WM 03705-1003 Yelm, WA - CAPXREF3E
E
E
E
EE
1
1
2
2
3
3
4
4
5
5
6
67
8
8
9
9
10
10
11
11
12
12
13
13
A A
B B
C C
D D
E E
F F
G G
H H
J J
K K
1
D1F1
1 1
FP1
1
BASR1
1
R1
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.T1
TITLE SHEET
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
SCOPE OF WORK SUMMARY
NOTE: THE INTENT OF THIS SUMMARY IS TO ASSIST VENDORS IN
IDENTIFYING EQUIPMENT NEEDS. IT IS NOT INTENDED FOR USE
BY CONTRACTOR TO CAPTURE ALL SCOPE ISSUES. REFER TO
PLANS AND SPECIFICATIONS (WHERE APPLICABLE) FOR
ADDITIONAL INFORMATION.
CODE COMPLIANCE
NOTE TO BIDDING
CONTRACTORS
THE AWARDED CONTRACTOR SHALL BE RESPONSIBLE FOR THE
ENTIRE SCOPE OF WORK INDICATED ON THESE PLANS, THE
ASSOCIATED SPECIFICATIONS AND WALMART SCOPE OF WORK
DOCUMENT. THIS CAPITAL EXPENDITURE SHALL BE COMPLETED AS
A "TURN KEY" PROJECT BY THE AWARDED CONTRACTOR AND SHALL
INCLUDE BUT NOT LIMITED TO ALL SHEETS ON THIS PRINT: HVAC,
REFRIGERATION, PLUMBING, ELECTRICAL EMS CONTROLS SYSTEMS,
ARCHITECTURAL AND STRUCTURAL DISCIPLINES.
CONSTRUCTION PHASING
GENERAL REQUIREMENTS
1 THE PLANS SHOWN THROUGHOUT THESE DOCUMENTS
ARE BASED ON LIMITED INFORMATION PROVIDED BY
WALMART AND A LIMITED SITE OBSERVATION SURVEY;
THE DESIGN PROFESSIONAL CANNOT BE HELD
RESPONSIBLE FOR THE ACCURACY OF THE EXISTING
CONDITIONS ILLUSTRATED.
2 THE CONTRACTOR IS TO INSPECT THE STORE PRIOR TO
COMMENCING WITH ANY WORK AND NOTIFY THE
WALMART MECHANICAL CONSTRUCTION MANAGER OF
ANY DISCREPANCIES BETWEEN THESE PLANS AND THE
EXISTING CONDITIONS.
3 ALL WORK SHALL BE DONE IN A SAFE AND
WORKMANLIKE MANNER AND IN STRICT ACCORDANCE
WITH THE LOCAL GOVERNING BUILDING CODE, NATIONAL
ELECTRIC CODE, ADA-ADAAGS, OSHA REGULATIONS,
AND ALL APPLICABLE CODES, REGULATIONS AND
ORDINANCES HAVING JURISDICTION.
4 THE CONTRACTOR IS RESPONSIBLE FOR HAVING A
THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS. THE FAILURE TO ACQUAINT HIMSELF
WITH ALL DRAWINGS AND SPECIFICATIONS DOES NOT
RELIEVE THE CONTRACTOR'S RESPONSIBILITY OF
PERFORMING HIS WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED DUE TO FAILURE
TO FAMILIARIZE WORKERS WITH ALL DRAWINGS AND
SPECIFICATIONS.
5 THE EXISTING BUILDING SHALL BE PROTECTED FROM
MOISTURE, DUST AND DEBRIS. INSTALL DUST
PARTITIONS OR DRAPES AS SHOWN OR AS REQUIRED
TO KEEP DUST AND MOISTURE FROM WALMART
PREMISES.
6 ANY DAMAGE TO WALMART PROPERTY WHICH OCCURS
DURING THE PROCESS OF CONSTRUCTION SHALL BE
REPAIRED AT NO ADDITIONAL COST TO WALMART; THIS
INCLUDES ALL MERCHANDISE. CONTRACTOR SHALL PAY
WALMART THE COST FOR ALL DAMAGED MERCHANDISE.
7 THE CONTRACTOR SHALL BE RESPONSIBLE FOR
RECEIVING, HANDLING, AND STORAGE OF OWNER
FURNISHED EQUIPMENT. CONTRACTOR SHALL
COORDINATE DELIVERY DATE CHANGES WITH WALMART
HVAC/REFRIGERATION ADMINISTRATOR. CONTRACTOR
SHALL PROVIDE EITHER ON-SITE STORAGE CONTAINERS,
COORDINATE EQUIPMENT LAYDOWN AREA ON-SITE,
AND/OR OFF-SITE STORAGE FOR OWNER FURNISHED
EQUIPMENT AND ANY OTHER CONSTRUCTION ITEMS.
CONTRACTOR SHALL COORDINATE LOCATION OF ANY
ON-SITE STORAGE CONTAINERS AND/OR EQUIPMENT
LAYDOWN AREA WITH WALMART STORE MANAGEMENT
PRIOR TO PLACEMENT. CONTRACTOR IS RESPONSIBLE
FOR SECURITY AND CONDITION OF OWNER FURNISHED
EQUIPMENT KEPT IN STORAGE AND SHALL PROVIDE
PERSONNEL TO RECEIVE AND MOVE EQUIPMENT. THE
CONTRACTOR SHALL BE RESPONSIBLE FOR THE TIMELY
ORDERING OF MATERIALS TO PROHIBIT DELAYS OF THE
CONSTRUCTION SCHEDULE OF THIS PROJECT. IT IS THE
RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE
DELIVERY OF MATERIALS IN A TIMELY MANNER.
8 THE CONTRACTOR SHALL MAINTAIN THE INTEGRITY OF
THE EXISTING BUILDING SECURITY AT ALL TIMES. THIS
INCLUDES KEEPING THE BUILDING SECURE OF
PERSONS, ENVIRONMENTAL ELEMENTS OR HAZARDS.
THE CONTRACTOR SHALL BE RESPONSIBLE TO MAINTAIN
THE INTEGRITY OF ALL EXISTING SECURITY SYSTEMS.
THE CONTRACTOR SHALL OBTAIN PERMISSION FROM
THE WALMART STORE MANAGER PRIOR TO THE
MODIFICATION OF ANY EXISTING SECURITY SYSTEM FOR
THE OPENING (DEMOLITION) OF ANY EXTERIOR WALL.
9 THE CONTRACTOR SHALL KEEP THIS AREA CLEAN AND
FREE OF DEBRIS AND IS TO REMOVE ALL TRASH AND
DEBRIS FROM THE CONSTRUCTION AREA DAILY. NO
FLAMMABLE MATERIALS OR LIQUIDS MAY BE STORED IN
THE EXISTING BUILDING OR IN THE NEW ADDITION.
10 REMOVE ANY EXISTING ITEMS, SERVICES, SIGNAGE,
FINISHES/OR SURFACES AS REQUIRED FOR THE
INSTALLATION OF NEW CONSTRUCTION.
11 PROVIDE FURRING FOR CONDUITS AND PIPING, SHOWN
OR NOT, AND FINISH OUT FURRING TO MATCH ADJACENT
EXISTING FINISHES.
12 REPAIR, REROUTE, AND EXTEND ALL SERVICES, PIPING,
CONDUIT OF EXISTING ITEMS AND EQUIPMENT AS
REQUIRED DURING THE CONSTRUCTION PROCESS FOR
THE COMPLETE INSTALLATION AND OPERATION OF NEW
EQUIPMENT. THIS INCLUDES ALL ITEMS SHOWN OR NOT
SHOWN ON THE DRAWINGS.
13 RESET EXISTING EQUIPMENT OR RELATED ITEMS
INCLUDING SIGNAGE AS REQUIRED FOR PROPER
OPERATION. WHERE EXISTING FINISHES ARE TO REMAIN,
CLEAN, REPAIR, PATCH, AND/OR RE-PAINT AS
NECESSARY TO BLEND WITH ADJACENT SURFACES.
14 CONSULT WALMART MECHANICAL CONSTRUCTION
MANAGER FOR COMPLETE APPLICABLE SCOPE OF
WORK. THE CONTRACTOR SHALL MAINTAIN THE
REQUIRED NUMBER OF EXITS WITHIN THE STORE.
MAINTAIN EXIT
INFORMATION SAFETY BOARD
SAFETY BOARDS AND OR POSTED CONSTRUCTION SCHEDULES ARE
REQUIRED ON CERTAIN CAP-X PROJECTS DEPENDING ON THE
PROJECT TYPE. CAP-X PROJECTS WILL BE LISTED AS ONE OF THE
FOLLOWING TYPES: COMBO, REF-1, REF-2, REF-3, REF-4, HVAC-1,
HVAC-2, HVAC-3, OR HVAC-4.
REF-1 / REF-2 / COMBO: INFORMATION SAFETY BOARD REQUIRED
W/ POSTED CONSTRUCTION SCHEDULE
REF-3: INFORMATION SAFETY BOARD REQUIRED W/ POSTED
CONSTRUCTION SCHEDULE
REF-4: NOT REQUIRED
HVAC-1: INFORMATION SAFETY BOARD REQUIRED W/ POSTED
CONSTRUCTION SCHEDULE
HVAC-2: INFORMATION SAFETY BOARD REQUIRED W/ POSTED
CONSTRUCTION SCHEDULE
HVAC-3: INFORMATION SAFETY BOARD REQUIRED W/ POSTED
CONSTRUCTION SCHEDULE
HVAC-4: NOT REQUIRED
REFER TO THE MECHANICAL CONSTRUCTION PROJECT
SPECIFICATION MANUAL SECTION 01500 -TEMPORARY FACILITIES
AND CONTROLS FOR COMPLETE TEMPORARY FACILITY AND
CONTROLS FOR COMPLETE TEMPORARY FACILITY REQUIREMENTS.
PHASING NOTES ARE INTENDED TO BE USED AS A GENERAL
GUIDE TO THE CONSTRUCTION AND PHASING OF PROJECT. IT IS
THE RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE ALL
AREAS OF PHASING WITH WALMART MECHANICAL
CONSTRUCTION MANAGER AND WALMART STORE MANAGER
PRIOR TO AND DURING CONSTRUCTION.
ALL DRAWINGS ARE IN COMPLIANCE WITH THE FOLLOWING CODES:
THE INTERNATIONAL BUILDING CODE, 2021 EDITION; AMENDED BY
CHAPTERS 51-50 AND 51-51 WAC
THE INTERNATIONAL FIRE CODE, 2021 EDITION; AMENDED BY
CHAPTER 51-54A WAC
THE INTERNATIONAL MECHANICAL CODE, 2021 EDITION; AMENDED
BY CHAPTER 51-52 WAC
THE NATIONAL ELECTRICAL CODE, 2023 EDITION
THE WASHINGTON STATE ENERGY CODE, 2021 EDITION
USE AND OCCUPANCY GROUP: M
CONSTRUCTION TYPE: V
BUILDING AREA: UNCHANGED
OCCUPANT LOAD: UNCHANGED
FIRE PROTECTION: YES
REFRIGERATION CAP-X REF3
STORE #3705 - 1003
YELM, WA
USMV-043985
1/32" = 1'-0" 1 KEY PLAN
THIS IS A CAP-X REF PROJECT. REFER TO
SPECIFICATIONS SECTION 1500 FOR ADDITIONAL INFORMATION
REGARDING REQUIRED JOB SITE TEMPORARY FACILITIES.
THESE PLANS ARE TYPICALLY ISSUED FOR BID AS REDUCED "1/2
(HALF) SIZE" DOCUMENTS. SCALES SHOWN APPLY TO ORIGINAL
"FULL SIZE" DOCUMENTS ONLY. DO NOT SCALE DRAWINGS, FIELD
VERIFY ALL DIMENSIONS.
SIGNS AND EMERGENCY LIGHTING AT ALL TIMES, AS
REQUIRED BY THE LOCAL BUILDING OFFICIAL.
15 WALMART SHALL OCCUPY THE BUILDING DURING
CONSTRUCTION. THE CONTRACTOR SHALL COORDINATE
WITH WALMART STORE MANAGER AND THE WALMART
MECHANICAL CONSTRUCTION MANAGER ALL
CONSTRUCTION PROCEDURES WHICH WILL INTERFERE
WITH THE NORMAL DAILY OPERATIONS OF THE STORE.
16 THE CONTRACTOR SHALL OBTAIN PERMISSION FROM
WALMART FOR ALL INTERRUPTIONS OF UTILITY
SERVICES TO THE EXISTING BUILDING PRIOR TO THE
INTERRUPTION. ACCIDENTAL INTERRUPTIONS SHALL BE
REMEDIED IMMEDIATELY WITH APPROPRIATE FORCES.
17 ALL CAP-X/SPECIAL REFRIGERATION PROJECTS ARE TO
BE BID AS NIGHT WORK. THE CONTRACTOR IS TO
ASSUME ALL WORK IS TO BE CONDUCTED ONLY AS
OVERNIGHT WORK. SOME WORK MAY BE ALLOWED
DURING REGULAR WORKING HOURS TO FACILITATE
COMPLETION SCHEDULES. WORK WILL ONLY BE
PERMITTED DURING REGULAR WORKING HOURS WITH
THE WALMART STORE MANAGEMENT'S AND/OR
WALMART MECHANICAL CONSTRUCTION MANAGER'S
PERMISSION. WORK TO BE PERFORMED ON THE
EXTERIOR OF THE BUILDING, ROOFTOP, BACK ROOM,
BEHIND DUST WALLS, AND WORK THAT DOES NOT
SIGNIFICANTLY INTERFERE WITH STORE OPERATIONS
MAY BE ALLOWED WITH THE WALMART STORE
MANAGEMENT'S AND/OR WALMART MECHANICAL
CONSTRUCTION MANAGER'S PERMISSION. THE
CONTRACTOR SHALL PAY FOR ADDITIONAL SECURITY
PERSONNEL TO SUPERVISE ACCESS TO THE BUILDING
AS REQUIRED BY WALMART STORE MANAGEMENT.
CONTRACTOR SHALL PROVIDE ALL SAFETY EQUIPMENT
AND EXTERIOR LIGHTING AS REQUIRED TO MAINTAIN A
SAFE WORKING ENVIRONMENT FOR WORK REQUIRED AT
NIGHT. THE CONTRACTOR SHALL PREPARE, AND
DELIVER TO WALMART STORE MANAGEMENT, A
SCHEDULE OF WORK FOR THE ENTIRE PROJECT SCOPE
OF WORK. THIS SCHEDULE WILL INCLUDE ALL PHASES
OF WORK TO BE PERFORMED AND SHALL LIST THE
START AND COMPLETION TIMES FOR EACH PHASE OF
WORK. THE CONTRACTOR SHALL UPDATE THIS
SCHEDULE WEEKLY AS CONSTRUCTION PROGRESSES.
18 THE CONTRACTOR SHALL COORDINATE WITH THE
ENGINEER OF RECORD ON DEVIATIONS IN INSTALLATION
AND CONSTRUCTION OF FIXTURES, PIPING, AND OTHER
ITEMS SPECIFIED IN THESE CONSTRUCTION
DOCUMENTS.
19 SALES FLOOR TO BE ACCESSIBLE TO CUSTOMERS
DURING NON-CONSTRUCTION HOURS. PROVIDE ALL
NECESSARY TEMPORARY BARRIERS AND COVERS
CAPABLE OF WITHSTANDING SHOPPING CART TRAFFIC
AND CUSTOMER INTERACTION TO PREVENT CUSTOMER
ACCESS OR EXPOSURE TO ANY CONSTRUCTION
RELATED HAZARDS. COORDINATE WITH WALMART
STORE MANAGER.
20 FURNISH AND INSTALL SEISMIC BRACING BASED ON
APPROPRIATE SEISMIC ZONE REQUIREMENTS PER
SMACNA PUBLISHED SEISMIC DETAILS AND LOCAL AND
NATIONAL CODES. CONTRACTOR'S RESPONSIBILITY
INCLUDES STRUCTURAL ENGINEER'S CERTIFICATION ON
DETAILS SUBMITTED FOR PERMITTING.
21 CONTRACTOR SHALL PAINT ALL NEW CONDUIT, DUCT,
PLUMBING PIPING, SPRINKLER PIPING, AND SUPPORTS
EXPOSED TO SALES FLOOR WITHOUT EXCEPTIONS.
MATCH CEILING OR ADJACENT WALL COLOR (WHERE
APPLICABLE). CONDUIT AND PIPING SHALL BE PAINTED
PRIOR TO INSTALLATION.
22 REFER TO SPECIFICATION SECTIONS 01600 -PRODUCT
REQUIREMENTS AND APPENDIX A -PRODUCTS AND
WORK BY OWNER OR SEPARATE CONTRACTOR. THESE
SECTIONS INCLUDE SPECIFIC INFORMATION REGARDING
ITEMS AND SERVICES TO BE FURNISHED AND INSTALLED
BY INDIVIDUALS OTHER THAN THE CONTRACTOR.
23 REPORT ANY DISCREPANCIES FOUND IN THE FIELD
IMMEDIATELY TO WALMART AND THE ENGINEER PRIOR
TO MAKING ANY STRUCTURAL MODIFICATIONS OR
ORDERING OF ANY MATERIALS.
24 IT IS IMPERATIVE THAT THE ROOF FRAMING, DECKING
AND ROOFING SYSTEM BE COMPLETED IMMEDIATELY
UPON THE DEMOLITION OF ANY PORTION OF AN
EXTERIOR WALL OR MAKING ANY OPENINGS IN THE
ROOF TO ELIMINATE POTENTIAL WATER DAMAGE OR
MOISTURE INFILTRATION. THE CONTRACTOR SHALL
KEEP THE BUILDING WATERTIGHT AT ALL TIMES.
25 THE GENERAL CONTRACTOR SHALL RESPOND TO ALL
REQUIREMENTS OF THE ENGINEER FOR VERIFICATIONS,
RESPONSES, AND SUBMISSIONS. ALL ADJACENT
BUILDINGS (IF APPLICABLE) SHALL REMAIN IN SERVICE
DURING DEMOLITION/CONSTRUCTION.
26 MUD AND DEBRIS TRACKED ONTO OWNER PAVING OR
CITY STREETS TO BE CLEANED IMMEDIATELY.
27 BUILDING COMPONENTS AFFECTED BY THE SCOPE OF
WORK AND ALLOWED TO REMAIN SHALL BE SECURED TO
PREVENT FALLING, LOOSENING, OR CREATING DAMAGE
OF ANY KIND IN THE FUTURE.
PERMITTING REQUIREMENTS AND CONTACT INFO
UPON NOTIFICATION OF CONTRACT AWARD, CONTRACTOR SHALL CONTACT THE ENGINEER OF RECORD'S PERMIT
COORDINATOR REGARDING BUILDING PERMIT STATUS. CONTRACTOR SHALL NOT CONTACT AHJ PRIOR TO
CONTACTING PERMIT COORDINATOR TO VERIFY BUILDING PERMIT STATUS. WHEN NECESSARY, THE CONTRACTOR
SHALL DELIVER PERMIT PLAN SETS AND PAY PERMIT FEES TO THE AHJ IN ORDER TO RECEIVE CONSTRUCTION
PERMITS. UPON REVIEW OF PROJECT SCOPE THE AHJ MAY REQUIRE THE CONTRACTOR TO COMPLETE
ADDITIONAL PERMITTING REQUIREMENTS FOR OR SUBMIT ADDITIONAL PLAN SETS FOR REVIEW TO ADDITIONAL
LOCAL, COUNTY, STATE, AND/OR FEDERAL AUTHORITIES WHICH MAY NOT BE LOCATED WITHIN THE LOCAL AHJ’S
OFFICES. SUBMIT ANY PLAN REVIEW COMMENTS OR QUESTIONS THROUGH THE WALMART APPROVED RFI
PROCESS. CONTRACTOR SHALL OBTAIN PERMIT(S) THE GREATER OF 10 WORKING DAYS OR 2 WEEKS PRIOR TO
THE START OF CONSTRUCTION TO AVOID UNNECESSARY DELAYS AND ADDITIONAL ENGINEERING FEES.
CONTRACTOR SHALL PICK UP AND PAY FOR ANY REQUIRED PERMIT(S) AND ALL ANCILLARY FEES. COST OF
REQUIRED PERMIT(S) WILL BE DETERMINED AT THE TIME OF PERMIT ISSUANCE. EXACT AMOUNT SHALL BE
COORDINATED WITH THE WALMART CONSTRUCTION MANAGER. CONTRACTOR SHALL EMAIL A COPY OF PERMIT(S)
WHEN OBTAINED TO PERMIT COORDINATOR LISTED BELOW. CONTRACTOR SHALL UPLOAD A COPY OF PERMIT(S)
WHEN OBTAINED TO EVOCO WORKSPACE SUPPORT FOLDER. UPON COMPLETION OF THE PROJECT,
CONTRACTOR SHALL EMAIL APPROVED FINAL INSPECTION REPORT AND CERTIFICATE OF COMPLETION TO PERMIT
COORDINATOR LISTED BELOW. UPON COMPLETION OF THE PROJECT, CONTRACTOR SHALL UPLOAD APPROVED
FINAL INSPECTION REPORT AND CERTIFICATE OF COMPLETION TO EVOCO WORKSPACE SUPPORT FOLDER.
CONTACT EMAIL PHONE
VENDOR CONTACT REQUIREMENTS
CONTRACTOR IS RESPONSIBLE, UPON AWARD, TO CONTACT AND VERIFY ALL DELIVERIES DATES/TIMES WITH
EVERY VENDOR FURNISHING EQUIPMENT OR SERVICES, OR TO CHANGE ANY DATES OR DELIVERIES. CONTRACTOR
MUST CONTACT WALMART CONSTRUCTION MANAGER LISTED BELOW. VENDOR CONTACT INFORMATION IS
AVAILABLE IN THE GCC EQUIPMENT PLATFORM AND IN THE PROJECT SPECIFICATIONS. THIS IS UNIQUE TO CAPITAL
EXPENDITURES PROJECTS.
PROJECT VENDORS
WALMART CONTACT LIST
CONTACT PHONE AND/OR EMAIL TITLE
STORE MANAGER
CONSTRUCTION MANAGER
WALMART PROJECT MANAGER
PROJECT SITE ADDRESS
STREET:17100 STATE ROUTE 507 SE
CITY:YELM
STATE:WA
COUNTY:THURSTON COUNTY
KELLY BOAZ O: 479-204-1494 C: 479-644-7338
kboaz@walmart.com
ICE CREAM FREEZER SCOPE OF WORK:
REPLACE ICE CREAM FREEZER .
ADD HCR DOOR.
REPLACE ICE CREAM FREEZER DOOR
ADD LEAK DETECTION.
