bed 1 ___________________________________________________________________ Name : Gravel Trench Bed 1 Bottom Length: 250.00 ft. Bottom Width: 2.00 ft. Trench bottom slope 1: 0 To 1 Trench Left side slope 0: 0 To 1 Trench right side slope 2: 0 To 1 Material thickness of first layer: 1.5 Pour Space of material for first layer: 0.3 Material thickness of second layer: 0 Pour Space of material for second layer: 0 Material thickness of third layer: 0 Pour Space of material for third layer: 0 Infiltration On Infiltration rate: 28 Infiltration safety factor: 1 Total Volume Infiltrated (ac-ft.): 95.553 Total Volume Through Riser (ac-ft.): 0.003 Total Volume Through Facility (ac-ft.): 95.556 Percent Infiltrated: 100 Total Precip Applied to Facility: 0 Total Evap From Facility: 0 Discharge Structure Riser Height: 1.5 ft. Riser Diameter: 8 in. Element Flows To: Outlet 1 Outlet 2 ___________________________________________________________________ Gravel Trench Bed Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs) 0.0000 0.011 0.000 0.000 0.000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-4 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0278 0.011 0.000 0.000 0.324 0.0556 0.011 0.000 0.000 0.324 0.0833 0.011 0.000 0.000 0.324 0.1111 0.011 0.000 0.000 0.324 0.1389 0.011 0.000 0.000 0.324 0.1667 0.011 0.000 0.000 0.324 0.1944 0.011 0.000 0.000 0.324 0.2222 0.011 0.000 0.000 0.324 0.2500 0.011 0.000 0.000 0.324 0.2778 0.011 0.001 0.000 0.324 0.3056 0.011 0.001 0.000 0.324 0.3333 0.011 0.001 0.000 0.324 0.3611 0.011 0.001 0.000 0.324 0.3889 0.011 0.001 0.000 0.324 0.4167 0.011 0.001 0.000 0.324 0.4444 0.011 0.001 0.000 0.324 0.4722 0.011 0.001 0.000 0.324 0.5000 0.011 0.001 0.000 0.324 0.5278 0.011 0.001 0.000 0.324 0.5556 0.011 0.001 0.000 0.324 0.5833 0.011 0.002 0.000 0.324 0.6111 0.011 0.002 0.000 0.324 0.6389 0.011 0.002 0.000 0.324 0.6667 0.011 0.002 0.000 0.324 0.6944 0.011 0.002 0.000 0.324 0.7222 0.011 0.002 0.000 0.324 0.7500 0.011 0.002 0.000 0.324 0.7778 0.011 0.002 0.000 0.324 0.8056 0.011 0.002 0.000 0.324 0.8333 0.011 0.002 0.000 0.324 0.8611 0.011 0.003 0.000 0.324 0.8889 0.011 0.003 0.000 0.324 0.9167 0.011 0.003 0.000 0.324 0.9444 0.011 0.003 0.000 0.324 0.9722 0.011 0.003 0.000 0.324 1.0000 0.011 0.003 0.000 0.324 1.0278 0.011 0.003 0.000 0.324 1.0556 0.011 0.003 0.000 0.324 1.0833 0.011 0.003 0.000 0.324 1.1111 0.011 0.003 0.000 0.324 1.1389 0.011 0.003 0.000 0.324 1.1667 0.011 0.004 0.000 0.324 1.1944 0.011 0.004 0.000 0.324 1.2222 0.011 0.004 0.000 0.324 1.2500 0.011 0.004 0.000 0.324 1.2778 0.011 0.004 0.000 0.324 1.3056 0.011 0.004 0.000 0.324 1.3333 0.011 0.004 0.000 0.324 1.3611 0.011 0.004 0.000 0.324 1.3889 0.011 0.004 0.000 0.324 1.4167 0.011 0.004 0.000 0.324 1.4444 0.011 0.005 0.000 0.324 1.4722 0.011 0.005 0.000 0.324 1.5000 0.011 0.005 0.000 0.324 1.5278 0.011 0.005 0.032 0.324 1.5556 0.011 0.005 0.092 0.324 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-5 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 1.5833 0.011 0.006 0.168 0.324 1.6111 0.011 0.006 0.255 0.324 1.6389 0.011 0.006 0.348 0.324 1.6667 0.011 0.007 0.441 0.324 1.6944 0.011 0.007 0.531 0.324 1.7222 0.011 0.007 0.610 0.324 1.7500 0.011 0.008 0.678 0.324 1.7778 0.011 0.008 0.730 0.324 1.8056 0.011 0.008 0.769 0.324 1.8333 0.011 0.009 0.799 0.324 1.8611 0.011 0.009 0.841 0.324 1.8889 0.011 0.009 0.873 0.324 1.9167 0.011 0.009 0.903 0.324 1.9444 0.011 0.010 0.933 0.324 1.9722 0.011 0.010 0.961 0.324 2.0000 0.011 0.010 0.989 0.324 2.0278 0.011 0.011 1.017 0.324 2.0556 0.011 0.011 1.043 0.324 2.0833 0.011 0.011 1.069 0.324 2.1111 0.011 0.012 1.094 0.324 2.1389 0.011 0.012 1.118 0.324 2.1667 0.011 0.012 1.143 0.324 2.1944 0.011 0.013 1.166 0.324 2.2222 0.011 0.013 1.189 0.324 2.2500 0.011 0.013 1.212 0.324 2.2778 0.011 0.014 1.234 0.324 2.3056 0.011 0.014 1.256 0.324 2.3333 0.011 0.014 1.277 0.324 2.3611 0.011 0.015 1.299 0.324 2.3889 0.011 0.015 1.319 0.324 2.4167 0.011 0.015 1.340 0.324 2.4444 0.011 0.016 1.360 0.324 2.4722 0.011 0.016 1.380 0.324 2.5000 0.011 0.016 1.399 0.324 ___________________________________________________________________ ___________________________________________________________________ ANALYSIS RESULTS Stream Protection Duration ___________________________________________________________________ Predeveloped Landuse Totals for POC #1 Total Pervious Area:0.275 Total Impervious Area:0 ___________________________________________________________________ Mitigated Landuse Totals for POC #1 Total Pervious Area:0 Total Impervious Area:0.55 ___________________________________________________________________ Flow Frequency Return Periods for Predeveloped. POC #1 Return Period Flow(cfs) MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-6 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 2 year 0.000417 5 year 0.001158 10 year 0.002134 25 year 0.004358 50 year 0.007156 100 year 0.011446 Flow Frequency Return Periods for Mitigated. POC #1 Return Period Flow(cfs) 2 year 0 5 year 0 10 year 0 25 year 0 50 year 0 100 year 0 ___________________________________________________________________ Stream Protection Duration Annual Peaks for Predeveloped and Mitigated. POC #1 Year Predeveloped Mitigated 1956 0.001 0.000 1957 0.000 0.000 1958 0.000 0.000 1959 0.000 0.000 1960 0.000 0.000 1961 0.001 0.000 1962 0.000 0.000 1963 0.000 0.000 1964 0.000 0.000 1965 0.000 0.000 1966 0.000 0.000 1967 0.000 0.000 1968 0.000 0.000 1969 0.000 0.000 1970 0.000 0.000 1971 0.002 0.000 1972 0.003 0.000 1973 0.000 0.000 1974 0.001 0.000 1975 0.000 0.000 1976 0.000 0.000 1977 0.000 0.000 1978 0.000 0.000 1979 0.000 0.000 1980 0.000 0.000 1981 0.001 0.000 1982 0.001 0.000 1983 0.000 0.000 1984 0.000 0.000 1985 0.000 0.000 1986 0.001 0.000 1987 0.000 0.000 1988 0.000 0.000 1989 0.000 0.000 1990 0.002 0.020 1991 0.002 0.000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-7 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 1992 0.000 0.000 1993 0.000 0.000 1994 0.000 0.000 1995 0.001 0.000 1996 0.003 0.000 1997 0.002 0.000 1998 0.001 0.000 1999 0.000 0.000 2000 0.000 0.000 2001 0.000 0.000 2002 0.001 0.000 2003 0.000 0.000 2004 0.014 0.000 2005 0.002 0.062 2006 0.010 0.000 2007 0.004 0.000 2008 0.000 0.000 ___________________________________________________________________ Stream Protection Duration Ranked Annual Peaks for Predeveloped and Mitigated. POC #1 Rank Predeveloped Mitigated 1 0.0139 0.0616 2 0.0100 0.0205 3 0.0043 0.0000 4 0.0033 0.0000 5 0.0029 0.0000 6 0.0024 0.0000 7 0.0022 0.0000 8 0.0022 0.0000 9 0.0018 0.0000 10 0.0016 0.0000 11 0.0014 0.0000 12 0.0014 0.0000 13 0.0014 0.0000 14 0.0010 0.0000 15 0.0008 0.0000 16 0.0006 0.0000 17 0.0005 0.0000 18 0.0005 0.0000 19 0.0005 0.0000 20 0.0005 0.0000 21 0.0004 0.0000 22 0.0003 0.0000 23 0.0003 0.0000 24 0.0003 0.0000 25 0.0002 0.0000 26 0.0002 0.0000 27 0.0002 0.0000 28 0.0002 0.0000 29 0.0002 0.0000 30 0.0002 0.0000 31 0.0002 0.0000 32 0.0002 0.0000 33 0.0002 0.0000 34 0.0002 0.0000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-8 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 35 0.0002 0.0000 36 0.0002 0.0000 37 0.0002 0.0000 38 0.0002 0.0000 39 0.0002 0.0000 40 0.0002 0.0000 41 0.0002 0.0000 42 0.0002 0.0000 43 0.0002 0.0000 44 0.0002 0.0000 45 0.0002 0.0000 46 0.0002 0.0000 47 0.0002 0.0000 48 0.0002 0.0000 49 0.0002 0.0000 50 0.0002 0.0000 51 0.0002 0.0000 52 0.0002 0.0000 53 0.0002 0.0000 ___________________________________________________________________ Stream Protection