2020.0001 MU - Development Proj Acceptance LTR v2.docxDecember 28, 2023
Chris Hansen
Yelm Community Schools
107 1st Street N
Yelm, Washington 98597
RE: YCS Bus Facility – City of Yelm Project No. MU 2020.0012 (Parcel# 22719310200)
Construction Closeout Engineering Acceptance Letter
Dear Mr. Hansen:
A project walk-thru was conducted on September 16, 20XX and determined that items on previous punchlist letters have been satisfactory addressed and the improvements associated with
Application # 2020.0123.CI0007 have been deemed acceptable by City of Yelm Public Services Department – Engineering Division.
The final phase to the closeout process is the Closing Documents Phase. Attached is a Project Closeout Checklist that identifies the required documents to be submitted for final closeout
of this project.
If you have any additional questions or comments please do not hesitate to call or contact me at rezar@yelmwa.gov or call me at (253) 278-2937.
Respectfully,
Public Services Department - Engineering
Reza R. Roukerd
Development Review Engineer
cc. Robert Balmelli, RB Engineering
enc.