KPS GLOBAL LLC
RIDG-U-RACK INC
COPELAND COLD CHAIN LP
HONEYWELL INTERNATIONAL INC
PARKER HANNIFIN
PROGASKET SOLUTIONS LLC
ERIC MILLS Eric.Mills@hargis.biz 206-436-0413
INDEX OF DRAWINGS
REFERENCE
SHEET NUMBER SHEET NAME
T1 TITLE SHEET
N1 RESPONSIBILITY MATRICES
N2 EDGE PROTECTION
FIXTURE
SHEET NUMBER SHEET NAME
D1 DEMOLITION PLAN
F1 FIXTURE PLANS AND SCHEDULES
FIRE PROTECTION
SHEET NUMBER SHEET NAME
FP1 OVERALL FIRE SPRINKLER PLAN
FP2 ENLARGED FIRE SPRINKLER PLAN
REFRIGERATION
SHEET NUMBER SHEET NAME
BASR1 BUILDING AUTOMATION SYSTEM
BASR2 BUILDING AUTOMATION SYSTEM
BASR3 BUILDING AUTOMATION SYSTEM
R1 REFRIGERATION PLAN AND PIPING SCHEDULES
R2 REFRIGERATION SCHEDULES AND DETAILS
R3 REFRIGERATION DETAILS
R4 REFRIGERATION SUBMITTALS
SR1 SEISMIC RESTRAINT
ELECTRICAL
CANDICE SINGH 360-400-8050
store-mgr.s03705@stores.us.wal-
mart.com
SHEET NUMBER SHEET NAME
RE1 REFRIGERATION ELECTRICAL PLAN
BILL PARDUE C: 916-300-4294
bpardue@mksvs.net
ISSUE BLOCK
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
N1
RESPONSIBILITY
MATRICES
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
MC MECHANICAL CONTRACTOR AND SUB-CONTRACTORS
WTC WATER TREATMENT CONTRACTOR
AES SUPPLIER OF AHU ADAPTER CURBS, RTU ADAPTER CURBS AND WALMART'S
EQUIPMENT SALVAGE PARTNER
WMT WALMART
PS WALK-IN BOX PANEL SUPPLIER
OEM ORIGINAL RACK EQUIPMENT MANUFACTURER, ORIGINAL CASE EQUIPMENT
MANUFACTURER, AHU MANUFACTURER, RTU MANUFACTURER
EMS EMS VENDOR
GC GENERAL CONTRACTOR AND SUB-CONTRACTORS
RC REFRIGERATION CONTRACTOR AND SUB-CONTRACTORS
ABBREVIATION DESCRIPTION
MATRIX LEGEND
60 LOOSEN AND RE-TIGHTEN OR REMOVE AND RE-INSTALL UTILITIES (CONDENSATE PIPING, CONDUITS, J-BOX,
FIRE SUPPRESSION, ETC.) AS REQUIRED IN ORDER TO ALLOW FOR THE WORK TO BE CARRIED OUT GC RC GC RC GC RC
59 CLEAR SITE OF ALL TOOLS, UNUSED INSTALLATION MATERIALS AND TRASH. RC/PS RC/PS RC/PS RC/PS RC/PS RC/PS
58 SUBMIT REQUIRED VERISAE AND OTHER REGULATORY FORMS AS REQUIRED BY THE END OF COMMISSIONING
WEEK. COMPLETED VERISAE FORMS ARE TO BE EMAILED TO MCEQUIP@WALMART.COM.RC RC RC RC RC RC
57
AFTER ALL CHANGES HAVE BEEN MADE TO A RACK, REMOVE ANY COMPRESSOR SUCTION FILTERS / SOCKS
AND REPLACE THE RACK LIQUID LINE FILTERS. LEAVE THE OLD FILTERS / DRIERS IN THE RACK HOUSE TO BE
INSPECTED BY THE MCM.
RC RC RC RC RC RC
56 SHUT DOWN AND ARRANGE FOR THE REMOVAL OF ANY TEMPORARY, REFRIGERATED STORAGE. WMT WMT WMT WMT WMT WMT
55 REMOVE THE OLD LEGENDS AND INSTALL REPLACEMENT LEGENDS AS SUPPLIED BY THE EOR / OEM. PROVIDE
TYPEWRITTEN SCHEDULES FOR ANY AFFECTED ELECTRICAL PANELS.RC RC RC RC RC RC
54 HAUL OFF ALL OF THE OLD WALK-IN PANELS FROM SITE (IF APPLICABLE).
NOTE: QUICK REFRIGERATION TO HAUL OFF ALL WALK-IN BOX PANELS FROM TEXAS PROJECTS.GC/PS RC/PS GC/PS RC/PS GC/PS RC/PS
53 RESTOCK PRODUCT BACK INTO THE WALK-IN BOX. WMT WMT WMT WMT WMT WMT
52 HAND OVER THE COMPLETED WALK-IN BOX TO THE STORE. (WALK-IN BOX MUST BE CLEAN, AT OPERATIONAL
TEMPERATURE AND FULLY FUNCTIONAL)GC RC GC RC GC RC
51 CARRY OUT A THOROUGH LEAK TEST ON ALL WELDED AND MECHANICAL JOINTS INSTALLED OR DISTURBED
DURING THE PROJECT.RC RC RC RC RC RC
50 INSTALL CIRCUIT LABELS TO THE WALK-IN BOX, CONTROLLERS AND EVAPORATORS AS REQUIRED. RC RC RC RC RC RC
49 ANCHOR RACKING AS INDICATED ON THE PLANS. GC RC GC RC GC RC
48 INSTALL SHELVING / RACKING AS INDICATED ON THE PLANS. RE-INSTALL RACKING AS NECESSARY. WMT RC WMT RC WMT RC
47 REINSTALL / RECOMMISSION THE APX REPEATER DEVICE.WMT WMT WMT WMT WMT WMT
46 NOTIFY WMT BUILDING CONTROLS THAT THE WALK-IN BOX IS RUNNING AND ONLINE. RC RC RC RC RC RC
45 FURNISH CONTROLS SUPPORT TO THE INSTALLING CONTRACTOR. N/A N/A N/A N/A EMS EMS
44 CARRY OUT ANY CONTROLS PARAMETER CHANGES AND PERFORM REMOTE CHECKOUT. N/A N/A N/A N/A RC RC
43 CARRY OUT ANY CONTROLS PARAMETER CHANGES. N/A N/A N/A N/A EMS EMS
42 FIELD-INSTALL AND START-UP HCR AIR DOORS AS REQUIRED. N/A N/A N/A N/A PS PS
41 FURNISH HCR AIR DOOR AS REQUIRED. N/A N/A N/A N/A PS/WMT PS/WMT
40 COMMISSION THE EVAPORATORS, VALVES AND CONTROLS AS REQUIRED. CHECK AND ADJUST MECHANICAL
TXV SUPERHEATS TO OEM RECOMMENDATIONS AND EPR SETTINGS PER LEGEND.N/A N/A N/A N/A RC RC
39 SWITCH ON THE REFRIGERATION, LIGHTING AND OTHER SYSTEMS WITHIN THE WALK-IN. RC RC RC RC RC RC
38
INSTALL / MODIFY ALL UTILITIES FOR FINAL BOX CONFIGURATION. (CONDENSATE PIPING, CONDUITS, J-BOX,
LIGHTING, FIRE SUPPRESSION ETC.) INSTALL CONDUIT FOR APX CABLING. SEAL ALL PENETRATIONS PER
SPECS
GC RC GC RC GC RC
37 INSTALL AND COMMISSION REFRIGERANT LEAK DETECTION SYSTEM AS NOTED ON THE PROJECT PRINTS. N/A N/A N/A N/A RC RC
36 EVACUATE AND PRESSURE TEST THE EVAPORATORS AND ANY PIPING MODIFIED DURING THE WORK. N/A N/A N/A N/A RC RC
35 INSTALL THE EVAPORATORS (MECHANICAL, ELECTRICAL, PLUMBING AND CONTROLS) AND CONTROL PANELS
AS DETAILED ON THE PRINTS.N/A N/A N/A N/A RC RC
34
INSTALL PROTECTION DEVICES AS INDICATED ON THE PRINTS. REINSTALL ANY EXISTING PROTECTION
DEVICES OR STRUCTURES AS REQUIRED. ENSURE THAT ANY UNDISTURBED PROTECTION DEVICES ARE
FIXED SECURELY.
GC RC GC RC GC RC
33
REATTACH ANY ITEMS PREVIOUSLY MOUNTED TO THE EXTERIOR OF THE WALK-IN BOX THAT WERE
TEMPORARILY SUPPORTED DURING THE WALK-IN BOX REPLACEMENT. (FOR EXAMPLE PANEL BOARDS, EMS
BACKBOARDS ETC.)
N/A N/A N/A N/A GC RC
32 RETRIEVE ANY FALL PROTECTION NETTING FROM THE ROOF MEMBERS, AND REATTACH IT TO THE TOP OF
THE WALK-IN BOX AS DESCRIBED ON THE PRINTS.N/A N/A N/A N/A GC RC
31 INSTALL NEW WALK-IN BOX. HANG THE DOOR AND ENSURE THAT ALL HARDWARE FUNCTIONS CORRECTLY. N/A N/A N/A N/A PS PS
30 REPLACE THE WOODEN THERMAL BREAKS AS NECESSARY. N/A N/A N/A N/A GC RC
29
PROVIDE SUPPORT FOR ANY ITEMS THAT MAY BE MOUNTED TO THE EXTERIOR OF THE WALK-IN BOX THAT
WILL REMAIN IN SERVICE DURING THE BOX REPLACEMENT. (FOR EXAMPLE PANEL BOARDS, EMS
BACKBOARDS ETC.)
N/A N/A N/A N/A GC RC
28
DISCONNECT ANY FALL PROTECTION NETTING FROM THE TOP OF THE WALK-IN BOX. LEAVING IT ATTACHED TO
THE ROOF MEMBERS, STOW IT OUT OF THE WAY FOR FUTURE RE-USE.
DEMOLISH AND REMOVE THE EXISTING WALK-IN BOX AS NOTED ON THE PROJECT PRINTS.
N/A N/A N/A N/A PS PS
27 CLEAN WALLS AND REPAIR ANY FAULTY PANELS IN PREPARATION FOR RELINING THE BOX THAT IS BEING
REPAIRED. RE-LINE THE WALK-IN BOX AND BATTEN / SEAL THE CEILING JOINTS WITHIN THE BOX AFFECTED.N/A N/A PS PS N/A N/A
26 CLEAN WALLS AND REPAIR ANY FAULTY PANELS IN PREPARATION FOR BATTEN / SEALING OF THE WALL
JOINTS WITHIN THE BOX THAT IS BEING REPAIRED. CARRY OUT THE BATTEN AND SEAL PROCESS.PS PS N/A N/A N/A N/A
25 FILL ANY GAPS IN THE PANEL JOINTS WITH SEALANT OR EXPANDABLE FOAM PRIOR TO TAPING THE JOINT. PS PS PS PS N/A N/A
24 REMOVE THE REFRIGERATION EVAPORATOR(S) FROM THE AFFECTED WALK-IN BOX AS NEEDED. N/A N/A GC RC GC RC
23 REMOVE THE APX REPEATER FROM THE WALK-IN BOX THAT IS BEING IMPACTED. STORE THE DEVICE FOR
REUSE FOLLOWING COMPLETION OF THE WALK-IN WORK.GC RC GC RC GC RC
22 REMOVE ALL UTILITIES (CONDENSATE PIPING, CONDUITS, J-BOX, LIGHTING, FIRE SUPPRESSION ETC.) IN
ORDER TO ALLOW FOR THE WORK TO BE CARRIED OUT.N/A N/A GC RC GC RC
21 REMOVE ANY PROTECTION DEVICES / STRUCTURES THAT W ILL IMPEDE THE COMPLETION OF THE WORK. GC RC GC RC GC RC
20 REMOVE ALL OF THE RACKING FROM INSIDE THE WALK-IN BOX THAT IS BEING IMPACTED. WMT RC WMT RC WMT RC
19
SHUT DOWN THE WALK-IN BOX THAT IS BEING IMPACTED.
NOTE: ALLOW LOW TEMP ROOMS TO "DEFROST" FOR A PERIOD OF 72 HOURS TO ENSURE ALL ICE HAS MELTED
FROM THE PANELS. ICE MELT NEEDS TO BE KEPT CLEARED THROUGHOUT THIS TIME TO ENSURE THAT WATER
IS NOT REABSORBED BY THE PANELS.
RC RC RC RC RC RC
18 REMOVE ALL OF REFRIGERATED PRODUCTS FROM THE WALK-IN BOX THAT IS BEING IMPACTED. WMT WMT WMT WMT WMT WMT
17 NOTIFY THE WMT BUILDING CONTROLS TEAM AND ADVISE THEM WHICH SYSTEM AND WHICH WALK-IN BOX
WILL BE IMPACTED BY THE WORK.RC RC RC RC RC RC
16 NOTIFY THE EMS VENDOR 24 HRS. IN ADVANCE OF THE WORK - TELL THEM WHICH WALK-IN BOXES ARE BEING
IMPACTED.RC RC RC RC RC RC
15 FURNISH TEMPORARY REFRIGERATED STORAGE AS NECESSARY. WMT WMT WMT WMT WMT WMT
14 OBTAIN HOT WORK PERMITS AS REQUIRED. GC RC GC RC GC RC
13 COORDINATE THE INSTALLATION TIME WITH STORE MANAGEMENT. GC RC GC RC GC RC
12 PREFABRICATE AS MUCH OF THE PIPE WORK AND ELECTRICAL CONDUIT AS POSSIBLE AND MOUNT ANY
DEVICES IN ORDER TO REDUCE THE AMOUNT OF "DOWN TIME" NEEDED TO COMPLETE THE INSTALLATION.RC RC RC RC RC RC
11 TERMINATE POWER CABLES TO THE EVAPORATOR CONTROL PANEL. RC RC RC RC RC RC
10 FURNISH AND INSTALL ALL ELECTRICAL POWER CABLING FROM POWER SOURCE TO THE EVAPORATOR
CONTROL PANEL IF NECESSARY.GC RC GC RC GC RC
9 INSTALL AND TERMINATE CONTROLS WIRING (24 VOLTS OR LESS) AS DETAILED ON THE PRINTS. RC RC RC RC RC RC
8 FURNISH ALL CONTROLS CABLING AS NECESSARY TO COMPLETE THE WORK. (24 VOLTS OR LESS) EMS EMS EMS EMS EMS EMS
7 FIELD-INSTALL ALL REFRIGERATION VALVES. RC RC RC RC RC RC
6 FURNISH ALL ISOLATION VALVES. RC RC RC RC
5 FURNISH ALL FIELD-INSTALLED REFRIGERATION VALVES. OEM/WMT OEM/WMT OEM/WMT OEM/WMT OEM/WMT OEM/WMT
4 FURNISH AND INSTALL ALL (REFRIGERANT AND DRAIN) PIPING. RC RC RC RC RC RC
3 DEPENDING ON THE SCOPE OF WORK, FURNISH EVAPORATOR CONTROL PANELS EMS/WMT EMS/WMT EMS/WMT EMS/WMT EMS/WMT EMS/WMT
2 DEPENDING ON THE SCOPE OF WORK, FURNISH EVAPORATORS AS REQUIRED. OEM/WMT OEM/WMT OEM/WMT OEM/WMT OEM/WMT OEM/WMT
1 DEPENDING ON THE SCOPE OF WORK, FURNISH BATTEN AND SEAL, RELINE OR WALK-IN PANELS MATERIALS. PS/WMT PS/WMT PS/WMT PS/WMT PS/WMT PS/WMT
REMODEL CAPEX REMODEL CAPEX REMODEL CAPEX
BATTEN AND SEAL RELINE REPLACE EVAPORATOR/BOX# SCOPE OF WORK
RESPONSIBLE PARTY
***NOTE***
THIS DOCUMENT IS INTENDED TO DESCRIBE IMPORTANT ELEMENTS OF THIS PROJECT AND TO DEFINE THE RESPONSIBLE PARTIES FOR THIS WORK STREAM. IT IS NOT MEANT TO BE AN EXHAUSTIVE SOURCE OF INFORMATION OR A
COMPLETE SCOPE OF WORK. IT SHALL BE READ AND USED IN CONJUNCTION WITH ADDITIONAL, DETAILED INFORMATION IN THE WALMART REALTY ONE BEST WAY STANDARDS LIBRARY, AND IN PUBLICATIONS AVAILABLE FROM THE
MANUFACTURER.
WALK-IN BOX PROJECTS
ISSUE BLOCK
NOTE
WALK-IN PANEL
NETTING SYSTEM
REF SPECS
CUT OPENING IN NETTING NO
LARGER THAN 1" GREATER
THAN PENETRATION
LASH NETTING AT ALL CUT
PENETRATIONS, REF SPECS
ATTACH BOTTOM OF NETTING AT
EACH SIDE OF SPLICE WITH #10 x 3"
WOOD SCREWS AND #10 WASHERS
THROUGH GROMMETS, ADD
GROMMETS AS NEEDED
REF MEPFR FOR DUCT,
CONDUIT, AND PIPING
LOCATIONS AND SIZES
EXTERIOR WALL
EXISTING
ROOF SYSTEM
EXISTING
STRUCTURE
SECURELY FASTEN WEB
STRAP THROUGH EVERY
JOIST PANEL POINT, 6'-0"
OC MAX
INSTALL NETTING 60º MAX
IN RELATION TO
HORIZONTAL WALK-IN
CEILING PANELS
WEB STRAP
REF SPEC
NET SYSTEM
REF SPEC
ATTACH BOTTOM NET WEBBING
TO WALK-IN PANEL BLOCKING
AT 2'-0" OC THROUGH INTEGRAL
GROMMETS WITH #10 x 3" WOOD
SCREWS AND #10 WASHERS AT
3/4" FROM EDGE OF WALK-IN
PANEL
WALK-IN PANEL
GREATER THAN 2"GREATER
THAN 6"
SECURELY FASTEN WEB
STRAP THROUGH EVERY
JOIST PANEL POINT, 6'-0"
OC MAX
6
0
.
0
0
°
M
A
X
6
0
.
0
0
°
M
A
X
60.00° M AX
EXISTING
ROOF SYSTEM
EXISTING STRUCTURE
SECURELY FASTEN WEB
STRAP THROUGH EVERY
JOIST PANEL POINT, 6'-0"
OC MAX
INSTALL NETTING 60º MAX
IN RELATION TO
HORIZONTAL WALK-IN
CEILING PANELS
WEB STRAP
REF SPEC
NET SYSTEM
REF SPEC
ATTACH BOTTOM NET
WEBBING TO WALK-IN
PANEL BLOCKING AT 2'-0"
OC THROUGH INTEGRAL
GROMMETS WITH #10 x 3"
WOOD SCREWS AND #10
WASHERS AT 3/4" FROM
EDGE OF WALK-IN PANEL
CEILING AS SCHEDULED
WALK-IN PANEL
ALTERNATE CONDITION
6
0
.
0
4
°
M
A
X
WHERE NETTING HEIGHT IS LESS THAN
5', GATHER NETTING AT STRUCTURE TO
ENSURE FULL TENSION FROM WALK-IN
PANEL TO JOIST
TYPICAL WEB STRAP
ATTACHMENT AT
JOIST THROUGH JOIST
PANEL POINT
CEILING TILES
OMITTED FOR
CLARITY
NET SYSTEM
REF SPECS
INSTALL
NETTING
WITHOUT
SLACK
TOP WEB STRAP AT
CORNER FOR LOWER NET
TOP WEB STRAP AT
CORNER FOR UPPER NET
INSIDE CORNER AT SPLIT
ELEVATION
(TRANSVERSE NET
ATTACHMENT)
INSIDE CORNER AT SPLIT
ELEVATION
(PARALLEL NET
ATTACHMENT)
AT CORNERS PROVIDE ONE WEB STRAP TO TENSION NET
AT TOP CHORD AND ONE FROM JOIST PANEL POINT TO
FOOTMAN LOOP AT WALK-IN PANEL
ATTACH FOOTMAN LOOP WITH (2) #10 x 3" WOOD SCREWS
CENTERED ON WOOD BLOCKING 3/4" FROM EDGE OF WALK-IN
BOX, PLACE SCREW ATTACHMENT 1" MIN FROM END OF BOX,
REF SPEC
LOOP WEB STRAP
THROUGH EYE BOLT
1/2" SLEEVE ANCHOR WITH 3/8"
ROD COUPLING WITH 1 1/2" MIN
EMBEDMENT AND A 3/8" EYEBOLT
REF SPEC
WEAVE CONTINUOUS WEB
STRAP THROUGH NETTING
AT EACH OPEN END
PROVIDING 6" MIN OF NET
BEYOND STRAP
GATHER NETTING AT CORNERS
AND SECURE WITH LASHING
TIES, REF SPECS
CONTINUOUS WEB STRAP FROM 2"
FOOTMAN LOOP AT WALK-IN PANEL
THROUGH JOIST PANEL POINT AT ALL INSIDE
AND OUTSIDE CORNERS AND NET
TERMINATIONS
CENTER OPENING IN
NETTING WITH OPENING IN
CEILING GRID
ATTACH BOTTOM NET WEBBING TO WALK-IN
PANEL BLOCKING AT 24" OC THROUGH
INTEGRAL GROMMETS WITH (1) #10 x 3"
WOOD SCREW AND #10 WASHERS 3/4"
FROM EDGE OF WALK-IN PANEL
P1001 UNISTRUT WHERE REQ'D
FOR NET ATTACHMENT, LOCATE
WITHIN 3" OF JOIST PANEL POINTS
WEAVE CONTINUOUS WEB STRAP
THROUGH NETTING AT EACH OPEN
END, TYP
ATTACH WEB STRAPS TO UNISTRUT USING
5/16" EYEBOLT FASTENED TO UNISTRUT
WITH 5/16" NUTS AND WASHERS
WALL ANCHOR
NOTIFY WALMART PROJECT
MANAGER IF ANY EXISTING
WALK-IN BOXES DO NOT
HAVE EDGE PROTECTION
PRESENT AT THE LOCATIONS
SHOWN PRIOR TO THE
COMMENCEMENT OF THE
PROJECT -ADD MISSING
EDGE PROTECTION AND
COORDINATE WITH AOR TO
PROVIDE NECESSARY
DETAILS AND SPECS
GREATER
THAN 6"
WALK-IN EDGE WALK-IN AGAINST
WALL
WALK-IN ADJACENT
TO WALK-IN
WALK-IN ADJACENT
TO COOLER OF A
DIFFERENT HEIGHT
WALK-IN ADJACENT
TO CEILING
WALK-IN
BOX
WALK-IN
BOX
WALK-IN
BOX
WALK-IN
BOX
WALK-IN
BOXCEILING
TILE
WALL
NETTING NETTING NETTING
NETTING
NETTING
GREATER
THAN 2"
GREATER
THAN 2"
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
N2
EDGE
PROTECTION
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
1/2" = 1'-0" 4 NETTING PENETRATIONS
3/8" = 1'-0" 5 NET SYSTEM ATTACHMENT PARALLEL TO STRUCTURE
3/8" = 1'-0" 2 NET SYSTEM ATTACHMENT PERPENDICULAR TO STRUCTURE
1/4" = 1'-0" 1 NET SYSTEM ON WALK-IN BOX
1/2" = 1'-0" 3 EDGE PROTECTION
EDGE PROTECTION NET SYSTEM SUPPLIER:
WALMART APPROVED INSTALLERS:
EDGE PROTECTION
NET SYSTEM NOTES
EDGE PROTECTION NET SYSTEM IS EXISTING TO REMAIN ABOVE
WALK-INS BEING REPLACED.