Duration POC #1 The Facility FAILED Facility FAILED duration standard for 1+ flows. Flow(cfs) Predev Mit Percentage Pass/Fail 0.0002 699 6 0 Pass 0.0003 148 6 4 Pass 0.0003 120 6 5 Pass 0.0004 98 6 6 Pass 0.0005 80 6 7 Pass 0.0006 61 6 9 Pass 0.0006 51 5 9 Pass 0.0007 48 5 10 Pass 0.0008 44 5 11 Pass 0.0008 38 5 13 Pass 0.0009 37 5 13 Pass 0.0010 33 5 15 Pass 0.0011 32 5 15 Pass 0.0011 30 5 16 Pass 0.0012 29 5 17 Pass 0.0013 27 5 18 Pass 0.0013 26 5 19 Pass 0.0014 22 5 22 Pass 0.0015 19 5 26 Pass 0.0015 18 5 27 Pass 0.0016 16 5 31 Pass 0.0017 16 5 31 Pass 0.0018 14 5 35 Pass 0.0018 13 5 38 Pass 0.0019 11 5 45 Pass 0.0020 9 5 55 Pass 0.0020 9 5 55 Pass 0.0021 9 5 55 Pass MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-9 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0022 9 5 55 Pass 0.0022 8 5 62 Pass 0.0023 6 5 83 Pass 0.0024 5 5 100 Pass 0.0025 5 5 100 Pass 0.0025 5 5 100 Pass 0.0026 5 5 100 Pass 0.0027 5 5 100 Pass 0.0027 5 5 100 Pass 0.0028 5 5 100 Pass 0.0029 5 5 100 Pass 0.0029 4 5 125 Fail 0.0030 4 5 125 Fail 0.0031 4 5 125 Fail 0.0032 4 5 125 Fail 0.0032 4 5 125 Fail 0.0033 4 5 125 Fail 0.0034 3 5 166 Fail 0.0034 3 5 166 Fail 0.0035 3 5 166 Fail 0.0036 3 5 166 Fail 0.0036 3 5 166 Fail 0.0037 3 5 166 Fail 0.0038 3 5 166 Fail 0.0039 3 5 166 Fail 0.0039 3 5 166 Fail 0.0040 3 5 166 Fail 0.0041 3 5 166 Fail 0.0041 3 5 166 Fail 0.0042 3 5 166 Fail 0.0043 3 5 166 Fail 0.0043 2 5 250 Fail 0.0044 2 5 250 Fail 0.0045 2 5 250 Fail 0.0046 2 5 250 Fail 0.0046 2 5 250 Fail 0.0047 2 5 250 Fail 0.0048 2 5 250 Fail 0.0048 2 5 250 Fail 0.0049 2 5 250 Fail 0.0050 2 5 250 Fail 0.0051 2 5 250 Fail 0.0051 2 5 250 Fail 0.0052 2 5 250 Fail 0.0053 2 5 250 Fail 0.0053 2 5 250 Fail 0.0054 2 5 250 Fail 0.0055 2 5 250 Fail 0.0055 2 5 250 Fail 0.0056 2 5 250 Fail 0.0057 2 5 250 Fail 0.0058 2 5 250 Fail 0.0058 2 5 250 Fail 0.0059 2 5 250 Fail 0.0060 2 5 250 Fail 0.0060 2 5 250 Fail MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-10 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0061 2 5 250 Fail 0.0062 2 5 250 Fail 0.0062 2 5 250 Fail 0.0063 2 5 250 Fail 0.0064 2 5 250 Fail 0.0065 2 5 250 Fail 0.0065 2 5 250 Fail 0.0066 2 5 250 Fail 0.0067 2 5 250 Fail 0.0067 2 5 250 Fail 0.0068 2 5 250 Fail 0.0069 2 5 250 Fail 0.0069 2 5 250 Fail 0.0070 2 5 250 Fail 0.0071 2 5 250 Fail 0.0072 2 5 250 Fail _____________________________________________________ The development has an increase in flow durations from 1/2 Predeveloped 2 year flow to the 2 year flow or more than a 10% increase from the 2 year to the 50 year flow. The development has an increase in flow durations for more than 50% of the flows for the range of the duration analysis. ___________________________________________________________________ Water Quality BMP Flow and Volume for POC #1 On-line facility volume: 0 acre-feet On-line facility target flow: 0 cfs. Adjusted for 15 min: 0 cfs. Off-line facility target flow: 0 cfs. Adjusted for 15 min: 0 cfs. ___________________________________________________________________ LID Report LID Technique Used for Total Volume Volume Infiltration Cumulative Percent Water Quality Percent Comment Treatment? Needs Through Volume Volume Volume Water Quality Treatment Facility (ac-ft.) Infiltration Infiltrated Treated (ac-ft) (ac-ft) Credit Gravel Trench Bed 1 POC N 86.96 N 100.00 Total Volume Infiltrated 86.96 0.00 0.00 100.00 0.00 0% No Treat. Credit Compliance with LID Standard 8 Duration Analysis Result = Failed ___________________________________________________________________ Perlnd and Implnd Changes No changes have been made. ___________________________________________________________________ This program and accompanying documentation are provided 'as-is' without warranty of any kind. The entire risk regarding the performance and results of this program is assumed by End User. Clear Creek Solutions Inc. and the governmental licensee or sublicensees disclaim all warranties, either expressed or implied, including but not limited to implied warranties of program and accompanying documentation. In no event shall Clear Creek Solutions Inc. be liable for any MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-11 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx damages whatsoever (including without limitation to damages for loss of business profits, loss of business information, business interruption, and the like) arising out of the use of, or inability to use this program even if Clear Creek Solutions Inc. or their authorized representatives have been advised of the possibility of such damages. Software Copyright © by : Clear Creek Solutions, Inc. 2005-2023; All Rights Reserved. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-12 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx WWHM2012 PROJECT REPORT ___________________________________________________________________ Project Name: SubBasin2: Bldg B-Roof Infil Site Name: Armor Storage & RV Site Address: 10403 Grove Road SE City : Yelm Report Date: 8/28/2023 Gage : Lake Lawrence Data Start : 1955/10/01 Data End : 2008/09/30 Precip Scale: 0.86 Version Date: 2023/01/27 Version : 4.2.19 ___________________________________________________________________ Low Flow Threshold for POC 1 : 50 Percent of the 2 Year ___________________________________________________________________ High Flow Threshold for POC 1: 50 year ___________________________________________________________________ PREDEVELOPED LAND USE Name : Basin 1 Bypass: No GroundWater: No Pervious Land Use acre A B, Forest, Flat .275 Pervious Total 0.275 Impervious Land Use acre Impervious Total 0 Basin Total 0.275 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater ___________________________________________________________________ MITIGATED LAND USE Name : Bldg B Roof Bypass: No GroundWater: No MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-13 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Pervious Land Use acre Pervious Total 0 Impervious Land Use acre ROOF TOPS FLAT 0.275 Impervious Total 0.275 Basin Total 0.275 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater Gravel Trench Bed 1 Gravel Trench Bed 1 ___________________________________________________________________ Name : Gravel Trench Bed 1 Bottom Length: 120.00 ft. Bottom Width: 2.00 ft. Trench bottom slope 1: 0 To 1 Trench Left side slope 0: 0 To 1 Trench right side slope 2: 0 To 1 Material thickness of first layer: 1.5 Pour Space of material for first layer: 0.3 Material thickness of second layer: 0 Pour Space of material for second layer: 0 Material thickness of third layer: 0 Pour Space of material for third layer: 0 Infiltration On Infiltration rate: 28 Infiltration safety factor: 1 Total Volume Infiltrated (ac-ft.): 47.287 Total Volume Through Riser (ac-ft.): 0.002 Total Volume Through Facility (ac-ft.): 47.289 Percent Infiltrated: 100 Total Precip Applied to Facility: 0 Total Evap From Facility: 0 Discharge Structure Riser Height: 1.5 ft. Riser Diameter: 8 in. Element Flows To: Outlet 1 Outlet 2 ___________________________________________________________________ Gravel Trench Bed Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs) 0.0000 0.005 0.000 0.000 0.000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-14 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0278 0.005 0.000 0.000 0.155 0.0556 0.005 0.000 0.000 0.155 0.0833 0.005 0.000 0.000 0.155 0.1111 0.005 0.000 0.000 0.155 0.1389 0.005 0.000 0.000 0.155 0.1667 0.005 0.000 0.000 0.155 0.1944 