CONTRACTOR SHALL CONTRACT WITH OWNER APPROVED
INSTALLERS FOR THE DETACHMENT AND/OR DEMOLITION OF EDGE
PROTECTION NET SYSTEM AS NECESSARY FOR DEMOLITION OF
WALK-INS PRIOR TO START OF DEMOLITION.
CONTRACTOR SHALL CONTRACT WITH OWNER APPROVED
INSTALLERS FOR THE RE-ATTACHMENT AND/OR RE-INSTALLATION
OF EDGE PROTECTION NET SYSTEM ABOVE WALK-INS BEING
REPLACED AFTER CONSTRUCTION OF WALK-INS IS COMPLETE.
EDGE PROTECTION NET SYSTEM IS FURNISHED BY OWNER.
CONTRACTOR SHALL COORDINATE WITH OWNER APPROVED
INSTALLERS AND OWNER EDGE PROTECTION NET SYSTEM
SUPPLIER FOR ACQUISITION OF ANY NEW REQUIRED
COMPONENTS.
REF SPECIFICATION 13300 FOR EDGE PROTECTION NET SYSTEM.
CONTRACTOR SHALL COORDINATE ALL WORK INVOLVING THE
EDGE PROTECTION NET SYSTEM WITH THE WALMART
MECHANICAL CONSTRUCTION MANAGER.
HAINES, JONES, & CADBURY
APOLLO
JEFF ORNS
IL, IN, KY, NC, OH, TN, VA, & WV
CAN
TIM BARRY
CT, DE, MA, MD, ME, NH, NJ, NY, PA, RI, & VT
GM NORTHRUP
JASON FARMAKIS
MI, MN, ND, SD, & WI
GREATER SOUTHWEST CONSTRUCTORS
JOHN WILKINSON
AR, LA, OK, & TX
MICHAEL STRAIN BUILDERS
SHERI COLVELL
AK, AZ, CA, HI, ID, MT, NM, NV, OR, UT, WA, & WY
NEWCO
BILL BROWN
AL, FL, GA, MS, & SC
QUAL-SERV
JOSH PADGETT
CO, IA, KS, MO, & NE
(800) 459-7099
WMT@hjcinc.com
(479) 601-9484
jeff.orns@apolloretail.com
(201) 996-9287
tlbarry@can-usa.net
(952) 226-3090
jfarmakis@gmnorthrup.com
(817) 596-3513
jwilkinson@centurytel.net
(760) 751-5050
Sheri@msbuilders.com
(352) 735-3877
bill@newcoconstruction.com
(479) 459-6349
jpadgett@qualservsolutions.com
ISSUE BLOCK
NOTE
E
E
E
EE
1
1
2
2
3
3
4
4
G G
H H
J J
ICE CREAM
FREEZER
GROCERY
FREEZER
2.21 TYP
2.32
2.32
DAIRY
COOLER
2.20
2.19
C-1
BML220C
(REPLACE)
EXISTING CONDENSATE HEADER
TO REMAIN. REPAIR ANY DAMAGE
TO HEADER AFTER WALK-IN
REPLACEMENT IS COMPLETE.
PROVIDE DUST WALL PROTECTION
AT ALL DEMOLISHED WALLS
BETWEEN ADJACENT SPACES
DURING CONSTRUCTION.
2
D1
CAP CIRCUIT C1 LIQUID
AND SUCTION LINES
FOR REUSE.
2.32
EXISTING PIPING TO
REMAIN. NOT ALL PIPING
SHOWN. TYP; UNO.
C1
2.272.15
2.27
SALES DEMO AREA
ROOF DECK
COORDINATE WITH SPECS
ANCHOR AT 24" OC
2 x 4 AT 24" OC
WALL TO
BE REMOVED
INSTALL CONT
LAYER 6 MIL POLY
SHEETS TAPE ALL
JOINTS
1/2" CD PLYWOOD
4'-0" x 8'-0"
HORIZONTAL
PROVIDE 2x4 NAILER
AT ALL JOINTS
CONTINUE PLYWOOD
TO DECK
DO NOT USE DUST
WALL TO SHORE ROOF
JOISTS
6'-0" LOAD BEARING
4'-0" ELSEWHERE
NOTES:
1. INSTALL TEMPORARY
WALL IN SECTIONS
APPROX 40'-0" PER DAY
(COORDINATE WITH
STORE MANAGER AND
WALMART
CONSTRUCTION
MANAGER)
2. LOCATE VERTICAL
2x4'S AS NOT TO
INTERFERE WITH
CEILING GRID OR LIGHT
FIXTURES
3. LOCATE HORIZONTAL
2x4 AT 2" ABOVE
CEILING EXCEPT LIGHT
FIXTURE LOCATIONS
4. SCREW PLYWOOD
(MAX SPACING 12" OC)
PAINT DUST WALLS TO MATCH
ADJACENT IF DUST WALLS TO
BE IN PLACE MORE THAN TWO
WEEKS -COORDINATE WITH
WALMART CONSTRUCTION
MANAGER
2 x 4 TREATED WOOD
SILL PLATE
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.D1
DEMOLITION
PLAN
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
DEMOLITION REQUIREMENTS
1 ALL DEMOLITION SHALL BE CARRIED OUT IN A SAFE
MANNER AND IN STRICT ACCORDANCE WITH OSHA
REGULATIONS.
2 THE CONTRACTOR SHALL FIELD VERIFY THE EXTENT OF
DEMOLITION. THE WORK INCLUDES, BUT IS NOT LIMITED
TO, THE DEMOLITION AND REMOVAL OF WALLS, DOORS,
FLOORS, AND ELECTRICAL ITEMS INCLUDING CONDUITS AS
SHOWN ON DRAWING OR AS REQUIRED FOR THE
INSTALLATION OF NEW WORK FOR A COMPLETE JOB.
3 WHEN UTILITIES ARE REMOVED, CAP AND SEAL A MINIMUM
OF 8" BELOW FINISH FLOOR OR A MINIMUM OF 6" ABOVE
FINISHED CEILING. SHOW ALL ABANDONED AND CAPPED
UTILITIES ON AS-BUILTS, DRAWINGS, AND RECORDED
DOCUMENTS.
4 IT IS THE CONTRACTOR'S RESPONSIBILITY TO PROVIDE
ADEQUATE SHORING, BRACING, AND SUPPORT SYSTEMS
AND TO KEEP THE EXISTING STRUCTURE INTACT AND IN A
SAFE CONDITION DURING THE REMOVAL OF STRUCTURAL
ITEMS AND NEW CONSTRUCTION.
5 THE CONTRACTOR SHALL RETAIN A REGISTERED
PROFESSIONAL ENGINEER TO DESIGN THE SHORING AND
SPECIFY DEMOLITION PROCEDURES.
6 IT IS THE CONTRACTOR'S RESPONSIBILITY FOR MEANS
AND METHODS OF DEMOLITION AND NEW
CONSTRUCTION. PRIOR TO THE EXCAVATION OF
FOUNDATIONS ADJACENT TO THE EXISTING STRUCTURE,
PROVIDE ADEQUATE SUPPORT FOR THE SUB-BASE TO
PREVENT UNDERMINING.
7 DURING DEMOLITION AND RECONSTRUCTION, THE
CONTRACTOR SHALL COORDINATE WITH THE WALMART
MECHANICAL CONSTRUCTION MANAGER ANY REQUIRED
SAFETY BARRIERS OR BARRICADES AND DUST WALLS.
REFER TO THE WALMART MECHANICAL CONSTRUCTION
MANAGER FOR PHASING AND SCHEDULING DEMOLITION
AND NEW CONSTRUCTION.
8 DISPOSAL OF ALL DECOMMISSIONED EQUIPMENT, NOT
APPORTIONED TO WALMART'S DESIGNATED SALVAGE
VENDOR, SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR IN ACCORDANCE WITH LOCAL CODES AND
ANY GOVERNMENTAL REGULATIONS; REFER TO WALMART
DIRECTIVES AND SPECIFICATIONS. THE CONTRACTOR
SHALL COORDINATE THE PICK-UP DATE WITH THE
DESIGNATED SALVAGE VENDOR, PREPARE AND LOAD
THE DESIGNATED SALVAGE ITEMS, KEEPING THEM
INTACT AND IN ACCORDANCE WITH LOCAL CODES AND
ANY GOVERNMENTAL REGULATIONS; REFER TO WALMART
DIRECTIVES AND SPECIFICATIONS. ITEMS TO BE
SALVAGED BY WALMART'S DESIGNATED SALVAGE
VENDOR SHALL BE LIMITED TO: VARIABLE FREQUENCY
DRIVES, CONDENSING UNITS, CONDENSERS,
EVAPORATORS, COPPER PIPING, ROOF TOP UNITS, AIR
HANDLING UNITS, AND COMPRESSOR HOUSES.
8-TX DISPOSAL OF ALL DECOMMISSIONED EQUIPMENT, NOT
APPORTIONED TO WALMART'S DESIGNATED SALVAGE
VENDOR, SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR IN ACCORDANCE WITH LOCAL CODES AND
ANY GOVERNMENTAL REGULATIONS; REFER TO WALMART
DIRECTIVES AND SPECIFICATIONS. THE CONTRACTOR
SHALL COORDINATE THE PICK-UP DATE WITH THE
DESIGNATED SALVAGE VENDOR, PREPARE AND LOAD THE
DESIGNATED SALVAGE ITEMS, KEEPING THEM INTACT AND
IN ACCORDANCE WITH LOCAL CODES AND ANY
GOVERNMENTAL REGULATIONS; REFER TO WALMART
DIRECTIVES AND SPECIFICATIONS. ITEMS TO BE
SALVAGED BY WALMART'S DESIGNATED SALVAGE
VENDOR SHALL BE LIMITED TO: REFRIGERATED CASES AS
DESIGNATED BY THE WALMART CONSTRUCTION
MANAGER, WALK-IN PANELS, MCCUE RAILING, VARIABLE
FREQUENCY DRIVES, CONDENSING UNITS, CONDENSERS,
EVAPORATORS, COPPER PIPING, ROOF TOP UNITS, AIR
HANDLING UNITS, AND COMPRESSOR HOUSES.
9 REFER TO SPECIFICATIONS SECTION 1500 FOR
ADDITIONAL INFORMATION REGARDING STORMWATER
RUNOFF CONTROL.
10.CONDUCT ALL DEMOLITION AND REMOVAL OF DEBRIS AS
REQUIRED TO ENSURE MINIMUM INTERFERENCE WITH
BUILDING/SITE FACILITIES AND OPERATIONS.
11.NOTES INDICATING DEMOLITION WORK ARE NOT
CONFINED SOLELY TO THE DEMOLITION PLANS. THE
CONTRACTOR SHALL REVIEW ALL CONSTRUCTION
DOCUMENTS, INCLUSIVE OF SCHEDULES AND
SPECIFICATIONS, TO DETERMINE FULL EXTENT OF
DEMOLITION WORK.
DEMOLITION NOTES
1.REMOVAL OF ANY SALVAGE EQUIPMENT OR DEBRIS IS
PROHIBITED. THIS INCLUDES THE SALE OF COPPER,
ALUMINUM, OR ANY RELATED MATERIALS.
2.WHERE APPLICABLE WALK-IN PANEL MANUFACTURER
SHALL DEMOLISH AND PROMPTLY HAUL OFF WALK-IN
PANELS AND DOORS TO BE REPLACED.
3.DURING DEMOLITION AND RECONSTRUCTION PHASES,
COORDINATE LOCATION OF ALL DUST WALLS AND
SECURITY ENCLOSURES WITH WALMART STORE
MANAGER. REFER TO DUST WALL DETAIL.
4.ALL NEW EQUIPMENT MUST BE ON SITE PRIOR TO
STARTING ANY DEMOLITION OR CONSTRUCTION.
5.PATCH/REPAIR FLOOR COVERING AS REQUIRED AFTER
INSTALLATION OF NEW CASES. MATCH EXISTING
FLOORING TYPE, COLOR, PATTERN, AND FINISH.
CONSTRUCTION LEGEND
EXISTING TO REMAIN
DEMOLISHED
AREA TO BE DEMOLISHED
KEYNOTES
2.15 REMOVE EXISTING DOOR PROTECTION.
2.19 EDGE PROTECTION NET SYSTEM IS EXISTING TO REMAIN
ABOVE WALK-IN BEING DEMOLISHED. CONTRACTOR SHALL
CONTRACT WITH OWNER APPROVED INSTALLERS FOR THE
DETACHMENT AND/OR DEMOLITION OF EDGE PROTECTION
NET SYSTEM AS NECESSARY FOR DEMOLITION OF WALK-IN
PRIOR TO START OF DEMOLITION. REFER TO EDGE
PROTECTION NET SYSTEM NOTES. COORDINATE ALL WORK
INVOLVING THE EDGE PROTECTION NET SYSTEM WITH THE
WALMART MECHANICAL CONSTRUCTION MANAGER.
2.20 REPLACE WALK-IN IN SAME LOCATION. COOLER PANEL
MANUFACTURER TO DEMOLISH EXISTING WALK-IN.
CONTRACTOR TO DEMOLISH EXISTING EVAPORATOR,
PIPING, CONDENSATE PIPING, CURBS/FLOOR RAILING, DOOR
GUARDS, FLOORING, PLUMBING, ELECTRICAL, DUCTWORK,
AND DRY WALL AS REQUIRED. CONTRACTOR TO REMOVE
RACKING AFTER STORE HAS REMOVED ALL MERCHANDISE.
2.21 CONTRACTOR TO REMOVE EXISTING STEEL RACKING IN
WALK-INS. COORDINATE DISPOSAL OR SALVAGE OF
RACKING WITH THE WALMART MECHANICAL CONSTRUCTION
MANAGER.
2.27 REMOVE EXISTING PIPE BOLLARDS. GRIND DOWN FLUSH
WITH FLOOR SLAB. PATCH AND REPAIR FLOOR AS
NECESSARY.
2.32 CONTRACTOR TO TEMPORARILY REMOVE EXISTING STEEL
RACKING AS NECESSARY TO PERFORM WORK INDICATED.
COORDINATE STORAGE OF STEEL RACKING DURING
CONSTRUCTION WITH WALMART MECHANICAL
CONSTRUCTION MANAGER.
1/8" = 1'-0" 1 DEMOLTION PLAN
NTS2DUST WALL SECTION
ISSUE BLOCK
NOTE
E
E
E
E
EE
1
1
2
2
3
3
4
4
G G
H H
J J
NETTING ETR.
ICE CREAM
FREEZER
12'
R5003.000
GROCERY
FREEZER
11.24
DAIRY
COOLER
11.23 TYP
60"x90" SLIDING DOOR WITH
STRIP CURTAIN.
11.29
REPLACED EXISTING
SLIDING 48"x84" DOOR
11.21
TYP11.32
WALK-IN DOORS, WINDOWS, HARDWARE,
WALL LINER MATERIALS, ETC. SHALL BE
FURNISHED AND INSTALLED BY COOLER
PANEL MANUFACTURER.
18
'
-
2
"
18' - 0"
FREEZER DIMENSIONS ARE
NOMINAL OUTSIDE
DIMENSIONS. COOLER PANEL
MANUFACTURER TO FIELD
VERIFY EXACT WALK-IN SIZES.
32" GALVANIZED STEEL
BOLLARD, 4" OD FURNISHED
BY OWNER, INSTALLED BY GC
2
F1
4
F1
3
F1
6
F1
TYP; UNO
CONTRACTOR SHALL FURNISH AND
INSTALL STAINLESS STEEL TRIM TO CLOSE
ANY GAPS THAT ARE LEFT BETWEEN WALK-
IN AND WALLS AND/OR CEILINGS AFTER
WALK-IN INSTALLION IS COMPLETED BY THE
WALK-IN PANEL MANUFACTURER.
5
F1
NEW STEEL ANGLE.
HCR PCAV DOOR
R0700.001
RA5000; TYP.
PREMANUFACTURED
COOLER/FREEZER PANEL,
NIC6" x 4" x 3/8" CONTINUOUS
STEEL ANGLE PAINT.
SAFTEY YELLOW OSHA
STANDARD.
1/2" DIA x 2-1/2" CONCRETE
SCREW ANCHOR AT 12" OC
PROVIDE 2-1/2" DEEP HOLE IN
SLAB AND INSTALL ANCHOR TO
SNUG TIGHT
CONCRETE SLAB
REF TO PROCTECTOR ANGLE DETAIL
FOR MORE STEEL ANGLE PLACEMENT,
VERIFY LOCATIONS FOR ADDITIONAL
ANGLES NOT SHOWN ON PLANS WITH
WALMART CONSTRUCTION MANAGER
5"
REF 3 -F1
REF 3 -F1
REF 3 -F1
ANGLE AT PUSH SIDE OF
INTERIOR DOOR
ANGLE AT
CORNERS
ANGLE AT PULL SIDE OF
INTERIOR DOOR
INTERIOR
DOOR
6 x 4 x 3/8" CONT
STEEL ANGLE
PROVIDE
SMOOTH EDGE
INTERIOR DOOR
PROVIDE
SMOOTH EDGE
WALL
6 x 4 x 3/8" CONT
STEEL ANGLE
6 x 4 x 3/8" CONT
STEEL ANGLE
WALL
6"
MI
N
1'
-
6
"
6"
MI
N
1'
-
0
"
10
"
10"
#4 x 6" AT 24" OC
WITH 2" EMBED
6" x 6" CONC. CURB
SEALANT
PREMANUFACTURED
COOLER/FREEZER PANEL, NIC
SL
O
P
E
1/
2
"
POLYETHYLENE BETWEEN
CURB AND COOLER WALL
1'
-
4
"
STEEL BOLLARD,
REF FLOOR PLANS FOR
TYPE AND LOCATION
STEEL ANGLE, REF FLOOR
PLANS FOR TYPE AND
EXACT LOCATION
WALK-IN PANEL WALL
AND DOOR BY OWNER, REF
FLOOR PLAN FOR DOOR TYPE
AIR DOOR REF PLANS FOR
LOCATION.
EXTERIOR
WALK-IN
INTERIOR
WALK-IN
CURBS, REF FLOOR PLANS
FOR TYPE, SIZE, NUMBER
AND EXACT LOCATION, TYP
NOTE:
1. SEALED CONCRETE CURBS ARE TO BE FORMED AFTER WALLS, WALK-INS,
ETC ARE IN PLACE, USING FACE OF WALL OR WALK-IN PANEL AS SIDE FORM
2. TYP DETAIL, REF PLAN FOR DOOR ORIENTATION
3. FOR WATERPROOFING,
CL
#6 SCREWS AT MAX 9" OC EACH SIDE,
EVENLY SPACE FASTENERS
PROVIDE 1" TOE KICK RETURN EACH SIDE
CONT CLEAR COATED 20 GA GALVANIZED
STEEL INFILL PANEL WITH HEMMED EDGES
SET IN A BED OF SEALANT EACH SIDE
FV
1"
1"
FV
FV
REFRIGERATED CASES
FV
HE
I
G
H
T
O
F
P
A
N
E
L
T
O
M
A
T
C
H
A
D
J
A
C
E
N
T
C
A
S
E
S
FOR OPENINGS OVER 24" IN WIDTH
INSTALL BACKUP FRAMING PER DETAIL
AND FASTEN TO HORIZONTAL FRAMING
MEMBERS AT MAX 9" OC WITH #6
SCREWS, EVENLY SPACE FASTENERS
PLAN AT FRONT OF
CASE AND WALL
REFRIGERATED
CASE
PLAN AT FRONT OF CASE
AND END OF WALL
1" MAX
FASTENER
AT PARTITION
1/2" MAX
FASTENER
AT CASE
PLAN AT CASES
REFRIGERATED
CASE
FRONT
FR
O
N
T
REFRIGERATED
CASE
FRONT
1/2" MAX
FASTENER TYP
PLAN AT REAR OF CASE
AND WALL
REFRIGERATED
CASE
FR
O
N
T
PARTITION OR
WALL
1" MAX
FASTENER
AT PARTITION
1/2" MAX
FASTENER
AT CASE
PARTITION OR
WALL
PLAN AT WALK-IN
PARTITION
OR WALL
1/2" MAX
FASTENER
TYP
WALK-IN
PANEL PARTITION
OR WALL
REFRIGERATED
CASE
FRONT
1/2" MAX
FASTENER
1/2" MAX
FASTENER
(PLAN VIEW)
SECTION AT TOP OF
CASE AND WALL
REFRIGERATED
CASECLOSURE
PANEL
1/2" MAX
FASTENER
PARTITION
OR WALL
CLOSURE
PANEL
CLOSURE
PANEL
CLOSURE
PANEL
CLOSURE
PANEL
CLOSURE
PANEL
TY
P
1"
OV
E
R
L
A
P
TYP
1"
OVERLAP
TYP
1"
OVERLAP
TYP
1"
OVERLAP
TY
P
1"
OV
E
R
L
A
P
NOTES:
1. REFRIGERATION CONTRACTOR TO PROVIDE GALVANIZED CLOSURE PANELS
AT ALL VERTICAL GAPS AND AT ALL HORIZONTAL GAPS 52" OR LOWER AFF
BETWEEN REFRIGERATED CASE, WALLS, AND/OR EQUIPMENT
2. PROVIDE SS CLOSURE PANELS LOCATED IN PREP AREAS
3. REF FLOOR PLANS FOR ALL PARTITION TYPES AND LOCATIONS
4. EASE EXPOSED EDGES TO SMALL UNIFORM RADIUS
5. SET CLOSURE PANEL IN A BED OF SEALANT EACH SIDE
6. FASTEN CLOSURE PANELS WITH #6 PAN HEAD SCREWS AT 9" OC
7. CLOSURE PANELS TO BE FASTENED ONLY TO BACK OF REFRIGERATED CASE
OR END PANEL SKINS AS INDICATED IN DRAWINGS
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.F1
FIXTURE
PLANS AND
SCHEDULES
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
GENERAL NOTES
1.DIMENSIONS OF REFRIGERATED CASES ARE TO THE
OUTERMOST POINTS OF THE CASES; ENDCAPS AND
BUMPERS ARE CONSIDERED PART OF THE CASE,
WHERE THEY OCCUR. DIMENSIONS ON THE FIXTURE
PLANS ARE FOR LAYOUT OF OWNER-FURNISHED
ITEMS ONLY AND ARE NOT TO BE USED FOR
LOCATION OF WALLS AND OTHER CONTRACTOR
BUILT ITEMS.
2.CONTRACTOR SHALL FURNISH AND INSTALL
STAINLESS STEEL TRIM TO CLOSE ANY GAPS THAT
ARE LEFT BETWEEN THE END CASES AND LONG
CASE RUNS AFTER THE CASES ARE SET IN THEIR
FINAL POSITION.
3.CASES FURNISHED BY WALMART, INSTALLED BY
CONTRACTOR. ALL NEW EQUIPMENT MUST BE ON
SITE PRIOR TO STARTING ANY DEMOLITION OR
CONSTRUCTION.
4.WALK-IN COOLERS/FREEZERS FURNISHED AND
INSTALLED BY COOLER PANEL MANUFACTURER. ALL
NEW EQUIPMENT MUST BE ON SITE PRIOR TO
STARTING ANY DEMOLITION OR CONSTRUCTION.
5.CONTRACTOR SHALL BE RESPONSIBLE FOR
MISCELLANEOUS WALK-IN COOLER/FREEZER WORK
INCLUDING BUT NOT LIMITED TO EVAPORATORS,
ELECTRICAL, EMS, SPRINKLER PENDANTS, CURBS,
SANITARY COVE BASE, THRESHOLDS, FLOOR REPAIR
AND RACKING.
6.PROPER INSTALLATION OF JOINT SEALANTS IS
CRITICAL TO MEETING WALMART QUALITY
ASSURANCE STANDARDS. PROVIDE SEALANTS IN
ACCORDANCE WITH DRAWINGS AND
SPECIFICATIONS. REFERENCE SPECIFICATIONS FOR
SEALANT SCHEDULE.
7.ALL JOINTS BETWEEN DISSIMILAR MATERIALS SHALL
BE SEALED AS REQUIRED FOR A COMPLETE AND
PROPER INSTALLATION, REGARDLESS OF WHETHER
SHOWN ON THE DRAWINGS OR INDICATED IN THE
SPECIFICATIONS. SUCH JOINTS NOT SHOWN OR
SCHEDULED SHALL BE SEALED WITH SEALANTS
CONSISTENT WITH SPECIFIED MATERIALS OR AS
RECOMMENDED BY THE MANUFACTURER FOR THE
SPECIFIC APPLICATION.
8.INTERIOR SEALANTS USED IN FOOD PREPARATION
AREAS SHALL MEET THE REQUIREMENTS FOR USE IN
USDA REGULATED FACILITIES.
9.INSTALL CONTINUOUS USDA APPROVED SEALANT AT
ALL JOINTS BETWEEN MATERIALS ON WALLS AND
FLOORS IN FOOD PREPARATION COOLER AND
FREEZER AREAS.
10.ALL FIXED (NON-MOVEABLE) EQUIPMENT INCLUDING
SINKS, OVENS, AND REFRIGERATED EQUIPMENT
SHALL BE SEALED TO THE WALLS. BASE OR LEGS
SHALL BE SET IN A BED OF SEALANT WITH EXCESS
REMOVED. MOVEABLE EQUIPMENT SHALL NOT BE
SEALED.
11.ROUTE ALL UTILITY SERVICE LINES (PIPES AND
CONDUIT) WITHIN STUD WALLS WHEREVER
POSSIBLE. ON COOLER/FREEZER PANELS IN FOOD
PREP AREAS WHERE UTILITIES MUST BE EXPOSED,
CONTRACTOR TO HAVE THE OPTION OF THE
FOLLOWING:
A.SURFACE MOUNT UTILITIES WITH NON-
CORROSIVE ANCHORS; SEAL BOTH SIDES OF
PIPE/CONDUIT TO PANEL CONTINUOUSLY
WITH SEALANT.
B.INSTALL UTILITIES 1/2" OFF FACE OF PANEL TO
ALLOW FOR CLEANING; USE ONLY NON-
CORROSIVE MATERIALS FOR SPACERS AND
ANCHORS.
C.COVER UTILITIES WITH 20 GAUGE STAINLESS
STEEL BENT PLATES MOUNTED TO WALL
WITH NON-CORROSIVE ANCHORS; APPLY
CONTINUOUS SEALANT ALONG EDGES AND
JOINTS.
CONSTRUCTION LEGEND
NEW WALL CONSTRUCTION
NEW COOLER WALL CONSTRUCTION
CONTRACTOR IS RESPONSIBLE, UPON AWARD, TO CONTACT AND VERIFY ALL DELIVERIES DATES/TIMES WITH EVERY VENDOR LISTED BELOW, OR TO CHANGE ANY DATES
OR DELIVERIES, CONTRACTOR MUST CONTACT WALMART CONSTRUCTION MANAGER, THIS IS UNIQUE TO CAPITAL EXPENDITURES PROJECTS.
EQUIPMENT SCHEDULE
MARK DESCRIPTION MANUFACTURER MODEL
SUPPLIED
BY
INSTALLED
BY
FINAL
CONNECT
HORIZONTAL SLIDING WALK-IN DOOR WITH STRIP CURTAIN (60X90) VARIES VARIES OW
HORIZONTAL SLIDING WALK-IN DOOR WITHOUT STRIP CURTAIN (48X60) VARIES VARIES OW
R0700.005 PUSH THROUGH VESTIBULE (72X108) KPS GLOBAL PCAV OW
R5003.000 WALK-IN PANELS KPS GLOBAL LLC <varies> OW
RA5000 RACK INDUSTRIAL RIDG-U-RACK INC UNKNOWN OW
KEYNOTES
11.21 EDGE PROTECTION NET SYSTEM IS EXISTING TO REMAIN
ABOVE WALK-IN BEING REPLACED. CONTRACTOR SHALL
CONTRACT WITH OWNER APPROVED INSTALLERS FOR THE
RE-ATTACHMENT AND/OR RE-INSTALLATION OF EDGE
PROTECTION NET SYSTEM ABOVE WALK-IN BEING
REPLACED AFTER CONSTRUCTION OF WALK-IN IS
COMPLETE. REFER TO EDGE PROTECTION NET SYSTEM
NOTES. COORDINATE ALL WORK INVOLVING THE EDGE
PROTECTION NET SYSTEM WITH THE WALMART
MECHANICAL CONSTRUCTION MANAGER. COOLER/FREEZER
WALK-INS, DOORS, WINDOWS, HARDWARE, WALL LINER,
MATERIALS, ETC. SHALL BE FURNISHED AND INSTALLED BY
COOLER PANEL MANUFACTURER.
11.23 CONTRACTOR TO RESET STEEL RACKING IN WALK-INS. THIS
INCLUDES LABOR AND MATERIAL TO DRILL AND PIN
RACKING TO THE FLOOR AS PER THE MANUFACTURERS
SPECIFICATIONS. COORDINATE LOCATIONS WITH THE
WALMART MECHANICAL CONSTRUCTION MANAGER. STEEL
AND GRID SUPPLIED BY WALMART.
11.24 6" WIDE x 6" HIGH CONTINUOUS CONCRETE CURB AT BASE
OF WALK-IN.
11.29 PATCH AND REPAIR EPOXY FLOOR AS NECESSARY.
PROVIDE SMOOTH TRANSITION AT DOORWAYS. MATCH
EXISTING FLOOR FINISHES.
11.32 CONTRACTOR TO RESET TEMPORARILY REMOVED STEEL
RACKING. THIS INCLUDES LABOR AND MATERIAL TO DRILL
AND PIN RACKING TO THE FLOOR AS PER THE
MANUFACTURERS SPECIFICATIONS. COORDINATE
LOCATIONS WITH WALMART MECHANICAL CONSTRUCTION
MANAGER.
EXISTING TO REMAIN
DEMOLISHED
AREA TO BE DEMOLISHED
ABBREVIATION KEY
GC -CONTRACTOR
OW -WALMART
V -VENDOR
1/8" = 1'-0" 1 FIXTURE PLAN
1" = 1'-0" 3 PROTECTOR ANGLE INSTALLTION
1/2" = 1'-0" 6 PROTECTOR ANGLE
1" = 1'-0" 4 CONCRETE CURB DETAIL
1/2" = 1'-0" 2 COOLER/FREEZER SLIDING DOOR
NTS5CLOSURE PANEL DETAIL
V
V
V
V
V
C
C
C
C
C
-
-
ISSUE BLOCK
NOTE
E
E
E
E
EE
1
1
2
2
3
3
4
4
5
5
6
67
8
8
9
9
10
10
11
11
12
12
13
13
A A
B B
C C
D D
E E
F F
G G
H H
J J
K K
2
FP2FP2
1
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.FP1
OVERALL FIRE
SPRINKLER
PLAN
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
N 0 20'40'60'
SCALE: 1"=40'-0"
7. THE FIRE PROTECTION ENGINEER OF RECORD
SHALL NOT BE RESPONSIBLE FOR THE
CONTRACTOR'S FAILURE TO CARRY OUT THE
CONSTRUCTION WORK IN ACCORDANCE WITH THE
CONTRACT DOCUMENTS, NOR SHALL THEY BE
REQUIRED TO SUPERVISE THE CONDUCT OF THE
WORK, THE CONSTRUCTION PROCEDURES
FOLLOWED BY THE CONTRACTOR,
SUBCONTRACTORS, THEIR RESPECTIVE
EMPLOYEES OR ANY OTHER PERSON AT THE JOB
SITE OTHER THAN THAT OF THE ENGINEERING
FIRM'S EMPLOYEES.
8. CONTRACTOR MUST REVIEW ALL CONSTRUCTION
DOCUMENTS PRIOR TO BID. SHOULD
MODIFICATIONS TO THESE PLANS BECOME
NECESSARY TO PROPERLY COORDINATE THE
SYSTEM WITH ALL OTHER TRADES, IT WILL BE THE
CONTRACTOR'S RESPONSIBILITY TO OBTAIN
APPROVAL OF THE CHANGES FROM BOTH THE
AUTHORITY HAVING JURISDICTION AND THE
OWNER'S DESIGNATED REVIEW CONSULTANT IN
ADDITION TO OBTAINING THE NECESSARY
APPROVALS, THE CONTRACTOR MUST MAKE NOTE
OF ANY FIELD OR COORDINATION CHANGES ON THE
INSTALLATION DRAWINGS, AND THEN MUST
PROVIDE A SET OF AS-BUILT DRAWINGS ONCE
COMPLETE.
9. CONTRACTOR MUST VERIFY ALL DROP DOWN
LOCATIONS AT EXTERIOR WALLS WITH THE
PROJECT MANAGER PRIOR TO INSTALLATION.
10. ALL PIPING MUST BE COORDINATED AROUND
FRAMING MEMBERS AND PROPERLY INSTALLED
INSIDE THE BAR JOIST.
11. CONTRACTOR SHALL ROUTE PIPING AROUND ALL
OBSTRUCTIONS AND PROVIDE SPRINKLER
PROTECTION UNDER OBSTRUCTIONS, AS DETAILED
IN NFPA 13 STANDARDS AS PART OF THE FIELD
COORDINATION AT NO ADDITIONAL COST TO
OWNER.
12. ALL SPRINKLER DEFLECTOR DISTANCE
REQUIREMENTS SHALL BE IN ACCORDANCE TO THE
STANDARDS OUTLINED IN NFPA 13.
13. ALL PIPING PASSING THROUGH CMU WALLS SHALL
BE INSTALLED WITH ONE INCH CLEARANCE ON ALL
SIDES. (CORE DIAMETER EQUAL TO PIPE +2"). ALL
CORES SHALL BE COORDINATED WITH STRUCTURAL
REINFORCING. CONTRACTOR IS RESPONSIBLE FOR
PROVIDING ALL CORING WITH PROPER CLEARANCE
AT ALL CMU WALLS. GENERAL CONTRACTOR SHALL
BE RESPONSIBLE FOR PROVIDING A TWO INCH
CLEARANCE AROUND ALL PIPING PASSING
THROUGH CONCRETE SLABS. THE SPRINKLER
CONTRACTOR SHALL FILL ALL CLEARANCES WITH
APPROVED MASTIC.
14. PROVIDE FLUSHING CONNECTIONS IN ACCORDANCE
WITH THE STANDARDS OUTLINED IN NFPA 13.
15. PROVIDE ALL NECESSARY OFFSETS, RISES OR
DROPS IN PIPING AND AUXILIARY DRAINS REQUIRED
BY BUILDING CONDITIONS.
16. EXAMINE THE JOB CONDITIONS AND VERIFY ALL
MEASUREMENTS, DISTANCES, ELEVATIONS,
CLEARANCES, ETC.
17. ARCHITECTURAL AND ELECTRICAL BACKGROUND
INFORMATION IS SHOWN FOR COORDINATION
PURPOSES ONLY. REFER TO THE CONTRACT
DOCUMENTS FOR LOCATIONS, SIZES AND
QUANTITIES OF OTHER TRADE WORK.
18. SPRINKLER SPACING SHALL BE PER NFPA 13
UNLESS OTHERWISE NOTED ON PLANS AND/ OR
PROTECTION CRITERIA LEGEND.
19. INTERFACE SPRINKLER SYSTEM WITH FIRE
PROTECTION SUPERVISORY SYSTEM.
20. ALL MATERIALS SHALL BE UL LISTED OR FM
APPROVED. SPRINKLER PIPE SHALL BE
MANUFACTURED TO STANDARDS RECOGNIZED BY
NFPA 13., THREADED PIPE SHALL HAVE A
CORROSION RESISTANCE RATING OF 1.0 OR
GREATER. CRIMP-TYPE COUPLINGS SHALL NOT BE
USED. THREADABLE THINWALL PIPE WITH
CORROSION RESISTANCE RATING OF LESS THAN 1.0
SHALL BE USED ONLY WITH ROLL GROOVE FITTINGS.
21. IF REQUIRED, PROVIDE 24 VOLT AC, ELECTRIC BELL,
MODEL NO. PBA248, ELECTRIC BELL BY POTTER
ELECTRIC SIGNAL OF ST. LOUIS, MISSOURI, LOCATE
AS REQUIRED BY AUTHORITIES HAVING
JURISDICTION. PROVIDE NEW DOUBLE POLE VANE
TYPE FLOW DETECTOR, MODEL NO. VSR-F, BY
POTTER ELECTRIC SIGNAL OF ST. LOUIS, MISSOURI.
SET ADJUSTABLE DELAYED SIGNAL AT 30 SECONDS.
MOUNT WATER FLOW INDICATORS NO HIGHER THAN
6 FEET ABOVE FINISH FLOOR.
22. ALL SPRINKLER SYSTEMS THAT ARE TO BE
MODIFIED SHALL BE HYDROSTATICALLY TESTED PER
NFPA 13 PRIOR TO SPRINKLER SYSTEM
MODIFICATION AND SHALL BE RE-HYDROSTATICALLY
TESTED AFTER COMPLETION OF WORK.
23. DO NOT HANG OR SUPPORT ANY LOADS OR MAKE
ANY ATTACHMENTS TO THE METAL ROOF DECK OR
JOIST BRIDGING.
24. SAMMY SCREWS ARE NOT PERMITTED.
25. CEILING FLANGES ARE NOT PERMITTED.
26. PROVIDE RETAINING STRAPS ON HANGERS WHERE
REQUIRED.
27. CONTRACTOR IS TO COORDINATE FINAL SPRINKLER
HEAD LOCATIONS AND PIPE ROUTING SUCH THAT
THEY DO NOT INTERFERE WITH NOR RECEIVE
DAMAGE FROM THE NORMAL OPERATIONS OF THE
AREA.
28. THE CONTRACTOR SHALL DIVERT ALL DRAINS AND
INSPECTORS TEST CONNECTION DISCHARGE AWAY
FROM FINISHED SURFACES AND PIPE TO APPROVED
DRAIN LOCATIONS. ROUTE DISCHARGE TO NEARBY
GREENSPACE OR STORM WATER DRAIN BY USE OF
BACKWASH HOSE.. THE CONTRACTOR WILL BE
BACKCHARGED FOR ANY REPAIR, REPLACEMENT,
OR CLEANING OF RUST STAINS ON
PAVEMENT,/CONCRETE DUE TO WATER DISCHARGE
FROM SPRINKLER SYSTEM DRAINS.
1. THE DESIGN SHOWN ON THESE CONTRACT
DOCUMENTS HAS BEEN PREPARED FOR APPROVAL
BY THE AUTHORITY HAVING JURISDICTION AND TO
PROVIDE GUIDANCE FOR BIDDING. SUBMIT
COMPLETE FIRE SPRINKLER SHOP DRAWINGS AS
REQUIRED BY CONTRACT DOCUMENTS TO THE
OWNERS DESIGNATED REVIEWERS. BASE
SPRINKLER DESIGN UPON THESE DRAWINGS AND
AS REQUIRED BY THE SPECIFICATIONS. SHOP
DRAWINGS MUST INCLUDE ELEVATIONS, HANGER
LOCATIONS, PIPE LENGTHS, DIMENSIONS,
FABRICATIONS METHODS, MATERIAL DATA, AND
ADDITIONAL INFORMATION NECESSARY TO CLARIFY
THE INTENT OF INSTALLATION. CONTRACTOR SHALL
PROVIDE PIPE SIZE, SPRINKLER SPACING, AND
SYSTEM CONFIGURATION AS SHOWN. ALTERNATE
MATERIALS MUST BE SENT TO THE FIRE
PROTECTION ENGINEER OF RECORD OR VIA THE RFI
PROCESS AND MUST BE APPROVED IN RECORD
DOCUMENTS PRIOR TO BID.
2. COORDINATE LOCATIONS OF FIRE PROTECTION
COMPONENTS, INCLUDING PIPING, ALARMS, DRAINS,
TEST POINTS, ETC. WITH ARCHITECTURAL,
STRUCTURAL, MECHANICAL, AND ELECTRICAL
COMPONENTS. OBSTRUCTION TO SPRINKLER
DISCHARGE MUST BE CONSIDERED DURING SHOP
DRAWING PRODUCTION AND INSTALLATION;
ADDITIONAL SPRINKLERS MAY BE REQUIRED AT NO
ADDITIONAL COST TO OWNER. REFER TO
SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.
3. CONTRACTOR MUST VISIT THE BUILDING SITE TO
DETERMINE THE FULL EXTENT OF THE EXISTING
FIRE PROTECTION WORK AND EXISTING
CONDITIONS, BECOME TOTALLY FAMILIAR WITH THE
DISCONNECTIONS, REMOVALS, RELOCATIONS
AND/OR RECONNECTIONS OF EXISTING FIRE
PROTECTION EQUIPMENT REQUIRED, AND
CONDITIONS IN THE PROPOSAL FOR THIS PROJECT.
NO EXTRA COMPENSATION WILL BE PAID FOR LACK
OF SUCH DETERMINATION, FAMILIARIZATION,
AND/OR ALLOWANCE.
4. SUBMIT A REQUEST FOR INFORMATION FOR
QUESTIONS REGARDING THE FIRE PROTECTION
DOCUMENTS PER RFI PROCESS LOCATED IN THE
FIRE PROTECTION SPECIFICATIONS.
5. NEUTRALIZATION WALLS, IF PROVIDED, ARE SHOWN
ON THE ARCHITECTURAL DRAWINGS. REFER TO
MECHANICAL DRAWINGS FOR NEUTRALIZATION
WALL PENETRATION DETAIL.
6. PENETRATIONS OF "RATED ASSEMBLIES" SHALL BE
FIRE STOPPED WITH AN APPROVED MATERIAL PER
METHODS REQUIRED BY PROJECT SPECIFICATIONS
AND THE AUTHORITY HAVING JURISDICTION.
GENERAL NOTES CONT.GENERAL NOTES
1. CONTRACTOR MUST VISIT THE BUILDING SITE TO
DETERMINE THE FULL EXTENT OF THE EXISTING FIRE
PROTECTION WORK AND EXISTING CONDITIONS,
BECOME TOTALLY FAMILIAR WITH THE
DISCONNECTIONS, REMOVALS, RELOCATIONS
AND/OR RECONNECTIONS OF EXISTING FIRE
PROTECTION EQUIPMENT REQUIRED, AND
CONDITIONS IN THE PROPOSAL FOR THIS PROJECT.
NO EXTRA COMPENSATION WILL BE PAID FOR LACK
OF SUCH DETERMINATION, FAMILIARIZATION, AND/OR
ALLOWANCE.
2. UNLESS INDICATED OTHERWISE, DISCONNECT AND
REMOVE ALL EXISTING FIRE PROTECTION
COMPONENTS NOT INTENDED TO BE REUSED.
3. DISCONNECT, RELOCATE, AND RECONNECT
EXISTING FIRE PROTECTION SYSTEMS AND
EQUIPMENT WHERE REQUIRED.
4. NOTE CAREFULLY THAT THE FIRE PROTECTION
DRAWINGS ARE INTENDED TO INDICATE, ONLY
DIAGRAMMATICALLY, THE EXTENT AND THE GENERAL
CHARACTER AND LOCATIONS OF THE WORK
INCLUDED. PROVIDE ALL WORK OBVIOUSLY
INTENDED, BUT HAVING MINOR DETAILS OMITTED OR
NOT SHOWN. COMPLETE AS REQUIRED TO
PERFORM THE FUNCTIONS INTENDED. FOLLOW THE
CONTRACT DOCUMENTS FOR BUILDING DETAILS
AND FIT THE WORK OF THE FIRE PROTECTION
DRAWINGS AND SPECIFICATIONS THERETO.
5. REMOVE ALL DEMOLITION MATERIALS AND DEBRIS
TO AN APPROVED DUMPING SITE AND CLEAN ALL
FIRE PROTECTION WORK PRIOR THE PROJECT
COMPLETION.
6. PERFORM ALL WORK ACCORDING TO THE PROJECT
PHASING SCHEDULE INFORMATION FOR THIS
PROJECT. PROVIDE ALL NECESSARY FIRE
PROTECTION WORK, TEMPORARY AND/OR
OTHERWISE, AND USE WHATEVER MEANS
NECESSARY, TO CONFORM TO THE REQUIRED
CONSTRUCTION PHASING OF THE PROJECT.
7. CONTRACTOR IS RESPONSIBLE FOR REPAIRING OR
REPLACING ITEMS DAMAGED DURING DEMOLITION
AND CONSTRUCTION.
8. CONTRACTOR SHALL PATCH ALL HOLES TO MATCH
ADJACENT SURFACES LEFT UNUSED AFTER EXISTING
SPRINKLER PIPING OR EQUIPMENT IS REMOVED AND
VACATED FROM THESE HOLES.