0.005 0.000 0.000 0.155 0.2222 0.005 0.000 0.000 0.155 0.2500 0.005 0.000 0.000 0.155 0.2778 0.005 0.000 0.000 0.155 0.3056 0.005 0.000 0.000 0.155 0.3333 0.005 0.000 0.000 0.155 0.3611 0.005 0.000 0.000 0.155 0.3889 0.005 0.000 0.000 0.155 0.4167 0.005 0.000 0.000 0.155 0.4444 0.005 0.000 0.000 0.155 0.4722 0.005 0.000 0.000 0.155 0.5000 0.005 0.000 0.000 0.155 0.5278 0.005 0.000 0.000 0.155 0.5556 0.005 0.000 0.000 0.155 0.5833 0.005 0.001 0.000 0.155 0.6111 0.005 0.001 0.000 0.155 0.6389 0.005 0.001 0.000 0.155 0.6667 0.005 0.001 0.000 0.155 0.6944 0.005 0.001 0.000 0.155 0.7222 0.005 0.001 0.000 0.155 0.7500 0.005 0.001 0.000 0.155 0.7778 0.005 0.001 0.000 0.155 0.8056 0.005 0.001 0.000 0.155 0.8333 0.005 0.001 0.000 0.155 0.8611 0.005 0.001 0.000 0.155 0.8889 0.005 0.001 0.000 0.155 0.9167 0.005 0.001 0.000 0.155 0.9444 0.005 0.001 0.000 0.155 0.9722 0.005 0.001 0.000 0.155 1.0000 0.005 0.001 0.000 0.155 1.0278 0.005 0.001 0.000 0.155 1.0556 0.005 0.001 0.000 0.155 1.0833 0.005 0.001 0.000 0.155 1.1111 0.005 0.001 0.000 0.155 1.1389 0.005 0.001 0.000 0.155 1.1667 0.005 0.001 0.000 0.155 1.1944 0.005 0.002 0.000 0.155 1.2222 0.005 0.002 0.000 0.155 1.2500 0.005 0.002 0.000 0.155 1.2778 0.005 0.002 0.000 0.155 1.3056 0.005 0.002 0.000 0.155 1.3333 0.005 0.002 0.000 0.155 1.3611 0.005 0.002 0.000 0.155 1.3889 0.005 0.002 0.000 0.155 1.4167 0.005 0.002 0.000 0.155 1.4444 0.005 0.002 0.000 0.155 1.4722 0.005 0.002 0.000 0.155 1.5000 0.005 0.002 0.000 0.155 1.5278 0.005 0.002 0.032 0.155 1.5556 0.005 0.002 0.092 0.155 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-15 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 1.5833 0.005 0.002 0.168 0.155 1.6111 0.005 0.003 0.255 0.155 1.6389 0.005 0.003 0.348 0.155 1.6667 0.005 0.003 0.441 0.155 1.6944 0.005 0.003 0.531 0.155 1.7222 0.005 0.003 0.610 0.155 1.7500 0.005 0.003 0.678 0.155 1.7778 0.005 0.004 0.730 0.155 1.8056 0.005 0.004 0.769 0.155 1.8333 0.005 0.004 0.799 0.155 1.8611 0.005 0.004 0.841 0.155 1.8889 0.005 0.004 0.873 0.155 1.9167 0.005 0.004 0.903 0.155 1.9444 0.005 0.004 0.933 0.155 1.9722 0.005 0.005 0.961 0.155 2.0000 0.005 0.005 0.989 0.155 2.0278 0.005 0.005 1.017 0.155 2.0556 0.005 0.005 1.043 0.155 2.0833 0.005 0.005 1.069 0.155 2.1111 0.005 0.005 1.094 0.155 2.1389 0.005 0.006 1.118 0.155 2.1667 0.005 0.006 1.143 0.155 2.1944 0.005 0.006 1.166 0.155 2.2222 0.005 0.006 1.189 0.155 2.2500 0.005 0.006 1.212 0.155 2.2778 0.005 0.006 1.234 0.155 2.3056 0.005 0.006 1.256 0.155 2.3333 0.005 0.007 1.277 0.155 2.3611 0.005 0.007 1.299 0.155 2.3889 0.005 0.007 1.319 0.155 2.4167 0.005 0.007 1.340 0.155 2.4444 0.005 0.007 1.360 0.155 2.4722 0.005 0.007 1.380 0.155 2.5000 0.005 0.008 1.399 0.155 ___________________________________________________________________ ___________________________________________________________________ ANALYSIS RESULTS Stream Protection Duration ___________________________________________________________________ Predeveloped Landuse Totals for POC #1 Total Pervious Area:0.275 Total Impervious Area:0 ___________________________________________________________________ Mitigated Landuse Totals for POC #1 Total Pervious Area:0 Total Impervious Area:0.275 ___________________________________________________________________ Flow Frequency Return Periods for Predeveloped. POC #1 Return Period Flow(cfs) MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-16 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 2 year 0.000417 5 year 0.001158 10 year 0.002134 25 year 0.004358 50 year 0.007156 100 year 0.011446 Flow Frequency Return Periods for Mitigated. POC #1 Return Period Flow(cfs) 2 year 0 5 year 0 10 year 0 25 year 0 50 year 0 100 year 0 ___________________________________________________________________ Stream Protection Duration Annual Peaks for Predeveloped and Mitigated. POC #1 Year Predeveloped Mitigated 1956 0.001 0.000 1957 0.000 0.000 1958 0.000 0.000 1959 0.000 0.000 1960 0.000 0.000 1961 0.001 0.000 1962 0.000 0.000 1963 0.000 0.000 1964 0.000 0.000 1965 0.000 0.000 1966 0.000 0.000 1967 0.000 0.000 1968 0.000 0.000 1969 0.000 0.000 1970 0.000 0.000 1971 0.002 0.000 1972 0.003 0.000 1973 0.000 0.000 1974 0.001 0.000 1975 0.000 0.000 1976 0.000 0.000 1977 0.000 0.000 1978 0.000 0.000 1979 0.000 0.000 1980 0.000 0.000 1981 0.001 0.000 1982 0.001 0.000 1983 0.000 0.000 1984 0.000 0.000 1985 0.000 0.000 1986 0.001 0.000 1987 0.000 0.000 1988 0.000 0.000 1989 0.000 0.000 1990 0.002 0.023 1991 0.002 0.000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-17 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 1992 0.000 0.000 1993 0.000 0.000 1994 0.000 0.000 1995 0.001 0.000 1996 0.003 0.000 1997 0.002 0.000 1998 0.001 0.000 1999 0.000 0.000 2000 0.000 0.000 2001 0.000 0.000 2002 0.001 0.000 2003 0.000 0.000 2004 0.014 0.000 2005 0.002 0.037 2006 0.010 0.000 2007 0.004 0.000 2008 0.000 0.000 ___________________________________________________________________ Stream Protection Duration Ranked Annual Peaks for Predeveloped and Mitigated. POC #1 Rank Predeveloped Mitigated 1 0.0139 0.0372 2 0.0100 0.0228 3 0.0043 0.0000 4 0.0033 0.0000 5 0.0029 0.0000 6 0.0024 0.0000 7 0.0022 0.0000 8 0.0022 0.0000 9 0.0018 0.0000 10 0.0016 0.0000 11 0.0014 0.0000 12 0.0014 0.0000 13 0.0014 0.0000 14 0.0010 0.0000 15 0.0008 0.0000 16 0.0006 0.0000 17 0.0005 0.0000 18 0.0005 0.0000 19 0.0005 0.0000 20 0.0005 0.0000 21 0.0004 0.0000 22 0.0003 0.0000 23 0.0003 0.0000 24 0.0003 0.0000 25 0.0002 0.0000 26 0.0002 0.0000 27 0.0002 0.0000 28 0.0002 0.0000 29 0.0002 0.0000 30 0.0002 0.0000 31 0.0002 0.0000 32 0.0002 0.0000 33 0.0002 0.0000 34 0.0002 0.0000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-18 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 35 0.0002 0.0000 36 0.0002 0.0000 37 0.0002 0.0000 38 0.0002 0.0000 39 0.0002 0.0000 40 0.0002 0.0000 41 0.0002 0.0000 42 0.0002 0.0000 43 0.0002 0.0000 44 0.0002 0.0000 45 0.0002 0.0000 46 0.0002 0.0000 47 0.0002 0.0000 48 0.0002 0.0000 49 0.0002 0.0000 50 0.0002 0.0000 51 0.0002 0.0000 52 0.0002 0.0000 53 0.0002 0.0000 ___________________________________________________________________ Stream Protection Duration POC #1 The Facility FAILED Facility FAILED duration standard for 1+ flows. Flow(cfs) Predev Mit Percentage Pass/Fail 0.0002 699 5 0 Pass 0.0003 148 5 3 Pass 0.0003 120 5 4 Pass 0.0004 98 5 5 Pass 0.0005 80 5 6 Pass 0.0006 61 5 8 Pass 0.0006 51 5 9 Pass 0.0007 48 5 10 Pass 0.0008 44 5 11 Pass 0.0008 38 5 13 Pass 0.0009 37 5 13 Pass 0.0010 33 5 15 Pass 0.0011 32 5 15 Pass 0.0011 30 5 16 Pass 0.0012 29 5 17 Pass 0.0013 27 5 18 Pass 0.0013 26 5 19 Pass 0.0014 22 5 22 Pass 0.0015 19 5 26 Pass 0.0015 18 5 27 Pass 0.0016 16 5 31 Pass 0.0017 16 5 31 Pass 0.0018 14 5 35 Pass 0.0018 13 5 38 Pass 0.0019 11 5 45 Pass 0.0020 9 5 55 Pass 0.0020 9 5 55 Pass 0.0021 9 5 55 Pass MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-19 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0022 9 5 55 Pass 0.0022 8 5 62 Pass 0.0023 6 5 83 Pass 0.0024 5 5 100 Pass 0.0025 5 5 100 Pass 0.0025 5 5 100 Pass 0.0026 5 5 100 Pass 0.0027 5 5 100 Pass 0.0027 5 5 100 Pass 0.0028 5 5 100 Pass 0.0029 5 5 100 Pass 0.0029 4 5 125 Fail 0.0030 4 5 125 Fail 0.0031 4 5 125 Fail 0.0032 4 5 125 Fail 0.0032 4 5 125 Fail 0.0033 4 5 125 Fail 0.0034 3 5 166 Fail 0.0034 3 5 166 Fail 0.0035 3 5 166 Fail 0.0036 3 5 166 Fail 0.0036 3 5 166 Fail 0.0037 3 5 166 Fail 0.0038 3 5 166 Fail 0.0039 3 5 166 Fail 0.0039 3 5 166 Fail 0.0040 3 5 166 Fail 0.0041 3 5 166 Fail 0.0041 3 5 166 Fail 0.0042 3 5 166 Fail 0.0043 3 5 166 Fail 0.0043 2 5 250 Fail 0.0044 2 5 250 Fail 0.0045 2 5 250 Fail 0.0046 2 5 250 Fail 0.0046 2 5 250 Fail 0.0047 2 5 250 Fail 0.0048 2 5 250 Fail 0.0048 2 5 250 Fail 0.0049 2 5 250 Fail 0.0050 2 5 250 Fail 0.0051 2 5 250 Fail 0.0051 2 5 250 Fail 0.0052 2 5 250 Fail 0.0053 2 5 250 Fail 0.0053 2 5 250 Fail 0.0054 2 5 250 Fail 0.0055 2 5 250 Fail 0.0055 2 5 250 Fail 0.0056 2 5 250 Fail 0.0057 2 5 250 Fail 0.0058 2 5 250 Fail 0.0058 2 5 250 Fail 0.0059 2 5 250 Fail 0.0060 2 5 250 Fail 0.0060 2 5 250 Fail MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-20 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0061 2 5 250 Fail 0.0062 2 5 250 Fail 0.0062 2 5 250 Fail 0.0063 2 5 250 Fail 0.0064 2 5 250 Fail 0.0065 2 5 250 Fail 0.0065 2 5 250 Fail 0.0066 2 5 250 Fail 0.0067 2 5 250 Fail 0.0067 2 5 250 Fail 0.0068 2 5 250 Fail 0.0069 2 5 250 Fail 0.0069 2 5 250 Fail 0.0070 2 5 250 Fail 0.0071 2 5 250 Fail 0.0072 2 5 250 Fail _____________________________________________________ The development has an increase in flow durations from 1/2 Predeveloped 2 year flow to the 2 year flow or more than a 10% increase from the 2 year to the 50 year flow. The development has an increase in flow durations for more than 50% of the flows for the range of the duration analysis. ___________________________________________________________________ Water Quality BMP Flow and Volume for POC #1 On-line facility volume: 0 acre-feet On-line facility target flow: 0 cfs. Adjusted for 15 min: 0 cfs. Off-line facility target flow: 0 cfs. Adjusted for 15 min: 0 cfs. ___________________________________________________________________ LID Report LID Technique Used for Total Volume Volume Infiltration Cumulative Percent Water Quality Percent Comment Treatment? Needs Through Volume Volume Volume Water Quality Treatment Facility (ac-ft.) Infiltration Infiltrated Treated (ac-ft) (ac-ft) Credit Gravel Trench Bed 1 POC N 43.03 N 99.99 Total Volume Infiltrated 43.03 0.00 0.00 99.99 0.00 0% No Treat. Credit Compliance with LID Standard 8 Duration Analysis Result = Failed ___________________________________________________________________ Perlnd and Implnd Changes No changes have been made. ___________________________________________________________________ This program and accompanying documentation are provided 'as-is' without warranty of any kind. The entire risk regarding the performance and results of this program is assumed by End User. Clear Creek Solutions Inc. and the governmental licensee or sublicensees disclaim all warranties, either expressed or implied, including but not limited to implied warranties of program and accompanying documentation. In no event shall Clear Creek Solutions Inc. be liable for any MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-21 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx damages whatsoever (including without limitation to damages for loss of business profits, loss of business information, business interruption, and the like) arising out of the use of, or inability to use this program even if Clear Creek Solutions Inc. or their authorized representatives have been advised of the possibility of such damages. Software Copyright © by : Clear Creek Solutions, Inc. 2005-2023; All Rights Reserved. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-22 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx WWHM2012 PROJECT REPORT ___________________________________________________________________ Project Name: Sub Basin 3 Bioretention Site Name: Site Address: City : Report Date: 8/28/2023 Gage : Lake Lawrence Data Start : 1955/10/01 Data End : 2008/09/30 Precip Scale: 0.86 Version Date: 2021/08/18 Version : 4.2.18 ___________________________________________________________________ Low Flow Threshold for POC 1 : 50 Percent of the 2 Year ___________________________________________________________________ High Flow Threshold for POC 1: 50 year ___________________________________________________________________ PREDEVELOPED LAND USE MITIGATED LAND USE Name : Basin 1 Bypass: No GroundWater: No Pervious Land Use acre A B, Lawn, Flat .015 C, Pasture, Flat .01 Pervious Total 0.025 Impervious Land Use acre ROADS FLAT 0.114 SIDEWALKS FLAT 0.003 Impervious Total 0.117 Basin Total 0.142 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater Surface retention 1 Surface retention 1 ___________________________________________________________________ Name : Bioretention 1 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-23 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Bottom Length: 25.00 ft. Bottom Width: 10.00 ft. Material thickness of first layer: 1.5 Material type for first layer: SMMWW 6 in/hr KSat Safety Factor of 2 Material thickness of second layer: 0 Material type for second layer: Sand Material thickness of third layer: 0 Material type for third layer: GRAVEL Infiltration On Infiltration rate: 28 per hour Infiltration safety factor: 1 Total Volume Infiltrated (ac-ft.): 22.191 Total Volume Through Riser (ac-ft.): 0 Total Volume Through Facility (ac-ft.): 22.191 Percent Infiltrated: 100% Infiltration Achieved Total Precip Applied to Facility: 1.637 Total Evap From Facility: 0.678 Underdrain not used Discharge Structure Riser Height: 1 ft. Riser Diameter: 8 in. Element Flows To: Outlet 1 Outlet 2 ___________________________________________________________________ Bioretention 1 Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs) 0.0000 0.0148 0.0000 0.0000 0.0000 0.0330 0.0147 0.0001 0.0000 0.0000 0.0659 0.0145 0.0002 0.0000 0.0000 0.0989 0.0142 0.0002 0.0000 0.0000 0.1319 0.0140 0.0003 0.0000 0.0000 0.1648 0.0138 0.0004 0.0000 0.0001 0.1978 0.0135 0.0005 0.0000 0.0002 0.2308 0.0133 0.0006 0.0000 0.0003 0.2637 0.0131 0.0007 0.0000 0.0005 0.2967 0.0128 0.0008 0.0000 0.0006 0.3297 0.0126 0.0009 0.0000 0.0008 0.3626 0.0124 0.0010 0.0000 0.0010 0.3956 0.0122 0.0011 0.0000 0.0013 0.4286 0.0120 0.0012 0.0000 0.0015 0.4615 0.0117 0.0013 0.0000 0.0019 0.4945 0.0115 0.0014 0.0000 0.0022 0.5275 0.0113 0.0015 0.0000 0.0026 0.5604 0.0111 0.0016 0.0000 0.0030 0.5934 0.0109 0.0017 0.0000 0.0034 0.6264 0.0107 0.0019 0.0000 0.0039 0.6593 0.0105 0.0020 0.0000 0.0045 0.6923 0.0103 0.0021 0.0000 0.0051 0.7253 0.0101 0.0022 0.0000 0.0057 0.7582 0.0099 0.0024 0.0000 0.0063 0.7912 0.0097 0.0025 0.0000 0.0070 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-24 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.8242 0.0095 0.0026 0.0000 0.0078 0.8571 0.0093 0.0028 0.0000 0.0086 0.8901 0.0091 0.0029 0.0000 0.0094 0.9231 0.0089 0.0030 0.0000 0.0103 0.9560 0.0087 0.0032 0.0000 0.0113 0.9890 0.0085 0.0033 0.0000 0.0122 1.0220 0.0083 0.0035 0.0000 0.0133 1.0549 0.0081 0.0036 0.0000 0.0144 1.0879 0.0080 0.0038 0.0000 0.0155 1.1209 0.0078 0.0040 0.0000 0.0167 1.1538 0.0076 0.0041 0.0000 0.0180 1.1868 0.0074 0.0043 0.0000 0.0193 1.2198 0.0072 0.0045 0.0000 0.0206 1.2527 0.0071 0.0046 0.0000 0.0220 1.2857 0.0069 0.0048 0.0000 0.0235 1.3187 0.0067 0.0050 0.0000 0.0250 1.3516 0.0066 0.0052 0.0000 0.0266 1.3846 0.0064 0.0053 0.0000 0.0282 1.4176 0.0062 0.0055 0.0000 0.0299 1.4505 0.0061 0.0057 0.0000 0.0317 1.4835 0.0059 0.0059 0.0000 0.0334 1.5000 0.0057 0.0060 0.0000 0.0579 Surface retention 1 Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) To Amended(cfs) Wetted Surface 1.5000 0.0148 0.0060 0.0000 0.0347 0.0000 1.5330 0.0151 0.0065 0.0000 0.0347 0.0000 1.5659 0.0153 0.0070 0.0000 0.0362 0.0000 1.5989 