9. CONTRACTOR IS RESPONSIBLE FOR PROVIDING AND
MAINTAINING FIRE DEPARTMENT ACCESS ROADS
THROUGHOUT THE PROJECT.
10. SPRINKLER SYSTEMS NOT ASSOCIATED WITH THE
DEMOLITION SHALL BE LEFT IN SERVICE.
11. THE CONTRACTOR SHALL PROPERLY NOTIFY THE
LANDLORD. THE LESSOR AND THE ADJACENT
TENANTS A MINIMUM OF 48 HOURS IN ADVANCE
BEFORE PROCEEDING WITH THIS WORK. ALL WORK
SHALL BE SCHEDULED IN ADVANCE.
FIRE SPRINKLER PIPING AND
DEMOLITION NOTES
NFPA STANDARDS EDITION
NFPA 13 2018
REFER TO SHEET T1 FOR APPLICABLE CODES
APPLICABLE CODES
SHEET NUMBER SHEET NAME
FP1 OVERALL FIRE
SPRINKLER PLAN
FP2 ENLARGED FIRE
SPRINKLER PLAN
SHEET INDEX
1. THE CONTRACTOR IS RESPONSIBLE FOR THE
COORDINATION, VERIFICATION AND PROVISION OF A
FIRE WATCH SUBJECT TO THE REQUIREMENTS OF
THE LOCAL JURISDICTION. ALL FIRE WATCH COSTS
INCURRED AS A RESULT OF THIS PROJECT SHALL BE
INCLUDED IN THE PROJECT BID AS A SEPARATE LINE
ITEM. COORDINATION AND VERIFICATION AS TO
WHEN A FIRE WATCH MAY BE NEEDED SHALL BE THE
RESPONSIBILITY OF THE GENERAL CONTRACTOR.
2. THE GENERAL CONTRACTOR SHALL REQUEST THE
STORE MANAGER TO NOTIFY ALARM CENTRAL OF
THE SYSTEM(S) BEING SHUT OFF FOR WORK AND
THE DURATION OF THE SHUT OFF.
3. THE GENERAL CONTRACTOR SHALL CALL DIRECT TO
THE FIRE DEPARTMENT AND ADVISE THAT THE FIRE
ALARM SYSTEM IS IN TEST.
4. AT THE END OF EACH NIGHTS WORK, THE GENERAL
CONTRACTOR SHALL CALL DIRECT TO THE FIRE
DEPARTMENT AND ALARM CENTRAL TO ADVISE
WORK IS COMPLETE.
5. (FIRST FIRE WATCH OPTION) A FIRE WATCH SHALL BE
REQUIRED WHEN ANY FIRE PROTECTION SYSTEM IS
IMPAIRED OR OTHERWISE DOWN FOR ALTERATION.
THE APPROVED FIRE WATCH SHALL BE CONDUCTED
BY A DEDICATED, TRAINED WALMART EMPLOYEE
WHOSE SOLE RESPONSIBILITY WILL BE TO PERFORM
HOURLY PATROLS OF THE PREMISES AND KEEP
WATCH FOR FIRES AND WILL NEED TO DOCUMENT
THEIR WALK AND REPORT BACK TO THE GENERAL
CONTRACTOR AND WALMART MANAGEMENT. THIS
PERSON SHALL BE PROVIDED WITH AT LEAST ONE
APPROVED MEANS FOR NOTIFICATION TO THE FIRE
DEPARTMENT.
6. (SECOND FIRE WATCH OPTION) A FIRE WATCH SHALL
BE REQUIRED WHEN ANY FIRE PROTECTION SYSTEM
IS IMPAIRED OR OTHERWISE DOWN FOR
ALTERATION. THE FIRE SPRINKLER CONTRACTOR
SHALL HIRE AN APPROVED OFF-DUTY FIRE FIGHTER
TO PERFORM THE REQUIRED FIRE WATCH. FIRE
WATCH PERSONNEL SHALL BE PROVIDED WITH AT
LEAST ON APPROVED MEANS FOR NOTIFICATION OF
THE FIRE DEPARTMENT AND THEIR SOLE DUTY SHALL
BE TO PERFORM CONSTANT PATROLS AND WATCH
FOR THE OCCURRENCE OF FIRE. FOR HOT WORK
OPERATIONS, A FIRE WATCH SHALL BE POSTED FOR
THE DURATION OF THE WORK AND 30 MINUTES
THEREAFTER.
7. ONLY (1) ONE SYSTEM IS PERMITTED TO BE SHUT
DOWN AT ONE TIME.
8. ANY FIRE DEPARTMENT FEES FOR FAILURE TO
FOLLOW PROCEDURES WILL BE AT THE GENERAL
CONTRACTORS EXPENSE.
9. REQUIRED MEANS OF EGRESS SHALL BE MAINTAINED
AT ALL TIMES DURING CONSTRUCTION, DEMOLITION,
REMODELING OR ALTERATIONS AND ADDITIONS TO
THE WALMART. ALL EXITS SHALL NOT BE BLOCKED,
REDUCED OR OTHERWISE MADE INOPERABLE WHICH
ALSO INCLUDES THE EXIT ACCESS, THE EXIT AND
EXIT DISCHARGE TO THE PUBLIC WAY. TEMPORARY
MEANS OF EGRESS ARE ALLOWED.
10. ALL SYSTEMS TO BE LEFT IN SERVICE PRIOR TO THE
END OF EACH WORKDAY.
SYSTEM IMPAIRMENT
REQUIREMENTS
THE CONTRACTOR IS RESPONSIBLE FOR PRODUCING
AND PROVIDING THE AHJ AND THE ENGINEER OF
RECORD HYDRAULIC CALCULATIONS FOR THIS
PROJECT. THE ENGINEER OF RECORD WILL NOT BE
RESPONSIBLE FOR PROVIDING THE HYDRAULIC
CALCULATIONS.
NEW HYDRAULIC PLACARDS SHALL BE PROVIDED AND
PERMANENTLY ATTACHED ON EACH APPLICABLE
RISER IN ACCORDANCE WITH NFPA 13.
HYDRAULIC CALCULATION
SPRINKLER SYMBOL LEGEND
WHERE SPRINKLERS ARE CALLED OUT TO "MATCH EXISTING," THE CONTRACTOR
SHALL PROVIDE SPRINKLERS MANUFACTURED BY TYCO, WHICH ARE EQUIVALENT TO
THE EXISTING TO REMAIN SPRINKLERS. SUBSTITUTIONS WILL NOT BE PERMITTED.
CONCEAL
DRY PEND 200WHITETY3555TYCO DS-C1"
SYMBOL SIZE MFR S.I.N.MAKE FINISH K-FACTORSTYLETEMP
TY3251TYCO TY-B1/2"WHITE 155 5.6
EXISTING
PENDENTVARIESVARIES VARIES VARIES VARIES
VARIES VARIESDEMO ------
------
----- -----
EXISTING
PENDENT
VARIES VARIES
RECESSED
STYLE 10
TY9226TYCO ESFR1"BRASS 212PENDENT
EXISTING
UPRIGHTVARIESVARIES VARIES VARIES VARIESBRASS VARIES
VARIES VARIESDEMO ------ ----------- -----
EXISTING
UPRIGHT
PENDENTMATCH
EXISTING TYCO MATCH
EXISTING
MATCH
EXISTING
MATCH
EXISTING
MATCH
EXISTING
MATCH
EXISTING
TY5332TYCO SW-203/4"WHITE 200
ECOH
SIDEWALL
TY3355TYCODS-11"WHITE 286
HSW 401
ESC
TY3351TYCO RFII1/2"WHITE 200
CONCEAL
PENDENT
TY3251TYCO TY-B1/2"WHITE 286
RECESSED
STYLE 10
PENDENT
TY5255TYCO DS-21"WHITE 286
401 ESC
DRY PEND
VARIES VARIESDEMO ----------- -----
EXISTING
SIDEWALL
------
UPRIGHTMATCH
EXISTING TYCO MATCH
EXISTING
MATCH
EXISTING
MATCH
EXISTING
MATCH
EXISTING
MATCH
EXISTING
TY52513/4"TYCO ELO-231B BRASS 286
OWNER FURNISHED SPRINKLERS AND
ACCESSORIES
WHERE SPRINKLERS ARE CALLED OUT TO "MATCH EXISTING" THE CONTRACTOR
SHALL PROVIDE SPRINKLERS MANUFACTURED BY TYCO, WHICH ARE EQUIVLIENT
TO THE EXISTING TO REMAIN SPRINKLERS.SUBSTITUTIONS WILL NOT BE
PERMITTED. REFERENCE SPECIFICATIONS APPENDIX B FOR ADDITIONAL
INFORMATION.
WHERE SPRINKLERS ARE INSTALLED BELOW OBSTRUCTIONS (REFRIGERATION
PIPING, RTUs, CABLE TRAYS, ETC.) THESE SPRINKLERS SHALL BE REPLACED WITH
SPRINKLERS MATCHING THE NEW SPRINKLERS BEING INSTALLED AT THE ROOF
DECK LEVEL.
THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY DAMAGE TO OWNER
FURNISHED SPRINKLERS DURING INSTALLATION. TO REPLACE DAMAGED
SPRINKLERS CONTACT HAINES, JONES, CADBURY 1-800-459-7099.
1" TYCO TY3555WHITE
CONCEEALED
DRY PENDANT2005.6
SYMBOL SIZE MFR MAKE S.I.N.FINISH STYLETEMPK-FACTOR
4
QTY
DS-C
EXISTING
HSWVARIESVARIES VARIES VARIES VARIESBRASS VARIES
5.6
5.6
5.6
5.6
11.2
11.2
11.2
25.2
DRY PEND 200WHITETY5255TYCO DS-21"
11.2
SYMBOL LEGEND
SPRINKLER RISER
TRAPEZE HANGER
HANGER
RISER NIPPLE/DROP NIPPLE
HYDRAULIC REFERENCE NODE POINT
SYMBOL DESCRIPTION
CAP
NEW SPRINKLER PIPE
EXISTING SPRINKLER PIPE
DEMOLISHED SPRINKLER PIPE
XXX
INSPECTOR'S TEST/AUXILIARY DRAIN
NEW CONNECTION
FIRE DEPARTMENT CONNECTION
PROVIDE ADDITIONAL SPRINKLERS AS REQUIRED PER
NFPA 13 IN EXISTING SPRINKLER CABINET FOR ANY
NEW SPRINKLERS INSTALLED.
PLUG
1/32" = 1'-0" 1 OVERALL FIRE PROTECTION PLAN
ISSUE BLOCK
NOTE
E
EE
EE
E
E
E
E
EE
1
1
2
2
3
3
G G
H H
J J
(E)3"
(E
)
1
-1/
4
"
10'-0"
2'
-3"
(E
)
1
"
11
'
-6"
(E
)
1
-1/
4
"
2'
-3"
(E
)
1
"
11
'
-6"
TYP13.912
1
1
2
2
3
3
G G
H H
J J
(E)3"
(E
)
1
-1/
4
"
10'-0"
2'
-3"
(E
)
1
"
11
'
-6"
(E
)
1
-1/
4
"
2'
-3"
(E
)
1
"
11
'
-6"
TYP13.973
3
FP2
SUPPLY FROM WET PIPE
SPRINKLER SYSTEM
TEE WITH PLUG
1" DRY
SPRINKLER
DROP
DOW CORNING 739
PLASTIC ADHESIVE
FREEZER/COOLER
CEILING
OPEN-CELL
POLYETHYLENE
FOAM BACKER ROD
SPRINKLER CUP
1" DRY
SPRINKLER
DROP
SUPPLY FROM WET PIPE
SPRINKLER SYSTEM
TEE WITH PLUG
SPRINKLER CUP
FREEZER/COOLER
CEILING
2 NYLON STRAP TIES
(INSTALL OPPOSITE DIRECTIONS)
TYCO RUBBER SEAL
BOOT MODEL DSB-2
SEALANT PER BOOT
MANUFACTURER
2 3/4"
OPTION A OPTION B
NOTE: CONTRACTOR TO SEAL DRY PENDENT SPRINKLERS AT FREEZER/COOLER USING ONE OF THE OPTIONS ABOVE. NO OTHER SEALANTS ARE PERMITTED
MI
N
6
"
TY
P
MI
N
C
A
S
I
N
G
L
E
N
G
T
H
1
2
"
TY
P
MI
N
6
"
TY
P
MI
N
C
A
S
I
N
G
L
E
N
G
T
H
1
2
"
TY
P
1. CORE DRILL 2 1/2" DIAMETER HOLE IN THE FREEZER/COOLER INSULATED
CEILING PANEL. LOCATE HOLE AND REQUIRED SPRINKLER PROTECTION
IN ACCORDANCE WITH NFPA 13 OBSTRUCTION CRITERIA (SSP TYPE
SPRINKLERS). MAINTAIN 6" CLEARANCE FROM COOLER SEAMS.
2. INSTALL DRY PENDENT SPRINKLER PER MANUFACTURER'S INSTALLATION
REQUIREMENTS.
3. COMPLETELY FILL ANNULAR CEILING OPENING BETWEEN THE ESCUTCHEON
AND TOP OF CEILING PANEL WITH OPEN-CELL POLYETHYLENE FOAM
BACKER ROD. EXPANDED FOAM IS NOT PERMITTED.
4. INJECT DOW CORNING 739 PLASTIC ADHESIVE SEALANT INTO AND AROUND
THE TOP OF THE FREEZER/COOLER CEILING CORE OPENING IN
ACCORDANCE WITH SEALANT MANUFACTURER'S INSTRUCTIONS.
1. CORE DRILL 2 1/2" DIAMETER HOLE IN THE FREEZER/COOLER INSULATED
CEILING PANEL. LOCATE HOLE AND REQUIRED SPRINKLER PROTECTION
IN ACCORDANCE WITH NFPA 13 OBSTRUCTION CRITERIA (SSP TYPE
SPRINKLERS). MAINTAIN 6" CLEARANCE FROM COOLER SEAMS
2. INSTALL TYCO DRY PENDENT SPRINKLER PER MANUFACTURER'S
INSTALLATION REQUIREMENTS. INSERT BOOT PRIOR TO MAKE-UP WITH
PIPING.
3. COMPLETELY SEAL INTERFACE BETWEEN BOOT FLANGE AND TOP OF
FREEZER/COOLER PANEL WITH ADHESIVE PROVIDED WITH BOOT IN
ACCORDANCE WITH MANUFACTURER'S INSTRUCTIONS.
4. APPLY STRAP TIES ON BOOT AROUND DRY SPRINKLER BARREL PER
MANUFACTURER'S INSTRUCTIONS.
OPTION "A" INSTALLATION PROCEDURE OPTION "B" INSTALLATION PROCEDURE
TYCO MODEL TY5255
WITH FLUSH ESCUTCHEON
(NO SUBSTITUTIONS) 2 3/4"
TYCO MODEL TY5255
WITH FLUSH ESCUTCHEON
(NO SUBSTITUTIONS)
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.FP2
ENLARGED
FIRE
SPRINKLER
PLAN
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
KEYNOTES
13.912 REMOVE EXISTING DRY PENDENT SPRINKLERS
FROM COOLERS/FREEZERS. PLUG ALL OUTLETS
NOT INTENDED FOR REUSE. SEAL ALL
COOLER/FREEZER PANEL PENETRATIONS IN
ACCORDANCE WITH X-FPX.
13.973 PROVIDE NEW DRY CONCEALED PENDENT
SPRINKLERS AS SHOWN AND CONNECT TO
EXISTING OVERHEAD SYSTEM. REF X-FPX.
COORDINATE WITH LOCATION OF LIGHTS AND
EVAPORATOR UNITS. NOT MORE THAN ONE
SPRINKLER SHALL BE SUPPLIED BY A 1" PIPE OR
CONNECTION. EXISTING CEILING LEVEL
SPRINKLER PROTECTION SHALL REMAIN.
ADDITIONAL SPRINKLERS MAY BE REQUIRED AT
NO ADDITIONAL COST TO OWNER.
1/8" = 1'-0" 1 FIRE PROTECTION DEMOLITION PLAN
1/8" = 1'-0" 2 FIRE PROTECTION PLAN
NTS3WALK-IN DRY PENDENT
ISSUE BLOCK
NOTE
XIO-8U-1 SCHEDULE
U1/A1 SENSOR C-1 LEAK (N,DI, FI)
U1/A2 SENSOR C-1 LEAK (N,AI, FI)
U1/A3 SENSOR SPARE
U1/A4 SENSOR SPARE
U1/A5 SENSOR SPARE
U1/A6 SENSOR SPARE
U1/A7 SENSOR SPARE
U1/A8 SENSOR SPARE
1
1
2
2
3
3
4
4
C C
D D
E E
F F
G G
H H
J J
ICE CREAM
FREEZER
GROCERY
FREEZER
DAIRY
COOLER
MEAT
COOLER
SEAFOOD
FREEZER
SALES
EDC4
EXISTING ES1, LDP, AND CIMS MOUNTED
ON EXISTING BAS BACKBOARD IN EDC4.
LABEL ALL NEW AND EXISTING LEAK
DETECTION ZONES. LABEL ALL SPARE
ZONES AS SPARE.
MOUNT OWNER FURNISHED XIO ON BAS
BACKBAORD. REFER TO XIO SCHEDULES
AND BAS ONE-LINE DIAGRAM.
WIRE HORN/STROBE TO
ICE CREAM FREEZER.
C-1
MOUNT OWNER FURNISHED SPORLAN
GATEWAY ROUTER ON BAS BACKBAORD.
REFER TO BAS ONE-LINE DIAGRAM.
EXISTING CIMS MOUNTED ON EXISTING
BAS BACKBOARD ABOVE MEAT COOLER.
5
BASR1
3
BASR1
6
BASR1
1
BASR2
2
BASR3
1
BASR3
3
BASR3
2
BASR1
INSTALL BOTTOM OF CONTROLLER ENCLOSURE
84" AFF MINIMUM ON COOLER/FREEZER. REF
PLANS FOR QUANTITY AND LOCATION.
COORDINATE PANEL LOCATION WITH DOOR
OPENING, PROTECTION, AND RACKING. DO NOT
MOUNT ENCLOSURES BELOW REFRIGERATION
EQUIPMENT OR PLUMBING LINES. VERIFY WITH
WALMART MECHANICAL CONSTRUCTION
MANAGER THAT ENCLOSURES ARE LOCATED IN
AN ACCESSIBLE SPACE.
INSTALL TEMPERATURE SENSOR
CABLE AND VALVE CONTROL WIRING
AND CABLING IN CONDUIT FROM TOP
OF COOLER/FREEZER TO WALK-IN
CONTROLLER ENCLOSURE. FOR
CABLE RUNS >25', REFER TO BAS
VENDOR INSTRUCTIONS. TYP.
CONTROLLER ENCLOSURE OWNER
FURNISHED, INSTALLED BY CONTRACTOR.
ENCLOSURES CONTAIN ONE CONTROLLER
AND REMOTE DISPLAY.
PROVIDE A CUSTOM, DIGITALLY PRINTED
AND HIGH-DURABILITY LAMINATED LABEL
MOUNTED ON CONTROLLER ENCLOSURES
INDICATING THE REFRIGERATION CIRCUIT(S)
SERVED BY THE CONTROLLERS WITHIN.
LETTERING SHALL BE WHITE, MINIMUM OF
3/4" HIGH, ON A BLACK BACKGROUND.
11.30.17
SIDE VIEW
DEFROST TERMINATION SENSOR
MOUNTED IN SENSOR WELL ON END
PLATE, 1 PER ELECTRIC DEFROST COIL.
CONNECT TO APPLICABLE
EVAPORATOR MODULE.
TO SINGLE COIL PIPING OR
MULTIPLE COIL PARALLEL PIPING
FOR MULTIPLE COIL REVERSE
RETURN PIPING
EVAP
FAN/
COIL
UNIT
SUPPLY
RETURN
12.05.17
PROVIDE CEILING MOUNTED WP JUNCTION BOX WITH
THREADED HUBS AND GASKETED COVERPLATE.
SEAL TOP OF JUNCTION BOX TO COOLER/FREEER
CEILING WITH SILICONE SEALANT, TYP.
COOLER/FREEZER BOX CEILING
PROVIDE CONDULET AT CEILING PENETRATION
FILLED WITH SILICONE SEALANT, TYP
1" EMT CONDUIT PENETRATION
SEALED WITH SILICONE
SEALANT, TYP
PROVIDE EMT CONDUIT AND WIRING TO
NEXT COIL CONTROL JUNCTION BOXES ON
SAME SYSTEM WHEN MULTIPLE COILS ARE IN
SAME COOLER/FREEZER BOX. CONDUIT AND
WIRING SAME SIZE AND QUANTITY AS WIRING
TO PANEL. COIL CONTROL CONDUIT SHALL
BE 1".
TYPICAL COIL
NOTE: DO NOT LOCATE WP JUNCTION BOX DIRECTLY IN FRONT OF DISCHARGE FAN, OFFSET TO SIDE.
PROVIDE 1" LIQUID-TIGHT FLEXIBLE METAL
CONDUIT TO KNOCKOUT ON UNIT. FINAL
CONNECTION TO COIL BY RC, TYP.
PROVIDE 1" EMT CONDUIT TO
WALK-IN COIL CONTROLLER
FOR COIL CONTROL WIRING
NOTE: THE CONDUIT AND WIRING IN THIS DETAIL IS FOR LOW VOLTAGE AND CONTROL VOLTAGE WIRING ONLY.
EVAPORATOR COIL POWER LINE VOLTAGE WIRING SHALL BE INSTALLED IN SEPARATE CONDUIT. REFER TO ELECTRICAL.
SECURE SENSING ELEMENT AND CABLE WITH (2)
NYLON MOUNTING BRACKETS (PANDUIT #PP2S-S10-X)
AT RIGHT ANGLES TO EACH OTHER. PLACE BULB
APPROX. 3" OFF CENTER IN MAXIMUM RETURN AIR
STREAM. MOUNT BRACKET WITH EXISTING FAN
SHROUD MOUNTING SCREW. DO NOT DRILL HOLE IN
DRAIN PAN TO MOUNT BRACKETS. CABLE TO EXTEND
TO COIL ON HINGED SIDE OF DRAIN PAN.
CONDUIT AND SENSOR
CABLE TO BUILDING
AUTOMATION SYSTEM.
(TYP)
CEILING
OF BOX
1/4" PENETRATION THRU
ROOF FOR SENSOR LEADS.
SEAL INSIDE AND OUT WITH
SILICONE OR EXPANDING
FOAM AND SEALANT.
CEILING OF BOX
6"
DUAL COIL EVAPORATOR
RETURN AIR TEMPERATURE
SENSOR INSTALLATION
INSTALL SENSOR AT COIL MIDPOINT,
CENTERED ON COIL LENGTH.