0.0156 0.0075 0.0000 0.0370 0.0000 1.6319 0.0158 0.0080 0.0000 0.0378 0.0000 1.6648 0.0161 0.0086 0.0000 0.0385 0.0000 1.6978 0.0163 0.0091 0.0000 0.0393 0.0000 1.7308 0.0166 0.0096 0.0000 0.0401 0.0000 1.7637 0.0168 0.0102 0.0000 0.0408 0.0000 1.7967 0.0171 0.0107 0.0000 0.0416 0.0000 1.8297 0.0173 0.0113 0.0000 0.0424 0.0000 1.8626 0.0176 0.0119 0.0000 0.0431 0.0000 1.8956 0.0178 0.0125 0.0000 0.0439 0.0000 1.9286 0.0181 0.0131 0.0000 0.0446 0.0000 1.9615 0.0184 0.0137 0.0000 0.0454 0.0000 1.9945 0.0186 0.0143 0.0000 0.0462 0.0000 2.0275 0.0189 0.0149 0.0000 0.0469 0.0000 2.0604 0.0192 0.0155 0.0000 0.0477 0.0000 2.0934 0.0195 0.0162 0.0000 0.0485 0.0000 2.1264 0.0197 0.0168 0.0000 0.0492 0.0000 2.1593 0.0200 0.0175 0.0000 0.0500 0.0000 2.1923 0.0203 0.0181 0.0000 0.0507 0.0000 2.2253 0.0206 0.0188 0.0000 0.0515 0.0000 2.2582 0.0208 0.0195 0.0000 0.0523 0.0000 2.2912 0.0211 0.0202 0.0000 0.0530 0.0000 2.3242 0.0214 0.0209 0.0000 0.0538 0.0000 2.3571 0.0217 0.0216 0.0000 0.0546 0.0000 2.3901 0.0220 0.0223 0.0000 0.0553 0.0000 2.4231 0.0223 0.0230 0.0000 0.0561 0.0000 2.4560 0.0226 0.0238 0.0000 0.0569 0.0000 2.4890 0.0229 0.0245 0.0000 0.0576 0.0000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-25 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 2.5220 0.0232 0.0253 0.0230 0.0579 0.0000 2.5549 0.0235 0.0260 0.0908 0.0579 0.0000 2.5879 0.0238 0.0268 0.1820 0.0579 0.0000 2.6209 0.0241 0.0276 0.2875 0.0579 0.0000 2.6538 0.0244 0.0284 0.3989 0.0579 0.0000 2.6868 0.0247 0.0292 0.5072 0.0579 0.0000 2.7198 0.0250 0.0300 0.6044 0.0579 0.0000 2.7527 0.0253 0.0309 0.6839 0.0579 0.0000 2.7857 0.0256 0.0317 0.7429 0.0579 0.0000 2.8187 0.0259 0.0325 0.7843 0.0579 0.0000 2.8516 0.0262 0.0334 0.8301 0.0579 0.0000 2.8846 0.0265 0.0343 0.8681 0.0579 0.0000 2.9176 0.0268 0.0352 0.9046 0.0579 0.0000 2.9505 0.0272 0.0360 0.9396 0.0579 0.0000 2.9835 0.0275 0.0369 0.9734 0.0579 0.0000 3.0000 0.0276 0.0374 1.0060 0.0579 0.0000 ___________________________________________________________________ Name : Surface retention 1 Element Flows To: Outlet 1 Outlet 2 Bioretention 1 ___________________________________________________________________ ___________________________________________________________________ ANALYSIS RESULTS POC #1 was not reported because POC must exist in both scenarios and both scenarios must have been run.Perlnd and Implnd Changes No changes have been made. ___________________________________________________________________ This program and accompanying documentation are provided 'as-is' without warranty of any kind. The entire risk regarding the performance and results of this program is assumed by End User. Clear Creek Solutions Inc. and the governmental licensee or sublicensees disclaim all warranties, either expressed or implied, including but not limited to implied warranties of program and accompanying documentation. In no event shall Clear Creek Solutions Inc. be liable for any damages whatsoever (including without limitation to damages for loss of business profits, loss of business information, business interruption, and the like) arising out of the use of, or inability to use this program even if Clear Creek Solutions Inc. or their authorized representatives have been advised of the possibility of such damages. Software Copyright © by : Clear Creek Solutions, Inc. 2005-2023; All Rights Reserved. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-26 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx WWHM2012 PROJECT REPORT ___________________________________________________________________ Project Name: SubBasin 4: Park-Bio-ARMO01 Site Name: Armor Storage Site Address: 10403 Grove Road SE City : Yelm, WA Report Date: 8/28/2023 Gage : Lake Lawrence Data Start : 1955/10/01 Data End : 2008/09/30 Precip Scale: 0.86 Version Date: 2023/01/27 Version : 4.2.19 ___________________________________________________________________ Low Flow Threshold for POC 1 : 50 Percent of the 2 Year ___________________________________________________________________ High Flow Threshold for POC 1: 50 year ___________________________________________________________________ PREDEVELOPED LAND USE Name : Basin 1 Bypass: No GroundWater: No Pervious Land Use acre A B, Forest, Flat 1.72 Pervious Total 1.72 Impervious Land Use acre Impervious Total 0 Basin Total 1.72 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater ___________________________________________________________________ MITIGATED LAND USE Name : Sub-Basin 4: South Parking Lot Bypass: No GroundWater: No MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-27 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Pervious Land Use acre A B, Pasture, Flat 1.11 Pervious Total 1.11 Impervious Land Use acre ROADS FLAT 0.6 SIDEWALKS FLAT 0.01 Impervious Total 0.61 Basin Total 1.72 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater Surface retention 1 Surface retention 1 ___________________________________________________________________ Name : Bioretention 1 Bottom Length: 250.00 ft. Bottom Width: 7.00 ft. Material thickness of first layer: 1.5 Material type for first layer: SMMWW 3 in/hr Material thickness of second layer: 1.5 Material type for second layer: Sand Material thickness of third layer: 0 Material type for third layer: GRAVEL Infiltration On Infiltration rate: 28 Factored infiltration rate from geotechnical report Infiltration safety factor: 1 Total Volume Infiltrated (ac-ft.): 117.409 Total Volume Through Riser (ac-ft.): 0 Total Volume Through Facility (ac-ft.): 117.409 Percent Infiltrated: 100 Total Precip Applied to Facility: 16.259 Total Evap From Facility: 6.285 Underdrain not used Discharge Structure Riser Height: 1 ft. Riser Diameter: 12 in. Element Flows To: Outlet 1 Outlet 2 ___________________________________________________________________ Bioretention 1 Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs) 0.0000 0.1538 0.0000 0.0000 0.0000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-28 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0495 0.1525 0.0005 0.0000 0.0000 0.0989 0.1505 0.0009 0.0000 0.0000 0.1484 0.1485 0.0015 0.0000 0.0000 0.1978 0.1465 0.0020 0.0000 0.0000 0.2473 0.1445 0.0025 0.0000 0.0000 0.2967 0.1426 0.0031 0.0000 0.0005 0.3462 0.1406 0.0037 0.0000 0.0007 0.3956 0.1386 0.0043 0.0000 0.0009 0.4451 0.1367 0.0049 0.0000 0.0012 0.4945 0.1347 0.0055 0.0000 0.0014 0.5440 0.1328 0.0062 0.0000 0.0018 0.5934 0.1308 0.0069 0.0000 0.0020 0.6429 0.1289 0.0076 0.0000 0.0027 0.6923 0.1269 0.0083 0.0000 0.0029 0.7418 0.1250 0.0091 0.0000 0.0038 0.7912 0.1230 0.0098 0.0000 0.0039 0.8407 0.1211 0.0106 0.0000 0.0051 0.8901 0.1192 0.0114 0.0000 0.0051 0.9396 0.1173 0.0123 0.0000 0.0065 0.9890 0.1153 0.0131 0.0000 0.0066 1.0385 0.1134 0.0140 0.0000 0.0081 1.0879 0.1115 0.0149 0.0000 0.0085 1.1374 0.1096 0.0158 0.0000 0.0100 1.1868 0.1077 0.0167 0.0000 0.0106 1.2363 0.1058 0.0177 0.0000 0.0121 1.2857 0.1039 0.0186 0.0000 0.0130 1.3352 0.1020 0.0196 0.0000 0.0144 1.3846 0.1001 0.0206 0.0000 0.0157 1.4341 0.0983 0.0217 0.0000 0.0170 1.4835 0.0964 0.0227 0.0000 0.0187 1.5330 0.0945 0.0237 0.0000 0.0199 1.5824 0.0926 0.0246 0.0000 0.0221 1.6319 0.0908 0.0256 0.0000 0.0230 1.6813 0.0889 0.0266 0.0000 0.0258 1.7308 0.0871 0.0276 0.0000 0.0265 1.7802 0.0852 0.0287 0.0000 0.0299 1.8297 0.0834 0.0297 0.0000 0.0302 1.8791 0.0815 0.0308 0.0000 0.0342 1.9286 0.0797 0.0319 0.0000 0.0343 1.9780 0.0778 0.0330 0.0000 0.0385 2.0275 0.0760 0.0342 0.0000 0.0391 2.0769 0.0742 0.0353 0.0000 0.0432 2.1264 0.0723 0.0365 0.0000 0.0443 2.1758 0.0705 0.0377 0.0000 0.0481 2.2253 0.0687 0.0389 0.0000 0.0499 2.2747 0.0669 0.0401 0.0000 0.0534 2.3242 0.0651 0.0413 0.0000 0.0559 2.3736 0.0633 0.0426 0.0000 0.0590 2.4231 0.0615 0.0439 0.0000 0.0622 2.4725 0.0597 0.0452 0.0000 0.0649 2.5220 0.0579 0.0465 0.0000 0.0691 2.5714 0.0561 0.0479 0.0000 0.0712 2.6209 0.0543 0.0492 0.0000 0.0763 2.6703 0.0525 0.0506 0.0000 0.0778 2.7198 0.0508 0.0520 0.0000 0.0840 2.7692 0.0490 0.0534 0.0000 0.0847 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-29 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 2.8187 0.0472 0.0549 0.0000 0.0919 2.8681 0.0454 0.0563 0.0000 0.0939 2.9176 0.0437 0.0578 0.0000 0.0939 2.9670 0.0419 0.0593 0.0000 0.0939 3.0000 0.0402 0.0603 0.0000 0.2025 Surface retention 1 Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) To Amended(cfs) Wetted Surface 3.0000 0.1538 0.0603 0.0000 0.1215 0.0000 3.0495 0.1558 0.0680 0.0000 0.1215 0.0000 3.0989 0.1578 0.0757 0.0000 0.1295 0.0000 3.1484 0.1598 0.0836 0.0000 0.1335 0.0000 3.1978 0.1618 0.0915 0.0000 0.1376 0.0000 3.2473 0.1638 0.0996 0.0000 0.1416 0.0000 3.2967 0.1659 0.1077 0.0000 0.1456 0.0000 3.3462 0.1679 0.1160 0.0000 0.1496 0.0000 3.3956 0.1699 0.1243 0.0000 0.1536 0.0000 3.4451 0.1719 0.1328 0.0000 0.1576 0.0000 3.4945 0.1740 0.1413 0.0000 0.1616 0.0000 3.5440 0.1760 0.1500 0.0000 0.1656 0.0000 3.5934 0.1781 0.1587 0.0000 0.1696 0.0000 3.6429 0.1801 0.1676 0.0000 0.1736 0.0000 3.6923 0.1821 0.1765 0.0000 0.1776 0.0000 3.7418 0.1842 0.1856 0.0000 0.1816 0.0000 3.7912 0.1863 0.1948 0.0000 0.1856 0.0000 3.8407 0.1883 0.2040 0.0000 0.1896 0.0000 3.8901 0.1904 0.2134 0.0000 0.1936 0.0000 3.9396 0.1925 0.2229 0.0000 0.1976 0.0000 3.9890 0.1945 0.2324 0.0000 0.2017 0.0000 4.0385 0.1966 0.2421 0.0800 0.2057 0.0000 4.0879 0.1987 0.2519 0.2754 0.2097 0.0000 4.1374 0.2008 0.2617 0.5323 0.2137 0.0000 4.1868 0.2029 0.2717 0.8261 0.2177 0.0000 4.2363 0.2050 0.2818 1.1332 0.2217 0.0000 4.2857 0.2071 0.2920 1.4294 0.2257 0.0000 4.3352 0.2092 0.3023 1.6924 0.2297 0.0000 4.3846 0.2113 0.3127 1.9054 0.2337 0.0000 4.4341 0.2134 0.3232 2.0620 0.2377 0.0000 4.4835 0.2155 0.3338 2.1721 0.2417 0.0000 4.5000 0.2162 0.3374 2.2994 0.2431 0.0000 ___________________________________________________________________ Name : Surface retention 1 Element Flows To: Outlet 1 Outlet 2 Bioretention 1 ___________________________________________________________________ ___________________________________________________________________ ANALYSIS RESULTS Stream Protection Duration MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-30 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx ___________________________________________________________________ Predeveloped Landuse Totals for POC #1 Total Pervious Area:1.72 Total Impervious Area:0 ___________________________________________________________________ Mitigated Landuse Totals for POC #1 Total Pervious Area:1.11 Total Impervious Area:0.61 ___________________________________________________________________ Flow Frequency Return Periods for Predeveloped. POC #1 Return Period Flow(cfs) 2 year 0.002609 5 year 0.00724 10 year 0.013348 25 year 0.027258 50 year 0.044756 100 year 0.071591 Flow Frequency Return Periods for Mitigated. POC #1 Return Period Flow(cfs) 2 year 0 5 year 0 10 year 0 25 year 0 50 year 0 100 year 0 ___________________________________________________________________ Stream Protection Duration Annual Peaks for Predeveloped and Mitigated. POC #1 Year Predeveloped Mitigated 1956 0.009 0.000 1957 0.002 0.000 1958 0.001 0.000 1959 0.001 0.000 1960 0.001 0.000 1961 0.006 0.000 1962 0.001 0.000 1963 0.001 0.000 1964 0.001 0.000 1965 0.001 0.000 1966 0.001 0.000 1967 0.002 0.000 1968 0.001 0.000 1969 0.001 0.000 1970 0.001 0.000 1971 0.011 0.000 1972 0.018 0.000 1973 0.001 0.000 1974 0.005 0.000 1975 0.001 0.000 1976 0.002 0.000 1977 0.001 0.000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-31 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 1978 0.002 0.000 1979 0.001 0.000 1980 0.001 0.000 1981 0.003 0.000 1982 0.004 0.000 1983 0.001 0.000 1984 0.001 0.000 1985 0.001 0.000 1986 0.003 0.000 1987 0.003 0.000 1988 0.001 0.000 1989 0.001 0.000 1990 0.010 0.000 1991 0.015 0.000 1992 0.001 0.000 1993 0.001 0.000 1994 0.001 0.000 1995 0.009 0.000 1996 0.021 0.000 1997 0.014 0.000 1998 0.003 0.000 1999 0.001 0.000 2000 0.001 0.000 2001 0.001 0.000 2002 0.009 0.000 2003 0.001 0.000 2004 0.087 0.000 2005 0.014 0.000 2006 0.063 0.000 2007 0.027 0.000 2008 0.001 0.000 ___________________________________________________________________ Stream Protection Duration Ranked Annual Peaks for Predeveloped and Mitigated. POC #1 Rank Predeveloped Mitigated 1 0.0871 0.0000 2 0.0626 0.0000 3 0.0270 0.0000 4 0.0208 0.0000 5 0.0182 0.0000 6 0.0149 0.0000 7 0.0140 0.0000 8 0.0137 0.0000 9 0.0113 0.0000 10 0.0098 0.0000 11 0.0088 0.0000 12 0.0086 0.0000 13 0.0085 0.0000 14 0.0062 0.0000 15 0.0048 0.0000 16 0.0035 0.0000 17 0.0033 0.0000 18 0.0032 0.0000 19 0.0032 0.0000 20 0.0030 0.0000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-32 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 21 0.0022 0.0000 22 0.0019 0.0000 23 0.0019 0.0000 24 0.0019 0.0000 25 0.0014 0.0000 26 0.0014 0.0000 27 0.0014 0.0000 28 0.0014 0.0000 29 0.0014 0.0000 30 0.0014 0.0000 31 0.0014 0.0000 32 0.0014 0.0000 33 0.0014 0.0000 34 0.0014 0.0000 35 0.0014 0.0000 36 0.0014 0.0000 37 0.0014 0.0000 38 0.0014 0.0000 39 0.0014 0.0000 40 0.0014 0.0000 41 0.0014 0.0000 42 0.0014 0.0000 43 0.0014 0.0000 44 0.0013 0.0000 45 0.0013 0.0000 46 0.0013 0.0000 47 0.0013 0.0000 48 0.0013 0.0000 49 0.0013 0.0000 50 0.0013 0.0000 51 0.0013 0.0000 52 0.0012 0.0000 53 0.0012 0.0000 ___________________________________________________________________ Stream Protection Duration POC #1 The Facility PASSED The Facility PASSED. Flow(cfs) Predev Mit Percentage Pass/Fail 0.0013 0 0 0 Pass 0.0017 0 0 0 Pass 0.0022 0 0 0 Pass 0.0026 0 0 0 Pass 0.0031 0 0 0 Pass 0.0035 0 0 0 Pass 0.0039 0 0 0 Pass 0.0044 0 0 0 Pass 0.0048 0 0 0 Pass 0.0053 0 0 0 Pass 0.0057 0 0 0 Pass 0.0061 0 0 0 Pass 0.0066 0 0 0 Pass 0.0070 0 0 0 Pass MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-33 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0074 0 0 0 Pass 0.0079 0 0 0 Pass 0.0083 0 0 0 Pass 0.0088 0 0 0 Pass 0.0092 0 0 0 Pass 0.0096 0 0 0 Pass 0.0101 0 0 0 Pass 0.0105 0 0 0 Pass 0.0110 0 0 0 Pass 0.0114 0 0 0 Pass 0.0118 0 0 0 Pass 0.0123 0 0 0 Pass 0.0127 0 0 0 Pass 0.0132 0 0 0 Pass 0.0136 0 0 0 Pass 0.0140 0 0 0 Pass 0.0145 0 0 0 Pass 0.0149 0 0 0 Pass 0.0153 0 0 0 Pass 0.0158 0 0 0 Pass 0.0162 0 0 0 Pass 0.0167 0 0 0 Pass 0.0171 0 0 0 Pass 0.0175 0 0 0 Pass 0.0180 0 0 0 Pass 0.0184 0 0 0 Pass 0.0189 0 0 0 Pass 0.0193 0 0 0 Pass 0.0197 0 0 0 Pass 0.0202 0 0 0 Pass 0.0206 0 0 0 Pass 0.0211 0 0 0 Pass 0.0215 0 0 0 Pass 0.0219 0 0 0 Pass 0.0224 0 0 0 Pass 0.0228 0 0 0 Pass 0.0232 0 0 0 Pass 0.0237 0 0 0 Pass 0.0241 0 0 0 Pass 0.0246 0 0 0 Pass 0.0250 0 0 0 Pass 0.0254 0 0 0 Pass 0.0259 0 0 0 Pass 0.0263 0 0 0 Pass 0.0268 0 0 0 Pass 0.0272 0 0 0 Pass 0.0276 0 0 0 Pass 0.0281 0 0 0 Pass 0.0285 0 0 0 Pass 0.0290 0 0 0 Pass 0.0294 0 0 0 Pass 0.0298 0 0 0 Pass 0.0303 0 0 0 Pass 0.0307 0 0 0 Pass 0.0311 0 0 0 Pass 0.0316 0 0 0 Pass MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-34 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.0320 0 0 0 Pass 0.0325 0 0 0 Pass 0.0329 0 0 0 Pass 0.0333 0 0 0 Pass 0.0338 0 0 0 Pass 