CONDULET AT CEILING
PENETRATION FILLED WITH
SEALANT
REFER TO MANUFACTURER'S INSTALLATION INSTRUCTIONS FOR ALL FIELD INSTALLED ITEMS. BAS CONTRACTOR
SHALL CARRY OUT ALL FURNISHING, INSTALLATION, AND WIRE TERMINATIONS UNLESS NOTED OTHERWISE.
S
L
OWNER-
FURNISHED
RETURN AIR
TEMP SENSOR INSTALL AND TERMINATE WIRING
BETWEEN FACTORY-INSTALLED
EEV AND BAS CONTROLLER.
INSTALL WIRING FROM
EEPR AND LLSV TO BAS
CONTROLLER.
REFER TO WALK-IN CONTROLLER
WIRING DETAIL FOR TERMINATIONS
PROVIDE 1/4" SCH 40
PLASTIC PLUMBER'S
SUPPLY TUBE WITH
CAPPED END. DRILL
HOLE TO RUN SENSOR
LEAD THROUGH.
ROUTE REFRIGERATION SENSOR AND EEV WIRING TO
KNOCKOUT. REFERENCE EVAPORATOR COIL SENSOR
WIRING PROVISIONS DETAIL FOR CONTINUATION.
PROVIDE JUNCTION BOX
WITH FLEXIBLE CONDUIT OR
SEALTITE AT CEILING FOR
EEPR AND LLSV.
INSTALL SENSOR AND WIRING BETWEEN
SUCTION TEMPERATURE SENSOR AND KE2
CONTROLLER.
INSTALL AND TERMINATE WIRING
BETWEEN REFRIGERATION CONTRACTOR-
INSTALLED PRESSURE TRANSDUCER AND
KE2 CONTROLLER
E
RL
RD
RP
N
FI
FA
M
DI
AI
EXISTING BAS DEVICE, SENSOR, OR WIRE FOR REUSE.
EXISTING BAS DEVICE OR SENSOR TO RELOCATE AND
RECONNECT. INSTALL NEW CABLE FOR RELOCATED
DEVICE OR SENSOR AS NECESSARY.
REDESIGNATED BAS DEVICE OR SENSOR.
REPLACED BAS DEVICE OR SENSOR.
NEW BAS DEVICE OR SENSOR.
NEW FIELD INSTALLED BAS DEVICE, SENSOR, OR WIRE.
NEW FACTORY INSTALLED BAS DEVICE, SENSOR, OR WIRE.
BAS DEVICE OR SENSOR USED FOR MONITORING ONLY.
DIGITAL INPUT.
ANALOG INPUT.
BAS ONE-LINE AND SCHEDULE NOTES
REFRIGERATION BAS ONE-LINE REFLECTS THE
INTENDED DESIGN BASED ON NEW CASES AND
EXISTING SYSTEM NUMBERS. VERIFY ALL
EXISTING CONDITION AND LOCATION OF ALL BAS
EQUIPMENT PRIOR TO ROUGH-IN.
WIRE LEGEND
WIR-1010 (TAN CABLE 18-2, 20-2 TWISTED PAIR)
WIR-2020 (BLUE CABLE 22-2 TWISTED PAIR)
NOTE:
1.) NOT ALL CONNECTIONS SHOWN ON THIS SCHEDULE ARE PRESENT
AT EACH REFRIGERATION GATEWAY. REFER TO ONE-LINE DIAGRAM
FOR CONNECTIONS SPECIFIC TO EACH REFRIGERATION GATEWAY.
UNLESS NOTED OTHERWISE, DEVICES AND
CABLING SHOWN IN THIS ONE-LINE DIAGRAM
ARE VENDOR FURNISHED; REFRIGERATION
BUILDING AUTOMATION CONTRACTOR TO
INSTALL CABLING AND DEVICES AND MAKE
FINAL TERMINATIONS. REFER TO PLANS FOR
DEVICE LOCATIONS.
COORDINATE WITH LEGACY BAS VENDOR
(NOVAR) FOR THE REPROGRAMMING OF THEIR
RACK CONTROLLER WITH THE REMOVAL OF
CIRCUITS FROM THEIR CONTROL. VERIFY
DEFROST SCHEDULES ARE COORDINATED
BETWEEN THE EXISTING RACK CONTROLLER
AND THE NEW CASE CONTROLS.
ES-1
COMMUNICATION PORT
LCD (IF APPLICABLE) / BACNET LOOP
SPECTRUM (NOVARnet) / BACNET LOOP
COM1
COM2
COM MODULE 1
COMMUNICATION PORT
SPECTRUM (NOVARnet) / BACNET LOOP
SPECTRUM (NOVARnet) / BACNET LOOP
COM3
COM4
COMMUNICATION PORT
SPECTRUM (NOVARnet) / BACNET LOOP
COM5
COM6
SPECTRUM (NOVARnet) / BACNET LOOP
COM MODULE 2
NOTES:
1.ALL CABLE WIR-2020 UNLESS NOTED OTHERWISE.
2.ALL WIR-1010 AND WIR-2020 CABLE FURNISHED BY
OWNER FOR INSTALLATION BY CONTRACTOR.
3.ALL OTHER CABLE FURNISHED AND INSTALLED BY
CONTRACTOR.
IF WIRING LENGTH BETWEEN DEVICES EXCEEDS
328', OBTAIN SPORLAN-APPROVED NETWORK
SWITCH TO INCREASE MAXIMUM WIRING
LENGTH TO 650'. INSTALL ONE ADDITIONAL
SWITCH FOR EACH SUBSEQUENT INCREMENT
OF 325' OF RUN BETWEEN DEVICES.
EXISTING 'ES-1'
REFRIGERATION GATEWAY
CAT5E
COM1 COM2 COM3 COM4
ES1 REMOTE
LCD SCREEN
REFER TO WALK-IN COIL
CONTROLLER WIRING DETAIL. TYP
EXISTING ES1 REMOTE LCD SCREEN.
BUILDING AUTOMATION CONTRACTOR
TO PROVIDE RS-485 BACNET CABLE TO
FIRST CASE/COIL CONTROLLER ON A
COMM LOOP ONLY. TYP.
OWNER-FURNISHED SPORLAN
GATEWAY ROUTER LOCATED ON BAS
BACKBOARD. TYP.
CAT5E ETHERNET CABLE OR GREATER
BETWEEN ROUTER AND S3C CONTROLLER.
TYP OF ALL CABLING BETWEEN SGR, SNS,
AND S3C. REFER TO MANUFACTURER
INSTRUCTIONS FOR SPECIFIC
REQUIREMENTS.
S3C (C-1)
COM5 COM6
EDC4
SGR
XIO-8U-1
BUILDING AUTOMATION CONTRACTOR TO
PROVIED RS-485 CABLE FROM BACKBOARD TO
XIO. TYP.
DIGITAL AND ANALOG SIGNAL CABLING FOR
EACH LEAK DETECTION ZONE ROUTED TO
LEAK DETECTION PANEL INSIDE STORE.
REFER TO PLANS FOR LEAK DETECTION
PANEL LOCATION AND LEAK DETECTION ZONE
DEVICES ONE-LINE DIAGRAM. REFER TO XIO
SCHEDULES. TYP.
XIO SCHEDULE(S)
SITE VERIFY OPEN COM AND UTILIZE. TYP.
EXISTING KE2 COM LOOP.
EXISTING SGR / S3C COM LOOP.
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.BASR1
BUILDING
AUTOMATION
SYSTEM
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
1/16" = 1'-0" 1 REFRIGERATION BUILDING AUTOMATION PLAN
OWNER FURNISHED REFRIGERATION CONTROLS EQUIPMENT
VENDOR VENDOR SAP # Type QTY NOTES
COPELAND COLD CHAIN LP 1000214394 Horn Strobe 3
COPELAND COLD CHAIN LP 1000214394 MRLDS 1
COPELAND COLD CHAIN LP 1000214394 Zone Alarm 1
HONEYWELL INTERNATIONAL INC 1000211094 1 XIO Enclosure 1
PARKER HANNIFIN 1000929314 #983629 Sporlan S3C enclosure 1
PARKER HANNIFIN 1000929314 Sporlan Gateway Router (SGR) 1
PROGASKET SOLUTIONS LLC 1000412309 LD_SENSOR_COVER 1
1. BAS CONTRACTOR SHALL CONTACT THE BAS
SUPPLIER(S) TO OBTAIN A CURRENT MODULE
CONFIGURATION PRINTOUT BEFORE TERMINATING
SENSOR LEADS AT INPUT MODULES. THE REQUEST
FOR THE CONFIGURATION PRINTOUT SHALL BE MADE
PRIOR TO THE INSTALLATION OF BAS CABLES. WIRING
TERMINATIONS SHALL BE LANDED ACCORDING TO
THE BAS SUPPLIER CONFIGURATION SHEETS.
2. BAS CONTRACTOR SHALL PROVIDE COMPLETED
REFRIGERATION SENSOR INPUT VERIFICATION
FORMS TO THE BAS SUPPLIER(S) AT THE BEGINNING
OF THE REFRIGERATION EQUIPMENT STARTUP. BAS
INSTALLER SHALL PROVIDE ASSISTANCE TO THE BAS
SUPPLIER(S) FOR SPOT CHECKING OF SENSORS FOR
ACCURACY.
3. ALL BAS CABLE ON THE SALES FLOOR SHALL BE
ROUTED IN CONDUIT AND CONCEALED FROM VIEW
AND ROUTED ALONGSIDE OTHER PIPING OR CONDUIT
AS MUCH AS POSSIBLE.
4. BAS CONTRACTOR SHALL BE PRESENT AND
AVAILABLE TO RESOLVE ISSUES AND PROVIDE
REFRIGERATION STARTUP ASSISTANCE UNTIL
RELEASED BY THE BAS SUPPLIER AND WALMART
MECHANICAL CONSTRUCTION MANAGER.
5. DURING THE REFRIGERATION STARTUP, BAS
CONTRACTOR SHALL COMPLETE ALL UNRESOLVED
REFRIGERATION WORK PRIOR TO WORKING ON
OTHER BAS INSTALLATION ITEMS.
6. WHEN THE BAS SUPPLIER IS NOT SCHEDULED TO
PERFORM THE ON SITE REFRIGERATION STARTUP,
THE BUILDING AUTOMATION CONTRACTOR IS
RESPONSIBLE FOR PERFORMING ALL CHECKS AND
TEST TO ENSURE A FULLY FUNCTIONAL
REFRIGERATION CONTROL SYSTEM. CONTACT THE
BAS SUPPLIER FOR THE BLANK TEST VERIFICATION
FORMS AND INSTRUCTIONS FOR COMPLETING. ALL
COMPLETED TEST VERIFICATION FORMS SHALL BE
RETURNED TO THE WALMART MECHANICAL
CONSTRUCTION MANAGER.
7. REFER TO ARCHITECTURAL DRAWINGS FOR PIPING
INSTALLATION AND SEALING REQUIREMENTS FOR
DEVICES SHOWN ON COOLER/FREEZER PANELS. DO
NOT INSTALL PIPING WITHIN COOLER/FREEZER
PANELS.
8. ROUTE ALL UTILITY SERVICE LINES (PIPES AND
CONDUIT) WITHIN STUD WALLS WHEREVER POSSIBLE.
ON COOLER/FREEZER PANELS IN FOOD PREP AREAS
WHERE UTILITIES MUST BE EXPOSED, CONTRACTOR
TO HAVE THE OPTION OF THE FOLLOWING:
A. SURFACE MOUNT UTILITIES WITH NON-
CORROSIVE ANCHORS; SEAL BOTH SIDES OF
PIPE/CONDUIT TO PANEL CONTINUOUSLY WITH
SEALANT.
B. INSTALL UTILITIES 1/2" OFF FACE OF PANEL TO
ALLOW FOR CLEANING; USE ONLY NON-
CORROSIVE MATERIALS FOR SPACERS AND
ANCHORS.
C. COVER UTILITIES WITH 20 GAUGE STAINLESS
STEEL BENT PLATES MOUNTED TO WALL WITH
NON-CORROSIVE ANCHORS; APPLY CONTINUOUS
SEALANT ALONG EDGES AND JOINTS.
9. REFERENCE ARCHITECTURAL DEMOLITION PLANS
FOR FULL EXTENT OF DEMOLITION WORK REQUIRED.
GENERAL REFRIGERATION
BAS NOTES
03.12.18
ALL DEMOLISHED NOVAR BAS EQUIPMENT SHALL BE
RETURNED TO WALMART MECHANICAL SERVICES
CONSTRUCTION MANAGER. EQUIPMENT TO BE
RETURNED INCLUDES: EXECUTIVE CONTROLLER(S),
IOM(S), CIM(S), CCM(S), ETC. PROVIDE
DOCUMENTATION FOR ALL EQUIPMENT REMOVED IN
ACCORDANCE WITH SPECIFICATIONS AND REQUIRED
CLOSE-OUT DOCUMENTS.
BAS EQUIPMENT SALVAGE
REQUIREMENTS
11.02.15
WHERE EXISTING REFRIGERATION CHASES ARE BEING
REMOVED, ANY DAMAGED OR IMPROPERLY SUPPORTED
BAS CONDUITS WITHIN CHASE SHALL BE REPAIRED OR
REPLACED AS REQUIRED. ANY EXISTING BAS CABLING
WITHIN CHASE NOT INSTALLED IN CONDUIT SHALL BE
RE-ROUTED THROUGH NEW CONDUIT. FINAL APPROVAL
BY WALMART CONSTRUCTION MANAGER. REFERENCE
ARCHITECTURAL DRAWINGS FOR REFRIGERATION
CHASES BEING REMOVED.
REFRIGERATION NETWORK GATEWAYE2E
BUILDING AUTOMATION SYSTEMBAS
TEMPERATURETEMP
VARIABLE FREQUENCY DRIVEVFD
BACKBOARD
NEW EQUIPMENT
EXISTING EQUIPMENT
FACTORY INSTALLED EQUIPMENT
EQUIPMENT TO BE DEMOLISHED
CASE INPUT MODULEM
REFRIGERATION CIRCUIT
PRESSURE TRANSDUCER
DUAL TEMP SWITCH
RELAY IN BOX
RELAY IN BOX & CONTACTOR PANEL
LEAK DETECTION PANEL
LEAK DETECTION SENSOR
AUDIO\VISUAL ALARM
ZONE ALARM SILENCE PANEL
REFRIGERATION CASE/CIRCUIT
CONTROLLER (SPORLAN)
LDP
L
ZA
X-#
DTS
RIB
S
C-##
S3C
CONTACTOR
RIB/C-##
REFRIG BAS SYMBOLS
12.21.18
P
TEMPERATURE SENSOR
24 HOURS PRIOR TO SHUTTING DOWN ANY
REFRIGERATION SYSTEMS, HVAC SYSTEMS OR BUILDING
AUTOMATION CONTROLS SYSTEMS, SEND EMAIL TO
NSRM@WALMART.COM. THE E-MAIL SHALL STATE WHAT,
WHY, AND WHEN IT IS BEING SHUT DOWN AND HOW LONG
IT IS ANTICIPATED TO BE SHUT DOWN. THEN SEND A
FOLLOW UP EMAIL TO NSRM@WALMART.COM AFTER THE
WORK IS COMPLETE AND THE SYSTEM IS BACK UP AND
RUNNING.
SPORLAN GATEWAY ROUTERSGR
SPORLAN NETWORK SWITCHSNS
REFRIGERATION CASE/CIRCUIT
CONTROLLER (OPUS)RCC
REFRIGERATION GATEWAYXCM.20R
40 AMP KE2 CONTROLLERKE2-40
XIO ENCLOSUREXIO
NTS4
WALK-IN COOLER/FREEZER COIL
CONTROLLER ENCLOSURE MOUNTING (SPORLAN/KE2)
NTS5ELECTRIC DEFROST TERMINATION SENSOR
NTS6EVAPORATOR COIL SENSOR WIRING PROVISIONS
NTS3WALK-IN EVAPORATOR CONTROL DEVICE LOCATION AND INSTALLATION
NTS2REFRIGERATION BAS ONE-LINE DIAGRAM (NOVAR/SPORLAN)
ISSUE BLOCK
NOTE
PR
E
S
S
U
R
E
T
R
A
N
S
D
U
C
E
R
CO
I
L
1
DE
F
R
O
S
T
T
E
R
M
I
N
A
T
I
O
N
RE
T
U
R
N
A
I
R
CO
I
L
O
U
T
L
E
T
(S
U
C
T
I
O
N
L
I
N
E
)
EE
V
1
WALK-IN CONTROLLER ENCLOSURE
POWER. REFRIGERATION CONTRACTOR
TO CONNECT TO 120V COIL FAN CIRCUIT
OR DEDICATED CONTROL POWER
CIRCUIT PROVIDED BY ELECTRICAL
CONTRACTOR REFER TO ELECTRICAL.
DAIRY COOLER OR SIMILAR WALK-INS:
REFRIGERATION CONTRACTOR TO
TERMINATE WIRING WHERE APPLICABLE.
REFER TO ELECTRICAL.
REFRIGERATION CONTRACTOR
TO TERMINATE DEFROST AND
FAN WIRING PROVIDED BY
ELECTRICAL CONTRACTOR
REFER TO ELECTRICAL.
FACTORY INSTALLED TERMINAL
BLOCK AT EVERY WALK-IN
CONTROLLER ENCLOSURE. TYP
PROVIDE 20' #22 AWG 2
CONDUCTOR WIRE. TYP
EEPR:ONE PER CIRCUIT BAS CONTRACTOR
TO INSTALL #18 AWG 4 (OR #14 AWG 4 FOR
RUNS OVER 250 FT) CONDUCTOR CABLE TO
EEPR VALVES. BAS CONTRACTOR TO
TERMINATE WIRING AT EEPR AND AT THE
CONTROLLER. WIRE FURNISHED BY
OWNER. REFER TO REFRIGERATION.
THIS DETAIL IS A SCHEMATIC REPRESENTATION AND MAY NOT REFLECT
ALL WALK-IN COIL CONTROLLER CONFIGURATIONS. REFERENCE
MANUFACTURER FOR FACTORY INSTALLED COMPONENT INFORMATION.
REFER TO MANUFACTURER'S INSTALLATION
INSTRUCTIONS FOR FACTORY WIRING
DIAGRAMS, FIELD WIRING TERMINATIONS,
AND RS485 BACNET WIRING DETAILS.
SENSORS AND TRANSDUCERS:
OWNER-FUNISHED WITH CONTROLLER
ENCLOSURE. BAS CONTRACTOR TO
INSTALL SENSORS AND TERMINATE
WIRING FROM THE CONTROLLER TO THE
SENSORS AND TRANSDUCER, TYP. REFER
TO MANUFACTURER'S INSTRUCTIONS.
EXTEND WIRING AS REQUIRED.
REFER TO REFRIGERATION FOR WALK-IN EVAPORATOR COIL
QUANTITY, LOCATION, AND DEFROST TYPE (ELECTRIC OR OFF-TIME).
CAT-5 ETHERNET CABLE TO NEXT
CONTROLLER ON COMM LOOP.
REFER TO ONE-LINE DIAGRAM.
CAT-5 ETHERNET CABLE
FROM PREVIOUS CONTROLLER
ON COMM LOOP. REFER TO
ONE-LINE DIAGRAM.
RS-485 COMM WIRING FROM
ES1 TO FIRST CASE/COIL
CONTROLLER ON COMM LOOP.
REFER TO ONE-LINE DIAGRAM.
LLSV:TERMINATE 120VAC LIQUID LINE
SOLENOID VALVE WIRING ((2)#12 W/(1) 12
GND)) AT WALK-IN COIL CONTROLLER.
REFER TO ELECTRICAL. LIQUID LINE
SOLENOID VALVE IS PROVIDED BY THE
REFRIGERAITON MANUFACTURER.
EE
P
R
LL
S
V
LLSV
EEPR SD
SPORLAN
S3C COIL
CONTROLLER
COMM
WIRING
STEPPER
VALVE
DRIVER
(COIL 2)
STEPPER
VALVE
DRIVER
(COIL 3)
BUILDING AUTOMATION SYSTEM
CONTRACTOR TO PROVIDE RS-485
COMM WIRING TO FIRST CASE/COIL
CONTROLLER ON COMM LOOP AND
CAT-5 ETHERNET CABLE BETWEEN
CONTROLLERS THEREAFTER.
(COIL 1)
STEPPER VALVE DRIVER QUANTITY DETERMINED
BY WALK-IN EVAPORATOR COIL QUANTITY. (1) OR
(2) EVAPORATORS EQUALS (1) VALVE DRIVER. (3)
EVAPORATORS EQUALS (2) VALVE DRIVERS.
FR
O
M
E
L
E
C
T
R
I
C
A
L
P
A
N
E
L
.
RE
F
E
R
T
O
E
L
E
C
T
R
I
C
A
L
.
TO
E
V
A
P
O
R
A
T
O
R
C
O
I
L
.
RE
F
E
R
T
O
E
L
E
C
T
R
I
C
A
L
.
FR
O
M
E
L
E
C
T
R
I
C
A
L
P
A
N
E
L
.
RE
F
E
R
T
O
E
L
E
C
T
R
I
C
A
L
.
TO
E
V
A
P
O
R
A
T
O
R
C
O
I
L
.
RE
F
E
R
T
O
E
L
E
C
T
R
I
C
A
L
.
FA
N
S
DE
F
R
O
S
T
LI
G
H
T
S
FACTORY INSTALLED
COIL FAN RELAY.
NE
U
T
R
A
L
S
CO
I
L
2
CO
I
L
3
SD SD
DE
F
R
O
S
T
T
E
R
M
I
N
A
T
I
O
N
RE
T
U
R
N
A
I
R
EE
V
2
DE
F
R
O
S
T
T
E
R
M
I
N
A
T
I
O
N
RE
T
U
R
N
A
I
R
EE
V
3
S
PR
E
S
S
U
R
E
T
R
A
N
S
D
U
C
E
R
PR
E
S
S
U
R
E
T
R
A
N
S
D
U
C
E
R
SS
CO
I
L
O
U
T
L
E
T
(S
U
C
T
I
O
N
L
I
N
E
)
CO
I
L
O
U
T
L
E
T
(S
U
C
T
I
O
N
L
I
N
E
)
EEV EEV
EEV
EEV:VALVE FACTORY INSTALLED, ONE PER
COIL. BAS CONTRACTOR TO INSTALL #22
AWG 4 CONDUCTOR WIRE TO EEV VALVES.
BAS CONTRACTOR TO TERMINATE WIRING
AT EEV AND AT THE CONTROLLER. WIRE
FURNISHED BY OWNER. REFER TO
REFRIGERATION SCHEDULES FOR
QUANTITY AND CIRCUIT NAME.