0.0342 0 0 0 Pass 0.0347 0 0 0 Pass 0.0351 0 0 0 Pass 0.0355 0 0 0 Pass 0.0360 0 0 0 Pass 0.0364 0 0 0 Pass 0.0369 0 0 0 Pass 0.0373 0 0 0 Pass 0.0377 0 0 0 Pass 0.0382 0 0 0 Pass 0.0386 0 0 0 Pass 0.0391 0 0 0 Pass 0.0395 0 0 0 Pass 0.0399 0 0 0 Pass 0.0404 0 0 0 Pass 0.0408 0 0 0 Pass 0.0412 0 0 0 Pass 0.0417 0 0 0 Pass 0.0421 0 0 0 Pass 0.0426 0 0 0 Pass 0.0430 0 0 0 Pass 0.0434 0 0 0 Pass 0.0439 0 0 0 Pass 0.0443 0 0 0 Pass 0.0448 0 0 0 Pass _____________________________________________________ ___________________________________________________________________ Water Quality BMP Flow and Volume for POC #1 On-line facility volume: 0.1089 acre-feet On-line facility target flow: 0.1298 cfs. Adjusted for 15 min: 0.1298 cfs. Off-line facility target flow: 0.0736 cfs. Adjusted for 15 min: 0.0736 cfs. ___________________________________________________________________ LID Report LID Technique Used for Total Volume Volume Infiltration Cumulative Percent Water Quality Percent Comment Treatment? Needs Through Volume Volume Volume Water Quality Treatment Facility (ac-ft.) Infiltration Infiltrated Treated (ac-ft) (ac-ft) Credit retention 1 POC N 106.84 N 100.00 Total Volume Infiltrated 106.84 0.00 0.00 100.00 0.00 0% No Treat. Credit Compliance with LID Standard 8 Duration Analysis Result = Passed ___________________________________________________________________ MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-35 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Perlnd and Implnd Changes No changes have been made. ___________________________________________________________________ This program and accompanying documentation are provided 'as-is' without warranty of any kind. The entire risk regarding the performance and results of this program is assumed by End User. Clear Creek Solutions Inc. and the governmental licensee or sublicensees disclaim all warranties, either expressed or implied, including but not limited to implied warranties of program and accompanying documentation. In no event shall Clear Creek Solutions Inc. be liable for any damages whatsoever (including without limitation to damages for loss of business profits, loss of business information, business interruption, and the like) arising out of the use of, or inability to use this program even if Clear Creek Solutions Inc. or their authorized representatives have been advised of the possibility of such damages. Software Copyright © by : Clear Creek Solutions, Inc. 2005-2023 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-36 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx WWHM2012 PROJECT REPORT ___________________________________________________________________ Project Name: SubBasin 5: Frontage Sub Basin Bioretention Cell Site Name: Site Address: City : Report Date: 8/28/2023 Gage : Lake Lawrence Data Start : 1955/10/01 Data End : 2008/09/30 Precip Scale: 0.86 Version Date: 2021/08/18 Version : 4.2.18 ___________________________________________________________________ Low Flow Threshold for POC 1 : 50 Percent of the 2 Year ___________________________________________________________________ High Flow Threshold for POC 1: 50 year ___________________________________________________________________ PREDEVELOPED LAND USE MITIGATED LAND USE Name : Basin 1 Bypass: No GroundWater: No Pervious Land Use acre A B, Pasture, Flat .13 Pervious Total 0.13 Impervious Land Use acre ROADS FLAT 0.22 SIDEWALKS FLAT 0.07 Impervious Total 0.29 Basin Total 0.42 ___________________________________________________________________ Element Flows To: Surface Interflow Groundwater Surface retention 1 Surface retention 1 ___________________________________________________________________ Name : Bioretention 1 Bottom Length: 522.00 ft. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-37 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Bottom Width: 0.50 ft. Material thickness of first layer: 1.5 Material type for first layer: SMMWW 3 in/hr KSat Safety Factor of 4 Material thickness of second layer: 0 Material type for second layer: Sand Material thickness of third layer: 0 Material type for third layer: GRAVEL Infiltration On Infiltration rate: 28 Infiltration safety factor: 1 Total Volume Infiltrated (ac-ft.): 62.864 Total Volume Through Riser (ac-ft.): 0.812 Total Volume Through Facility (ac-ft.): 63.676 Percent Infiltrated: 98.72 Remaining 1.28% Runoff Volume through riser to gravel trench Total Precip Applied to Facility: 16.482 Total Evap From Facility: 3.751 Underdrain not used Discharge Structure Riser Height: 0.5 ft. Riser Diameter: 8 in. Element Flows To: Outlet 1 Outlet 2 Gravel Trench Bed 1 ___________________________________________________________________ Bioretention 1 Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs) 0.0000 0.1158 0.0000 0.0000 0.0000 0.0275 0.1146 0.0001 0.0000 0.0000 0.0549 0.1125 0.0002 0.0000 0.0000 0.0824 0.1105 0.0003 0.0000 0.0000 0.1099 0.1085 0.0004 0.0000 0.0000 0.1374 0.1064 0.0006 0.0000 0.0000 0.1648 0.1044 0.0008 0.0000 0.0001 0.1923 0.1023 0.0010 0.0000 0.0001 0.2198 0.1003 0.0012 0.0000 0.0002 0.2473 0.0983 0.0015 0.0000 0.0002 0.2747 0.0962 0.0018 0.0000 0.0003 0.3022 0.0942 0.0020 0.0000 0.0003 0.3297 0.0922 0.0024 0.0000 0.0004 0.3571 0.0901 0.0027 0.0000 0.0005 0.3846 0.0881 0.0031 0.0000 0.0006 0.4121 0.0861 0.0035 0.0000 0.0007 0.4396 0.0841 0.0039 0.0000 0.0009 0.4670 0.0820 0.0043 0.0000 0.0010 0.4945 0.0800 0.0047 0.0000 0.0012 0.5220 0.0780 0.0052 0.0000 0.0013 0.5495 0.0760 0.0057 0.0000 0.0015 0.5769 0.0739 0.0062 0.0000 0.0017 0.6044 0.0719 0.0068 0.0000 0.0019 0.6319 0.0699 0.0073 0.0000 0.0021 0.6593 0.0679 0.0079 0.0000 0.0024 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-38 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 0.6868 0.0659 0.0085 0.0000 0.0026 0.7143 0.0639 0.0091 0.0000 0.0029 0.7418 0.0618 0.0098 0.0000 0.0031 0.7692 0.0598 0.0104 0.0000 0.0034 0.7967 0.0578 0.0111 0.0000 0.0038 0.8242 0.0558 0.0119 0.0000 0.0041 0.8516 0.0538 0.0126 0.0000 0.0044 0.8791 0.0518 0.0134 0.0000 0.0048 0.9066 0.0498 0.0141 0.0000 0.0052 0.9341 0.0478 0.0149 0.0000 0.0056 0.9615 0.0458 0.0158 0.0000 0.0060 0.9890 0.0438 0.0166 0.0000 0.0064 1.0165 0.0418 0.0175 0.0000 0.0069 1.0440 0.0398 0.0184 0.0000 0.0073 1.0714 0.0378 0.0193 0.0000 0.0078 1.0989 0.0358 0.0202 0.0000 0.0083 1.1264 0.0338 0.0212 0.0000 0.0089 1.1538 0.0318 0.0222 0.0000 0.0094 1.1813 0.0298 0.0232 0.0000 0.0100 1.2088 0.0278 0.0242 0.0000 0.0105 1.2363 0.0258 0.0253 0.0000 0.0111 1.2637 0.0238 0.0263 0.0000 0.0118 1.2912 0.0218 0.0274 0.0000 0.0124 1.3187 0.0199 0.0285 0.0000 0.0131 1.3462 0.0179 0.0297 0.0000 0.0138 1.3736 0.0159 0.0309 0.0000 0.0145 1.4011 0.0139 0.0320 0.0000 0.0152 1.4286 0.0119 0.0332 0.0000 0.0159 1.4560 0.0099 0.0345 0.0000 0.0167 1.4835 0.0080 0.0357 0.0000 0.0175 1.5000 0.0060 0.0365 0.0000 0.0242 Surface retention 1 Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) To Amended(cfs) Wetted Surface 1.5000 0.1158 0.0365 0.0000 0.0181 0.0000 1.5275 0.1179 0.0397 0.0000 0.0181 0.0000 1.5549 0.1199 0.0430 0.0000 0.0188 0.0000 1.5824 0.1219 0.0463 0.0000 0.0191 0.0000 1.6099 0.1240 0.0497 0.0000 0.0195 0.0000 1.6374 0.1260 0.0531 0.0000 0.0198 0.0000 1.6648 0.1281 0.0566 0.0000 0.0201 0.0000 1.6923 0.1302 0.0601 0.0000 0.0204 0.0000 1.7198 0.1322 0.0637 0.0000 0.0208 0.0000 1.7473 0.1343 0.0674 0.0000 0.0211 0.0000 1.7747 0.1363 0.0711 0.0000 0.0214 0.0000 1.8022 0.1384 0.0749 0.0000 0.0218 0.0000 1.8297 0.1404 0.0787 0.0000 