P P P
PROVIDE 20' #18 AWG 4
CONDUCTOR WIRE. TYP
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.BASR2
BUILDING
AUTOMATION
SYSTEM
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
NTS1WALK-IN CONTROLLER WIRING (SPORLAN, EEV, WITH EEPR)
ISSUE BLOCK
NOTE
15A
Di
g
i
t
a
l
O
u
t
s
1
-
3
D
i
g
i
t
a
l
O
u
t
p
u
t
s
4
-
8
Di
g
i
t
a
l
O
u
t
1
1
-
1
5
Di
g
i
t
a
l
O
u
t
9
-
1
0
Te
r
m
Tx
Rx
gnd
TxRx
Tx
Rx
Te
r
m
g
n
d
V
n
r
CA
N
B
u
s
98
9
9
1
0
0
1
0
1
1
0
2
1
0
3
1
0
4
1
0
5
93
PW
R
ON
FU
S
E
5
X
2
0
TxRx
Te
r
m
gnd
CA
N
B
u
s
30
LAN
PW
R
ON
ALARM
11.02.15
HORN/STROBE LIGHT
+84" AFF
MRLDS LEAK DETECTOR
SENSOR MOUNTED
INSIDE WALK-IN
+18" AFF
SEAL ALL WALK-IN
PENETRATIONS WITH
SILICONE SEALANT. TYP
PROVIDE 1" EMT
STUB UP TO
STRUCTURE TOP OF FREEZER
OR COOLER
BAR JOIST
USE DOOR BOLLARD TO
PROTECT SENSOR. (DO
NOT BLOCK COVER
REMOVAL OR SENSOR
ACCESS)
SUPPORT ALL
CONDUITS AND
BOXES PER N.E.C.
ZONE ALARM
SILENCE PANEL.
+48" AFF
SIDE VIEWFRONT VIEW BACK VIEW
PROVIDE SENSOR
CONNECTION IN 1/2"
CONDUIT ALONG
EXTERIOR OF BOX.
MRLDS LEAK
SENSOR CABLE.
HORN/STROBE
ALARM PANEL
CABLE.
ZONE ALARM
SILENCE
PANEL
CABLE.
1/2" EMT WITH
COMP. FITTINGS &
MINERALLAC
STRAPS
1/2" SEALTITE DRIP LOOP
(MUST ENTER EXISTING K.O.
IN BOTTOM OF SENSOR)
REFRIGERANT SENSOR, HORN/
STROBE DEVICES, AND ZONE
ALARM SILENCE PANEL
FURNISHED BY LEAK DETECTION
VENDOR.
PROVIDE AN ENGRAVED PLASTIC
LABEL READING "REFRIGERANT LEAK"
ADJACENT TO EACH LEAK DETECTION
HORN STROBE. LETTERING SHALL BE
BLACK, MINIMUM OF 1/4" HIGH, ON A
WHITE BACKGROUND.
BELDEN 9418 18/4
AWG SHLD. CABLE
WITH DRAIN/GROUND
WIRE. TYP
PROVIDE AN ENGRAVED
PLASTIC LABEL INDICATING
ZONE SERVED BY ALARM
SILENCE PANEL. LETTERING
SHALL BE BLACK, MINIMUM
OF 1/4" HIGH, ON A WHITE
BACKGROUND.
COORDINATE LEAK
DETECTION SENSOR
INSTALLATION LOCATION
WITH WALK-IN RACKING
PANEL POWER
INDICATOR LIGHT
ZONE MRLDS POWER
INDICATOR LIGHT.
TYP
DIXELL iPRO
CONTROL SCREEN
UNINTERRUPTED POWER
SUPPLY (UPS) READY
INDICATOR LIGHT. OFF =
<20% BATTERY
REMAINING.
DOOR TO BASE BRAIDED
GROUND STRAP (6"
MAX). CPC #135-1004
OR EQUAL. CONNECTS
POINTS INSIDE PANEL.
3/8" 6-32 STUD
PROTRUDES INTO
ENCLOSURE. INCLUDES
STAR WASHER AND NUT.
WALL-MOUNTED LEAK
DETECTION PANEL.
20.75"x 27 3/8"
BAS Cmn
BAS Zn2 SIl
BAS Zn3 Sil
BAS Zn4 Sil
BAS Zn5 Sil
BAS Zn6 Sil
24VAC Out
NO Contacts
ZONE ALARM,
LIGHT &
SILENCE
22/2 CABLE OR
EQUIVALENT
BAS Zn1 SIl
SENSOR 1 1-5V IN
SENSOR -IN
SENSOR 1 SHIELD
iPRO ANALOG OUT1 -
iPRO ANALOG OUT1 +
MRLDS 1 24VAC PWR
MRLDS 1 24VAC PWR
HRN/STROBE 24VAC N
HORN OUT 24VAC HOT
STROBE OUT 24VAC HOT
HRN/STROBE 24VAC HOT
ZONE 1 AUX DRY CONTACT OUT -NC
ZONE 1 AUX DRY CONTACT OUT - C
ZONE 1 AUX DRY CONTACT OUT - NO
BAS ZONE SILENCE COMMON
HORN/STROBE
(24VAC)
SIGNAL STROBE
MRLDS LEAK DETECTION
SENSOR BACKPLATE
REPEAT PER ZONE
FRONT "LEAK
DETECTION
PANEL" VIEW
INSIDE "LEAK
DETECTION
PANEL" VIEW
ZONE 1
GAS
(+)
LEAK DETECTION PANEL FURNISHED
BY LEAK DETECTION VENDOR.
SEAL ALL PENETRATIONS
WITH SILICONE SEALANT
PROVIDE 1" EMT
STUB UP TO
STRUCTURE
INSTALL LEAK
DETECTION PANEL
(LDP) 42" AFF
SEAL BASE OF
LDP WITH
SILICONE SEALANT
LEAK DETECTION DEVICE
WIRING PER LEAK
DETECTION ZONE. TYP
18/4 CABLE OR
EQUIVALENT
WIR-2020 OR EQUIVALENT.
CABLE FURNISHED AND
INSTALLED BY BAS
CONTRACTOR.
18/4 CABLE OR
EQUIVALENT
18/4 CABLE OR
EQUIVALENT
ZONE 1 DRY CONTACT OUT -NC
ZONE 1 DRY CONTACT OUT - C
ZONE 1 DRY CONTACT OUT - NO
11.21.17
ZONE ALARM
SILENCE PANEL
MRLDS LEAK
SENSOR
HORN/STROBE ALARM
DAISY CHAIN TO ADDITIONAL
HORN/STROBES AS NECESSARY.
REFER TO PLANS FOR WALK-IN
HORN/STROBE QUANTITY.
ANALOG WIRING TO
INPUT MODULE AT RACK.
DIGITAL WIRING TO INPUT
MODULE AT RACK.
LDP
ZA
L
REFER TO LEAK DETECTION
PANEL INSTALLATION AND
WIRING DETAIL FOR CABLE
TYPES.
LEAK DETECTION PANEL. ONE
LDP SERVES UP TO (6) LEAK
DETECTION ZONES. REFER
TOPLANS FOR PANEL
LOCATION.
COMPRESSOR HOUSE
WALK-IN LEAK
DETECTION ZONE
XIO
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.BASR3
BUILDING
AUTOMATION
SYSTEM
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
REFRIGERANT LEAK CONTROL SEQUENCE OF OPERATION FOR COOLERS AND FREEZERS:
THE LEAK DETECTION CONTROL MODULES, UPON REGISTERING A CONCENTRATION THAT IS: ONE-HALF OF THE IDLH OR AT THE OEL; WHICHEVER IS LESS, SHALL:
1. ACTIVATE VISUAL AND AUDIBLE ALARMS FOR THE ZONE INDICATING THE LEAK
2. ENABLE AN AUTOMATIC SHUTDOWN OF THE LLSV AND EEPR TO ISOLATE THE REFRIGERANT FLOW IN THE CIRCUIT IN ALARM.
AUDIBLE / VISUAL DEVICES INSIDE COOLERS AND FREEZERS SHALL BE INSTALLED IN WEATHERPROOF JUNCTION BOXES, REFERENCE LEAK DETECTOR INSTALLATION DETAIL.
AUDIBLE / VISUAL DEVICES SHALL ANNUNCIATE AT A SOUND PRESSURE LEVE THAT IS A MINIMUM OF 15 DBA ABOVE THE AMBIENT NOISE LEVEL.
LEGEND
OEL: OCCUPATIONAL EXPOSURE LIMIT TWA: TIME WEIGHTED AVERAGE LLSV: LIQUID LINE SOLENOID VALVE
IDLH: IMMEDIATELY DANGEROUS TO LIFE OR HEALTH SPL: SOUND PRESSURE LEVEL EPR: EVAPORATOR PRESSURE REGULATOR
REFRIGERATION LEAK DETECTION SEQUENCE OF OPERATIONS
11.02.15
NTS2COOLER/FREEZER LEAK DETECTION DEVICE MOUNTING
NTS1LEAK DETECTION PANEL INSTALLATION AND WIRING
NTS3LEAK DETECTION ZONE DEVICES ONE-LINE DIAGRAM
ISSUE BLOCK
NOTE
E
E
E
E
EE
PIPING SCHEDULE RACK LTC
VERTICAL ESTIMATED
PIPE HORIZONTAL SUCTION RISER TOTAL
DESIGNATION SUCTION
AS REQUIRED LIQUID LENGTH
^^C1 2-1/8 1-3/8 5/8 175
1) RISER SIZE IS SHOWN EVEN WHERE A RISER IS NOT EXPECTED. THIS IS FOR
REFERENCE ONLY AND TO BE USED IN THE EVENT THAT A PIPING CONFLICT
CAUSES THE NEED FOR A RISER. IF RISER LENGTH EXCEEDS 4 FEET, IT MUST BE
APPROVED BY ENGINEER OF RECORD.
2) ESTIMATED TOTAL LENGTH INCLUDES HORIZONTAL AND VERTICAL PIPE SECTIONS.
THIS IS ONLY AN ESTIMATE AND ACTUAL LENGTH WILL VARY.
3) ALL EXISTING PIPE SIZES ARE BASED ON ORIGINAL REFRIGERATION LEGENDS
^ RISER SIZE IS SHOWN EVEN WHERE A RISER IS NOT EXPECTED. THIS IS
FOR REFERENCE ONLY AND IS TO BE USED IN THE EVENT THAT A PIPING
CONFLICT CAUSES THE NEED FOR A RISER. IF THE RISER LENGTH EXCEEDS 4
FEET, IT MUST BE APPROVED BY ENGINEER OF RECORD.
**** NEW PIPING
^^ NEW PIPING CONNECTED TO EXISTING PIPING TO REMAIN. REFER TO
REFRIGERATION PIPING PLAN FOR APPROXIMATE LOCATION OF
NEW AND EXISTING PIPING.
1
1
2
2
3
3
4
4
G G
H H
J J
ICE CREAM
FREEZER
GROCERY
FREEZER
DAIRY
COOLER
C-1
KR64E-220
(REPLACED)
EXISTING CONDENSATE
HEADER TO REMAIN.
15.605
EXISTING PIPING TO
REMAIN. NOT ALL PIPING
SHOWN. TYP; UNO.
CO
CD
PROVIDE RUNNING TRAP
BETWEEN COOLER WALK-IN
AND FREZZER WALK-IN ON
COOLER SIDE.
STACKED CONDENSATE
PIPING.
CO
15.607
HCR DOOR PROVIDED AND
INSTALLED BY OTHERS, TYP.
2
R3
1
R2
5
R3
SIM
15.606
TYP15.604
C1
15.638
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.R1
REFRIGERATION
PLAN AND
PIPING
SCHEDULES
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
KEYNOTES
15.604 PROVIDE AIRTIGHT SEAL AROUND ALL PIPING
AND BOLT PENETRATIONS THROUGH
COOLER/FREEZER BOX WALLS OR CEILINGS.
15.605 SUPPORT EVAPORATORS WITH BOLTS THROUGH
ROOF TO 1-5/8" X 1-5/8" X 10' LONG 14 GA.
GALVANIZED UNISTRUT SPANNING THREE ROOF
PANELS. PROVIDE DOUBLE NUTS ON EACH BOLT.
15.606 CONDENSATE DRAIN; PITCH DRAIN LINES DOWN
APPROXIMATELY 1" PER 10' TOWARD DRAIN.
PROVIDE COPPER PIPING WITH ELECTRIC HEAT
TAPE AND INSULATION ON ALL CONDENSATE
LINES EXPOSED TO FREEZING TEMPERATURES.
15.607 SEE SCHEDULES FOR EVAPORATOR TYPES,
SIZES, AND CAPACITIES; CONTROL METHOD; AND
ALL REFRIGERATION PIPING SIZES, ETC.
15.638 REFRIGERATION CONTRACTOR SHALL FURNISH
AND INSTALL LIQUID LINE SOLENOID,
EVAPORATOR PRESSURE REGULATOR, AND
FULL PORT ISOLATION BALL VALVES IN A
SERVICE ACCESSIBLE LOCATION ON TOP OF
WALK-IN BOX. COORDINATE LOCATION WITH
EDGE PROTECTION SYSTEM. REFER TO
REFRIGERATION SUBMITTALS / SCHEDULES FOR
EXACT REQUIREMENTS. PROVIDE VALVE
LOCATION IDENTIFICATION TAG OF ENGRAVED
PLASTIC. REMOVE THE EXISTING CIRCUIT
CONTROL VALVES AT THE COMPRESSOR HOUSE
AS REQUIRED.
CIRCUIT NUMBER (CIRCUIT INFO)
REFRIGERATION PIPING (BELOW)
TYPICALTYP
10.12.17
##.####
CONNECT TO EXISTING
CONTINUATION
ELBOW -TURNED DOWN
CONDENSATE DRAIN LINE (CD)
CLEANOUTS (CO)
EVAPORATOR COIL
REFRIGERATION KEYNOTE REFERENCE
REFRIGERATION PIPING (ABOVE)
CO
(DETAIL REFERENCE)DETAIL NUMBER
EXISTING TO REMAINETR
#
X#
X-##
# XXX
ELBOW TURNED UP
ISOLATION VALVE
REFRIGERATION SYMBOLS
QUANTITY / MODEL NUMBER
SHEET NUMBER
DEMO REFRIGERATION PIPING
GENERAL NOTES
1. PLANS INDICATE GENERAL ROUTING OF
REFRIGERANT LINES, WITH A SINGLE LINE
SHOWN INDICATING BOTH SUCTION AND LIQUID
LINE ROUTING FOR EACH SYSTEM.
2. REFRIGERATION SYSTEM INSTALLATION SHALL
BE IN COMPLETE CONFORMANCE WITH
SPECIFICATIONS, AND WITH ALL REQUIREMENTS
OF REFRIGERATION EQUIPMENT
MANUFACTURER.
3. REFRIGERATION DRAWINGS ARE PROVIDED AS
AN AID TO BIDDERS AND TO INDICATE DESIRED
ROUTING OF REFRIGERATION LINES;
CONTRACTOR SHALL ASSUME FULL
RESPONSIBILITY FOR CORRECT INSTALLATION
OF PIPING AND ACCESSORIES TO PROVIDE A
COMPLETE AND FULLY OPERATING SYSTEM.
4. REFER TO SPECIFICATION 15600 FOR
INSULATION THICKNESS. INSIDE DIAMETER OF
INSULATION SHALL MATCH PIPE DIAMETER TO
MINIMIZE AIR GAPS BETWEEN PIPING AND
INSULATION. PROVIDE FACTORY PRE-
MANUFACTURED FITTINGS AT ALL TRAPS AND
ELBOWS. WHERE PRE-MANUFACTURED
FITTINGS ARE UNAVAILABLE MITER CUT ALL
FITTINGS TO ENSURE PROPER SEAL BETWEEN
INSULATION SEGMENTS.
5. PIPE INSULATION SHALL MATCH EXISTING
COLOR UNLESS NOTED OTHERWISE ON PLANS
OR SPECIFICATIONS.
6. COORDINATE REFRIGERATION DEMOLITION
ISSUES WITH THE ARCHITECTURAL DRAWINGS.
REFER TO ARCHITECTURAL PLANS FOR
REFRIGERATION EQUIPMENT DEMOLITION AND
COOLER REPAIR AND REMODELING.
7. REFRIGERATION SYSTEM SHALL REMAIN
OPERATIONAL DURING REMODELING. DURING
THE PHASING OF OLD TO NEW SYSTEMS, BOTH
NEW AND OLD REFRIGERATION SYSTEMS MAY
BE REQUIRED TO OPERATE AT THE SAME TIME
FOR A SHORT PERIOD.
8. WHERE NEW REFRIGERATED EQUIPMENT IS
INDICATED ON THE DRAWINGS, PROVIDE
DEMOLITION, REMOVAL, AND TEMPORARY
STORAGE OF OLD EQUIPMENT PER WALMART
MECHANICAL SERVICES CONSTRUCTION
MANAGER'S INSTRUCTIONS, AND
REFRIGERATION DEMO NOTES.
9. COORDINATE REMOVAL AND DISPOSAL OF
EXISTING EVAPORATORS, REFRIGERATED
CASES, AND CONDENSING UNITS, WITH
WALMART MECHANICAL SERVICES
CONSTRUCTION MANAGER.
10. REMOVE COPPER LINES, EVAPORATORS, AND
CONDENSATE LINES FROM COOLERS/
FREEZERS BEING REMOVED FROM SITE.
COORDINATE WITH WALK-IN PANEL VENDOR
FOR TIME LINE OF REPLACEMENT. REFERENCE
SPECIFICATION FOR CONTACT INFORMATION.
11. WALK-IN PANEL VENDOR SHALL PROPERLY
PREPARE ALL COOLER/FREEZER PANELS,
GLASS DOORS, SLIDER OR SWING DOORS,
PALLETIZE, AND PREPARE THE EQUIPMENT TO
SHIP OFF SITE.
12. COORDINATE WITH FIRE PROTECTION
CONTRACTOR FOR THE REMOVAL OF
SPRINKLERS FOR ALL REMOVED
COOLER/FREEZER BOXES.
13. COORDINATE WITH ELECTRICAL CONTRACTOR
FOR THE REMOVAL OF ALL REMOVED
COOLER/FREEZER BOXES ELECTRICAL WIRING
DEVICES.
14. COORDINATE WITH BAS CONTRACTOR FOR THE
REMOVAL OF ALL REMOVED COOLER/FREEZER
BOXES BAS WIRING AND DEVICES.
15. EXISTING REFRIGERATION PIPING MAY BE RE-
USED UNLESS OTHERWISE NOTED ON PLANS.
REFER TO SCHEDULES FOR PIPE SIZE
REQUIREMENTS.
16. BUILDING COMPONENTS ABANDONED BY THE
SCOPE OF WORK SHALL BE SECURED TO
PREVENT FALLING, LOOSENING, OR CREATING
DAMAGE OF ANY KIND IN THE FUTURE.
17. IF ANY RACK SYSTEMS WILL BE OPENED TO ADD
OR REPLACE CASES, EVAPORATORS, ETC. THEN
24 TO 48 HOURS AFTER THE WORK IS
COMPLETED AND ALL FINAL ADJUSTMENTS
HAVE BEEN MADE, PROVIDE AND CHANGE
LIQUID LINE FILTER CORES, OIL SYSTEM FILTER
USING SPORLAN OF STYLE FILTER, AND
REPLACE SUCTION FILTERS. FILTERS ARE TO BE
RATED FOR WAX REMOVAL. CONTRACTOR TO
PROPERLY DISPOSE OF OIL AND COMPONENTS
REPLACED. REFER TO SPECIFICATION 15600.
18. REFER TO GROCERY ARCHITECTURAL
DRAWINGS FOR ADDITIONAL WORK BY
REFRIGERATION CONTRACTOR.
19. COMPLETE ASSET TAGGING PROCESS FOR ALL
NEW REFRIGERATED CASES. REFER TO
SPECIFICATIONS.
01.31.18
REMOVE EXISTING REFRIGERATION EQUIPMENT NOTED
FOR DEMO OR REPLACEMENT, INCLUDING (BUT NOT
LIMITED TO): REFRIGERATED CASES, WALK-IN COILS,
ASSOCIATED VALVES, REFRIGERATION AND
CONDENSATE PIPING, HANGERS AND SUPPORTS, AND
CONTROLS NOT BEING REUSED. COORDINATE DISPOSAL
OF EQUIPMENT WITH CONSTRUCTION MANAGER. PATCH
PENETRATIONS TO MATCH EXISTING. REFER TO
ARCHITECTURAL DRAWINGS.
REFRIGERATION CONTRACTOR IS RESPONSIBLE FOR ALL
FINAL REFRIGERATION ELECTRICAL TERMINATIONS TO
REFRIGERATION EQUIPMENT.
EPA CLEAN AIR ACT
COMPLY WITH CLEAN AIR ACT, TITLE VI, SECTION 608
AND CODE OF FEDERAL REGULATION TITLE 40, PART 82
WHEN ADDING OR REMOVING REFRIGERATED
EQUIPMENT. RECORD ALL EQUIPMENT IDENTIFICATION
NUMBERS, MODEL AND SERIAL NUMBERS, THE AMOUNT
OF REFRIGERANT RECOVERED FROM EACH UNIT, THE
DATE OF DECOMMISSIONING, COMPANY NAME AND
SIGNATURE OF ON-SITE SUPERVISOR.11.02.15
24 HOURS PRIOR TO SHUTTING DOWN ANY
REFRIGERATION SYSTEMS, HVAC SYSTEMS OR BUILDING
AUTOMATION CONTROLS SYSTEMS, SEND EMAIL TO
NSRM@WALMART.COM. THE E-MAIL SHALL STATE WHAT,
WHY, AND WHEN IT IS BEING SHUT DOWN AND HOW LONG
IT IS ANTICIPATED TO BE SHUT DOWN. THEN SEND A
FOLLOW UP EMAIL TO NSRM@WALMART.COM AFTER THE
WORK IS COMPLETE AND THE SYSTEM IS BACK UP AND
RUNNING.
UNLESS NOTED OTHERWISEUNO
SIMILARSIM
* MODIFY CIRCUIT
** NEW CASE, COIL, CIRCUIT OR VALVE
**** CHANGE EXISTING PIPE SIZE AS INDICATED
^^ NEW PIPING CONNECTED TO EXISTING PIPING TO
REMAIN. REFER TO REFRIGERATION PIPING PLAN
FOR APPROXIMATE LOCATION OF NEW AND
EXISTING PIPING.
^ RISER SIZE IS SHOWN EVEN WHERE A RISER IS
NOT EXPECTED. THIS IS FOR REFERENCE
ONLY AND IS TO BE USED IN THE EVENT THAT
A PIPING CONFLICT CAUSES THE NEED FOR A
RISER. IF THE RISER LENGTH EXCEEDS 4 FEET, IT
MUST BE APPROVED BY ENGINEER OF RECORD.