0.0221 0.0000 1.8571 0.1425 0.0826 0.0000 0.0224 0.0000 1.8846 0.1446 0.0866 0.0000 0.0228 0.0000 1.9121 0.1466 0.0906 0.0000 0.0231 0.0000 1.9396 0.1487 0.0946 0.0000 0.0234 0.0000 1.9670 0.1508 0.0987 0.0000 0.0238 0.0000 1.9945 0.1528 0.1029 0.0000 0.0241 0.0000 2.0220 0.1549 0.1071 0.0230 0.0242 0.0000 2.0495 0.1570 0.1114 0.0776 0.0242 0.0000 2.0769 0.1590 0.1157 0.1496 0.0242 0.0000 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-39 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 2.1044 0.1611 0.1201 0.2335 0.0242 0.0000 2.1319 0.1632 0.1246 0.3244 0.0242 0.0000 2.1593 0.1653 0.1291 0.4174 0.0242 0.0000 2.1868 0.1673 0.1337 0.5072 0.0242 0.0000 2.2143 0.1694 0.1383 0.5893 0.0242 0.0000 2.2418 0.1715 0.1430 0.6596 0.0242 0.0000 2.2692 0.1736 0.1477 0.7159 0.0242 0.0000 2.2967 0.1756 0.1525 0.7583 0.0242 0.0000 2.3242 0.1777 0.1574 0.7901 0.0242 0.0000 2.3516 0.1798 0.1623 0.8301 0.0242 0.0000 2.3791 0.1819 0.1673 0.8619 0.0242 0.0000 2.4066 0.1840 0.1723 0.8926 0.0242 0.0000 2.4341 0.1861 0.1774 0.9223 0.0242 0.0000 2.4615 0.1882 0.1825 0.9510 0.0242 0.0000 2.4890 0.1902 0.1877 0.9789 0.0242 0.0000 2.5000 0.1911 0.1898 1.0060 0.0242 0.0000 ___________________________________________________________________ Name : Surface retention 1 Element Flows To: Outlet 1 Outlet 2 Gravel Trench Bed 1 Bioretention 1 ___________________________________________________________________ Name : Gravel Trench Bed 1 Bottom Length: 70.00 ft. Bottom Width: 4.00 ft. Trench bottom slope 1: 0 To 1 Trench Left side slope 0: 0 To 1 Trench right side slope 2: 0 To 1 Material thickness of first layer: 2 Pour Space of material for first layer: 0.3 Material thickness of second layer: 0 Pour Space of material for second layer: 0 Material thickness of third layer: 0 Pour Space of material for third layer: 0 Infiltration On Infiltration rate: 28 Infiltration safety factor: 1 Total Volume Infiltrated (ac-ft.): 0.811 Total Volume Through Riser (ac-ft.): 0 Total Volume Through Facility (ac-ft.): 0.811 Percent Infiltrated: 100 Overflow through riser infiltrated 100% Total Precip Applied to Facility: 0 Total Evap From Facility: 0 Discharge Structure Riser Height: 2 ft. Riser Diameter: 8 in. Orifice 1 Diameter: 8 in. Elevation: 2 ft. Element Flows To: Outlet 1 Outlet 2 ___________________________________________________________________ MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-40 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Gravel Trench Bed Hydraulic Table Stage(feet) Area(ac.) Volume(ac-ft.) Discharge(cfs) Infilt(cfs) 0.0000 0.006 0.000 0.000 0.000 0.0333 0.006 0.000 0.000 0.181 0.0667 0.006 0.000 0.000 0.181 0.1000 0.006 0.000 0.000 0.181 0.1333 0.006 0.000 0.000 0.181 0.1667 0.006 0.000 0.000 0.181 0.2000 0.006 0.000 0.000 0.181 0.2333 0.006 0.000 0.000 0.181 0.2667 0.006 0.000 0.000 0.181 0.3000 0.006 0.000 0.000 0.181 0.3333 0.006 0.000 0.000 0.181 0.3667 0.006 0.000 0.000 0.181 0.4000 0.006 0.000 0.000 0.181 0.4333 0.006 0.000 0.000 0.181 0.4667 0.006 0.000 0.000 0.181 0.5000 0.006 0.001 0.000 0.181 0.5333 0.006 0.001 0.000 0.181 0.5667 0.006 0.001 0.000 0.181 0.6000 0.006 0.001 0.000 0.181 0.6333 0.006 0.001 0.000 0.181 0.6667 0.006 0.001 0.000 0.181 0.7000 0.006 0.001 0.000 0.181 0.7333 0.006 0.001 0.000 0.181 0.7667 0.006 0.001 0.000 0.181 0.8000 0.006 0.001 0.000 0.181 0.8333 0.006 0.001 0.000 0.181 0.8667 0.006 0.001 0.000 0.181 0.9000 0.006 0.001 0.000 0.181 0.9333 0.006 0.001 0.000 0.181 0.9667 0.006 0.001 0.000 0.181 1.0000 0.006 0.001 0.000 0.181 1.0333 0.006 0.002 0.000 0.181 1.0667 0.006 0.002 0.000 0.181 1.1000 0.006 0.002 0.000 0.181 1.1333 0.006 0.002 0.000 0.181 1.1667 0.006 0.002 0.000 0.181 1.2000 0.006 0.002 0.000 0.181 1.2333 0.006 0.002 0.000 0.181 1.2667 0.006 0.002 0.000 0.181 1.3000 0.006 0.002 0.000 0.181 1.3333 0.006 0.002 0.000 0.181 1.3667 0.006 0.002 0.000 0.181 1.4000 0.006 0.002 0.000 0.181 1.4333 0.006 0.002 0.000 0.181 1.4667 0.006 0.002 0.000 0.181 1.5000 0.006 0.002 0.000 0.181 1.5333 0.006 0.003 0.000 0.181 1.5667 0.006 0.003 0.000 0.181 1.6000 0.006 0.003 0.000 0.181 1.6333 0.006 0.003 0.000 0.181 1.6667 0.006 0.003 0.000 0.181 MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-41 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx 1.7000 0.006 0.003 0.000 0.181 1.7333 0.006 0.003 0.000 0.181 1.7667 0.006 0.003 0.000 0.181 1.8000 0.006 0.003 0.000 0.181 1.8333 0.006 0.003 0.000 0.181 1.8667 0.006 0.003 0.000 0.181 1.9000 0.006 0.003 0.000 0.181 1.9333 0.006 0.003 0.000 0.181 1.9667 0.006 0.003 0.000 0.181 2.0000 0.006 0.004 0.000 0.181 2.0333 0.006 0.004 0.360 0.181 2.0667 0.006 0.004 0.569 0.181 2.1000 0.006 0.004 0.768 0.181 2.1333 0.006 0.004 0.963 0.181 2.1667 0.006 0.005 1.150 0.181 2.2000 0.006 0.005 1.324 0.181 2.2333 0.006 0.005 1.478 0.181 2.2667 0.006 0.005 1.608 0.181 2.3000 0.006 0.005 1.713 0.181 2.3333 0.006 0.006 1.810 0.181 2.3667 0.006 0.006 1.899 0.181 2.4000 0.006 0.006 1.983 0.181 2.4333 0.006 0.006 2.064 0.181 2.4667 0.006 0.007 2.142 0.181 2.5000 0.006 0.007 2.217 0.181 2.5333 0.006 0.007 2.290 0.181 2.5667 0.006 0.007 2.361 0.181 2.6000 0.006 0.007 2.429 0.181 2.6333 0.006 0.008 2.496 0.181 2.6667 0.006 0.008 2.561 0.181 2.7000 0.006 0.008 2.624 0.181 2.7333 0.006 0.008 2.686 0.181 2.7667 0.006 0.008 2.746 0.181 2.8000 0.006 0.009 2.805 0.181 2.8333 0.006 0.009 2.863 0.181 2.8667 0.006 0.009 2.920 0.181 2.9000 0.006 0.009 2.975 0.181 2.9333 0.006 0.010 3.030 0.181 2.9667 0.006 0.010 3.083 0.181 3.0000 0.006 0.010 3.136 0.181 ___________________________________________________________________ ___________________________________________________________________ ANALYSIS RESULTS POC #1 was not reported because POC must exist in both scenarios and both scenarios must have been run.Perlnd and Implnd Changes No changes have been made. ___________________________________________________________________ This program and accompanying documentation are provided 'as-is' without warranty of any kind. The entire risk regarding the performance and results of this program is assumed by End User. Clear Creek Solutions Inc. and the governmental licensee or sublicensees disclaim all warranties, either expressed or implied, including but not limited to implied warranties of program and accompanying documentation. In no event shall Clear Creek Solutions Inc. be liable for any damages whatsoever (including without limitation to damages for loss of business profits, loss of MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page C-42 of 42 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx business information, business interruption, and the like) arising out of the use of, or inability to use this program even if Clear Creek Solutions Inc. or their authorized representatives have been advised of the possibility of such damages. Software Copyright © by : Clear Creek Solutions, Inc. 2005-2023; All Rights Reserved. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page D-1 of 1 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Appendix D - Geotechnical Report Provided under separate cover. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page E-1 of 1 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Appendix E - Critical Areas Report Provided under separate cover. MC# ARMO-0001 Armor Storage - Grove Road 8/28/2023 Preliminary Drainage Report Page F-1 of 1 PreliminaryDrainageReport-GroveRoadStorage-Yelm.docx Appendix F - Source Control BMPs To be provided with the final engineering submittal.