# CONTRACTOR TO FIELD VERIFY EXISTING
RISER SIZE. IF EXISTING PIPE SIZE DOES NOT
MATCH SCHEDULE, REPLACE EXISTING RISER
WITH NEW SIZE AS SHOWN.
PIPING SYMBOLS
SEISMIC NOTES
12.20.13
REFER TO SEISMIC RESTRAINT SHEET SR1 FOR
INSTALLATION DETAILS. REFER TO THE SPECIFICATIONS
FOR FURTHER INFORMATION.
1/8" = 1'-0" 1 REFRIGERATION PLAN
ISSUE BLOCK
NOTE
REFRIGERATION SCHEDULE - EXISTING RACK LTC Refrig. EMS:Novar Condenser Type:Air H/R Media: --
Subcooler Liquid Temps SG1 Comp RGT ºF:-- DESIGN DB ºF : 100 EXTERIOR DRY BULB (DB) ºF :96.6
Format: SC Store#: 03705
System Type:Weatherpac Refrigerant:R448a System Elec:460V 3Ph 60 Hz Sat. Cond. Temp ºF:115 H/R Use:--SG1 Liq Temp ºF:--SG2 Comp RGT ºF:--DESIGN WB ºF :--Based on 5 yr Extreme DB-ASHRAE Pub.:2021
Proto Size: 176
City/State:Yelm, WA Consultant:Hargis Engineers Estimated Refrigerant Charge --Defrost Elec: 208V 60 Hz 1 or 3Ph
Cond Design TD ºF:15 H/R Water GPM:--SG2 Liq Temp ºF:--SG3 Comp RGT ºF:--DESIGN INTERIOR DRY BULB ºF : 75 EXTERIOR WET BULB (WB) ºF :70.6
ProtoCycle Date:--Date Prepared 04/19/24 Prepared by: Wyatt King Rack and Condenser (lbs)--Sys.Pilot Elec:208V 1Ph Summer H/R Avail: N/A
H/R Glycol Type:--SG3 Liq Temp ºF:--Evap. Superheat ºF:10 DESIGN INTERIOR RH % : 55%
Based on 0.4% Monthly Max WB-ASHRAE Pub.:2021
Fixture and Field Piping (lbs)--Cond. Elec: 460V 3Ph 60 Hz Winter H/R Avail: N/A
H/R Glycol %:--ASHRAE Design Conditions Weather Station: Gray AFF WMO: 742071 ELEVATION ft: 300 ASHRAE Climate Zone: 3B
CIRCUIT INFORMATION FIXTURE ELECTRICAL INFORMATION MISC INFORMATION
Case Fixture Length / Quantity Walk-In Box Size LSHX Y or N?Evaporator Case/Lights Anti-Sweat Drain Pan
& Model #Coil TXV / Sub-Circuit Load Circuit Evap. Walk-In Circuit Control Valves Defrost Defrost Heaters Fans Amps Amps Amps
CKT #FT /# of Doors 2 Dr/4' 3 Dr/6' 4 Dr/8' 5 Dr/12' L W H
Case/Coil Model Case/Coil Manuf. Application WI Evaps Distributor Nozzle (MBH) Load (MBH)
SST Air Temp EPR LLSV Type Amps Voltage Amps Voltage (120v) (120v) (120V)
Comments Equip Number CKT #
*C01 18 18 12 **KRD64E-220TDAK KRACK Ice Cream Freezer **HX-6 **SER-C / **#2 -21.6 -20 -10 **CDST-9-11 **E6S140 EL 17.4 208/3 3.6 208/1 - - -WALK-IN & EVAP REPLACED - *C01
C02 10 DRS ONRZH-E HILL PHEONIX Reach-In Ice Cream - --12.3 -17 ETR SORIT-12 ME6S140 EL 30.2 208/3 5.0 120/1 ETR ETR ETR ETR ETR C02
C03 10 DRS ONRZH-E HILL PHEONIX Reach-In Ice Cream -- - 12.3 -17 ETR SORIT-12 ME6S140 EL 27.6 208/3 5.0 120/1 ETR ETR ETR ETR ETR C03
C04 2 ENDS FWE HUSSMANN Dual Temp End Cases - --4.4 -20 ETR SORIT-12DT ME6S140 EL 13.0 208/1 1.6 120/1 ETR ETR ETR ETR ETR C04
C05 24 FT FW HUSSMANN Dual Temp Coffin - --12.7 -20 ETR SORIT-12DT ME6S140 EL 30.4 208/3 6.4 120/1 ETR ETR ETR ETR ETR C05
C06 2 ENDS FWE HUSSMANN Dual Temp End Cases - --4.4 -20 ETR SORIT-12DT ME6S140 EL 13.0 208/1 1.6 120/1 ETR ETR ETR ETR ETR C06
C07 24 FT FW HUSSMANN Dual Temp Coffin - --12.7 -20 ETR SORIT-12DT ME6S140 EL 30.4 208/3 6.4 120/1 ETR ETR ETR ETR ETR C07
C08 10 DRS ONRZH-E HILL PHEONIX Reach-In Ice Cream - --12.3 -17 ETR SORIT-12 ME6S140 EL 30.2 208/3 5.0 120/1 ETR ETR ETR ETR ETR C08
C09 - - Spare - --- - - - - - - - - - - - - ETR ETR C09
Total Load: 92.7 -23 Sat. Suction Temp °F
General Notes:
1.)Refrigeration OEM: Hussmann
2.)Case/Evap changes result in a net CHANGE of 0.0 MBH.
LIQUID LINE FROM RACK
PROVIDE NORMALLY
OPEN FULL PORT BALL
VALVE WITH INTEGRAL
SCHRADER VALVE IN
AN ACCESSIBLE
LOCATION. ENSURE
SCHRADER VALVE IS
ORIENTATED AS
SHOWN. PROVIDE
INSULATION FOR BOTH
VALVES. DO NOT TRAP
LIQUID BY CLOSING
LOOP AND CASE
ISOLATION VALVES
WHEN SERVICING.
INSULATION
SUCTION LINE TO RACK
07.07.17
INTERMEDIATE SUCTION LINE TRAP IN
WALL, VOID SPACE, OR HIDDEN FROM
VIEW. INTERMEDIATE TRAP SHOULD BE
PLACED AT THE MIDPOINT OF ANY
SUCTION LINE RISE WHICH EXCEEDS 16
FEET OR PLACED AT THE HIGHEST
POINT THAT IS HIDDEN FROM VIEW.
SUCTION LINE (TYP)
INVERTED
SUCTION LINE
TRAP AT TOP OF SUCTION
LINE RISER (TYP)
LIQUID
LINE (TYP)
SUCTION LINE TRAP
AT THE BASE OF
THE RISER AT ALL
POINTS WHERE
SUCTION LINES RISES.
SECURE ALL VERTICAL
REFRIGERATION PIPING TO
UNISTRUT MOUNTED TO THE WALL
OR SECURED VIA HANGERS. REFER
TO VERTICAL REFRIGERATION LINE
SUPPORT DETAIL. (TYP)
INSTALL VERTICAL PIPING AS
COMPLETELY SELF-SUPPORTING
BEFORE CONNECTING TO OTHER
PIPING.
REFER TO UNISTRUT
PIPING SUPPORT DETAIL
REFER TO LINE RACKING BEHIND
REFRIGERATED CASES DETAIL
OR VERTICAL FACE PIPING
SUPPORT DETAIL.
CONSTRUCT INTERMEDIATE
SUCTION LINE TRAPS FROM
PRE-MANUFACTURED TRAPS.
(TYP)
REDUCE RISER
PIPE SIZE AFTER
BASE TRAP
FREEZER/COOLER
BOX CEILING OR
WALLPATCH HOLE WITH 26 GAUGE
GALVANIZED SHEET METAL
TRIM (TOP AND BOTTOM)
SEAL PATCH WITH
SILICONE (TYP.)
EXPANDING FOAM
SEALANT (TYP.)
ATTACH PATCH WITH #8 X 3/4 HEX
HEAD SELF TAPPING SCREWS (TYP.)
SEAL FILL OPENING
WITH SILICONE
PROCEDURE FOR PATCHING HOLES:
1. ATTACH 26 GAUGE GALVANIZED SHEET METAL TRIM TO BOTTOM OF HOLE AND
PARTIALLY TRIM TOP OF HOLE LEAVING 1" GAP AT TOP FOR EXPANDING FOAM
SEALANT FILL.
2. FILL OPENING WITH EXPANDING FOAM SEALANT, LET EXPAND AND CURE AND
TRIM EXCESS FOAM FROM FILL OPENING.
3. SEAL ALL EDGES AND EXPANDING FOAM SEALANT OPENING WITH SILICONE
SEALANT.
4. VERIFY SPECIFIC APPLICATION WITH THE WALK-IN PANEL MANUFACTURER.
07.07.17
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.R2
REFRIGERATION
SCHEDULES
AND DETAILS
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
NTS3REFRIGERATION ISOLATION VALVES
NTS2
INTERMEDIATE
SUCTION LINE TRAP
NTS1COOLER/FREEZER BOX PENETRATION PLUG
OWNER FURNISHED WALK-IN EVAPORATOR COIL SCHEDULE
Manufacturer VENDOR Type VOLTAGE QTY NOTES
KRACK HUSSMANN CORPORATION KR64E-220 208 V 1
GENERAL INFORMATION (ALL COILS):
1. COILS FURNISHED BY OWNER AND INSTALLED BY CONTRACTOR.
2. INFORMATION CONTAINED WITHIN THIS SCHEDULE IS FOR OWNER'S PURCHASING REPRESENTATIVE. REFER TO REFRIGERATION SCHEDULE(S) FOR SPECIFIC
INFORMATION REGARDING EQUIPMENT.
3. SUPPLIER SHALL VERIFY PRODUCT REQUIREMENTS INCLUDING BUT NOT LIMITED TO LIQUID TO SUCTION HEAT EXCHANGER, EXPANSION DEVICE TYPE, ELECTRICAL
REQUIREMENTS, ETC. WITH REFRIGERATION SCHEDULE(S).
NOTES:
A.EVAPORATOR COIL SHALL BE FURNISHED WITH FACTORY INSTALLED VALVES, SENSORS, TRANSDUCERS, AND ALL OTHER APPURTENANCES, AS OUTLINED IN THE 15690
EQUIPMENT SPECIFICATION, INCLUDING: ELECTRONIC EXPANSION VALVE (EEV), SCHRADER VALVES (TWO IN THE SUCTION LINE, ONE IN THE LIQUID LINE, UPSTREAM OF
THE EEV), SUCTION PRESSURE TRANSDUCER, AIR TEMPERATURE SENSOR, SUCTION TEMPERATURE SENSOR, DEFROST TERMINATION TEMPERATURE SENSOR AND ALL
OTHER COMPONENTS. REFER TO DETAILS FOR FIELD INSTALLED CONTROL WIRING BETWEEN EVAPORATOR COIL AND WALK-IN UNIT CONTROLLER.
HCR PCAV AIR CURTAIN WALMART PANEL VENDOR RC EC A, B
FURNISHED BY INSTALLED BY START-UP BY ELECTRICAL BY
EQUIPMENT RESPONSIBILITY NOTES
HCR RESPONSIBILITY MATRIX
GENERAL INFORMATION:
1. REFER TO EQUIPMENT SCHEDULED FOR EQUIPMENT INFORMATION.
NOTES:
A. ELECTICAL WIRING AND CONNECTIONS BY EC INCLUDING PANEL TO DISCONNECT, DISCONNECT TO CONTROLLER HEAD,
INTERCONNECTIONS BETWEEN CONTROL PANEL AND AIR DOOR, AND DOOR SWITCH WIRE. ALL WIRING SHALL BE ROUTED
THROUGH CONDUIT.
B.START-UP OF HCR PCAV DOOR INCLUDES INSTALLATION OF DOOR SWITCH AND FOLLOWING ENTIRE HCR START-UP GUIDE.
A
ISSUE BLOCK
NOTE
EXIT WALK-IN AS SOON AS
POSSIBLE AND RUN HEADER
ALONG EXTERIOR OF BOX.
COORDINATE HEADERS
WITH FIXTURES AND
EQUIPMENT OUTSIDE
WALK-IN BOX. TYP
WALK-INS WITH TEMPERATURES
BELOW FREEZING
USE COPPER PIPING WITH
ELECTRIC HEAT TRACE AND
INSULATION ON CONDENSATE
LINES EXPOSED TO FREEZING AND
WHEN OTHERWISE NOTED. TYP
EACH INDIVIDUAL
EVAPORATOR DRAIN MUST
CONNECT DIRECTLY TO
HEADER. TYP
COORDINATE HEADERS WITH
FIXTURES AND EQUIPMENT
INSIDE WALK-IN BOX. TYP
TERMINATE CONDENSATE DRAIN
OVER HUB DRAIN OR SERVICE
SINK WITH AIR GAP. INSTALL
TRAP UPSTREAM OF HUB DRAIN
OR SERVICE SINK. TYP
TERMINATE COPPER DRAINS TO
COMMON COPPER HEADER ONE
SIZE LARGER THAN COIL DRAIN
AND MAINTAIN SLOPE OF 1/8" PER 12"
TOWARD DRAIN.
DIRECT
CONNECTION TO
HEADER. TYP
WALK-INS WITH TEMPERATURES
ABOVE FREEZING
USE 2" COMMON PVC HEADER
AND MAINTAIN SLOPE OF 1/8"
PER 12" TOWARD DRAIN.
EACH INDIVIDUAL EVAPORATOR
DRAIN MUST CONNECT
DIRECTLY TO HEADER. TYP TERMINATE CONDENSATE DRAIN
OVER HUB DRAIN OR SERVICE
SINK WITH AIR GAP. INSTALL
TRAP UPSTREAM OF HUB DRAIN
OR SERVICE SINK. TYP
TERMINATE COPPER DRAINS TO
COMMON PVC HEADER. UTILIZE A
UNION AT ALL COPPER TO PVC
TRANSITIONS. TYP
PROVIDE
CLEANOUT FOR
ALL HEADERS. TYP
TERMINATE CONDENSATE DRAIN
OVER HUB DRAIN OR SERVICE
SINK WITH AIR GAP. INSTALL
TRAP UPSTREAM OF HUB DRAIN
OR SERVICE SINK. TYP
WALK-INS WITH TEMPERATURES
ABOVE OR BELOW FREEZING
TERMINATE INDIVIDUAL COPPER DRAINS TO 2"
COMMON PVC HEADER AND MAINTAIN SLOPE
OF 1/8" PER 12" TOWARD DRAIN. UTILIZE A
UNION AT ALL COPPER TO PVC TRANSITIONS.
INSULATE COPPER PIPE OUTSIDE WALK-IN
WALL PER SPECIFICATIONS
INSTALL TRAP AT EACH
INDIVIDUAL DRAIN
UPSTREAM OF HEADER.
TYP
BELOW FREEZING ABOVE FREEZING
PROVIDE TRAP UPSTREAM
OF INDIRECT CONNECTION
FROM COPPER TO PVC.
REF WALK-INS WITH
BELOW FREEZING
PLAN VIEW.
REF WALK-INS WITH
TEMPERATURES
ABOVE FREEZING
PLAN VIEW.
USE ELECTRIC HEAT TRACE AND
INSULATION ON CONDENSATE LINES
EXPOSED TO FREEZING AND WHEN
OTHERWISE NOTED. TYPCOPPER PIPING
FOR ALL INDIVIDUAL
DRAINS. TYP
CONDENSATE DRAINS SERVING
MULTIPLE WALK-INS
COORDINATE HEADERS WITH
FIXTURES AND EQUIPMENT
INSIDE WALK-IN BOX. TYP
UTILIZE A UNION AT COPPER TO
PVC TRANSITION. INSULATE
COPPER PIPE OUTSIDE WALK-IN
WALL PER SPECIFICATIONS
PROVIDE RUNNING TRAP FOR INTERIOR CONDENSATE HEADERS
RUNNING BETWEEN MULTIPLE WALK-INS OPERATING AT
TEMPERATURES ABOVE FREEZING. IF A CONDENSATE PIPE
FROM ONE WALK-IN MUST BE ROUTED THROUGH A WALK-IN
EXPOSED TO FREEZING TEMPERATURES, USE A SEPARATE
DEDICATED CONDENSATE PIPE FOR EACH WALK-IN.
WHEN HEADER CANNOT
RUN ALONG BOX EXTERIOR
WHEN HEADER CANNOT
RUN ALONG BOX EXTERIOR
WHEN HEADER CANNOT
RUN ALONG BOX EXTERIOR
11.17.17
S
L
SCHRADER VALVE
WALK-IN WALL
SLOPE DRILL HOLE IN COOLER/FREEZER BOX WALLS, CENTER PIPE
IN OPENING, AND SEAL WITH EXPANDING FOAM. AFTER
FOAM CURES, TRIM FLUSH TO PANEL. BUTT INSULATION TO
THE BOUNDARY OF BOX PENETRATION. SEAL WHERE
INSULATION BUTTS AGAINST THE PANEL AND AROUND
PERIMETER OF INSULATION TO CREATE VAPOR BARRIER.
TYP OF ALL PIPE PENETRATIONS THROUGH BOX WALL. (TYP)
HOLE DIAMETER 1" GREATER THAN PIPE
INSULATED WALL
EXPANDING
FOAM
REFRIGERANT LINE
SILICONE SEALANT
INSTALL AND INSULATE LIQUID LINE SOLENOID,
EVAPORATOR PRESSURE REGULATOR AND FULL PORT
BALL VALVES ON TOP OF WALK-IN COOLER/FREEZER.
MOUNT NEAR EDGE OF WALK-IN TO ALLOW SERVICE
ACCESS. COORDINATE WITH EDGE PROTECTION SYSTEM.SLOPE REFRIGERANT LINES DOWN
TOWARD COMPRESSORS AT 1" PER 20 FT.
LOCATE HIGHEST POINT OF REFRIGERANT
LINES JUST BELOW ROOF DECK OVER COIL
SERVED. ROUTE THROUGH WEBS IN JOIST
GIRDERS WHERE POSSIBLE. COORDINATE
WITH SKYLIGHTS, HVAC, LIGHTING,
CONDUIT AND FIRE PROTECTION.
SEAL AROUND BOLT
PENETRATIONS THRU
COOLER/FREEZER BOX WALLS
OR CEILINGS WITH BACKER
ROD AND SEALANT. (TYP)
SUPPORT EVAPORATORS WITH
BOLTS THRU CEILING PANEL TO
1 5/8" X 1 5/8" X 10 FT. LONG 14
GAUGE. GALVANIZED UNISTRUT
SPANNING THREE
COOLER/FREEZER CEILING
PANELS. PROVIDE DOUBLE
NUTS ON EACH BOLT. (TYP)
FOAM TOPS OF BOLT PENETRATIONS. (TYP.)
SUCTION LINE
TRAP
EVAP
FAN/COIL
UNIT
PROVIDE INVERTED P-TRAP
ON TOP OF ALL SUCTION
RISERS
PIPE
INSULATION
MOUNT COIL ACCORDING TO
MANUFACTURER'S RECOMMENDATIONS. (TYP)
SHORT RADIUS TRAP SHALL BE
ONE-PIECE CONSTRUCTION.
HOLD AS HIGH AS POSSIBLE
REFERENCE EVAPORATOR COIL
CONDENSATE PIPING DETAIL.
INSTALL 3/4" LONG RADIUS DRAIN TRAP
AT EACH INDIVIDUAL DRAIN UPSTREAM
OF HEADER.
PROVIDE COPPER CONDENSATE
DRAIN PIPING FULL SIZE OF COIL
DRAIN PAN CONNECTION AND
SLOPE 1/8" PER 12" TOWARD DRAIN
OR HEADER.
DRAIN PAN
UNION
11.17.17
3"
MAX
3"
MAX
INSUGUARD OR COOPER B-LINE
SNAP N' SHIELD PIPE SADDLE
SECURED TO UNISTRUT. MATCH
COLOR OF INSULATION. (TYP)
1 5/8"x1 5/8" GALVANIZED
UNISTRUT P-1000, 6'-0" MAXIMUM
ON CENTERS, 2'-0" MAXIMUM
FROM ANY ELBOW.
NOTE: FOR OVERHEAD LINES, UNISTRUT HORIZONTAL, TRAPEZE HUNG
BOTTOM OF
STRUCTURE
LOADS MUST BE
HUNG WITHIN 3"
OF PANEL POINTS
THREADED
ROD TYP
TOP BEAM
CLAMP (TYP.)
TOP CHORD OF JOIST
ROOF
PIPING
INSULATION1/2" RETAINING
NUT, UNSISTRUT
P4010T
1/2" CHANNEL
NUT WITH
SPRING,
UNISTRUT P1010
07.07.17
ELECTRICAL CONDUITS
MOUNTED ON UNISTRUT
SECURE UNISTRUT BY BOLTING
BRACKET TO FLOOR ONLY
DO NOT ATTACH
UNISTRUT TO CASE
REFRIGERATED
CASES
BETWEEN REFRIGERATED CASES BETWEEN REFRIGERATED CASE AND WALL
REFER TO UNISTRUT
PIPING SUPPORT DETAIL
REFER TO UNISTRUT
PIPING SUPPORT DETAIL
Wall
SECURE UNISTRUT BY
BOLTING TO WALL STUD
ONLY.UNISTRUT POST BASE P1887.
ANCHOR WITHIN 0'-6" OF
EACH END OF UNISTRUT.
MAXIMUM ANCHOR
SPACING OF UNITSRUT
NOT TO EXCEED 8'.
UP TO 8'-0" POST:
P1000
ELEVATION
SUCTION LINE
.020" THICK PVC JACKET FOR ALL
REFRIGERATION LINES EXTERIOR
TO BUILDING (TYPICAL)
TYPICAL
LIQUID
LINE
PLAN
INSULATION
UNISTRUT
INSULATION
LIQUID
LINE
KLO-SHURE 7-SERIES
STRUT MOUNTED
COUPLING FOR
EXPOSED PIPING.
(TYPICAL OF OPTION 2)
TYPICAL SUCTION LINE
1 5/8"x1 5/8" GALVANIZED
UNISTRUT P-1000, 10'-0"
MAXIMUM ON CENTERS
REFRIGERANT SUCTION
LINES SPACED 8" O.C.
MOUNTED ON UNISTRUT
(TYP)
NOTE: MAINTAIN TIGHT SPACING BETWEEN PIPING
BUTT INSULATION AGIANST PIPE
SUPPORT, AND SEAL INSULATION AT
EDGE OF COUPLING.
(TYPICAL OF OPTION 2)
OPTION 1: HIDDEN PIPING SUPPORT OPTION 2: VISIBLE PIPING SUPPORT
PIPING INSULATION
(BEYOND)
#022 CUSH-A CLAMP
FIRMLY CLAMPED TO PIPE.
(TYPICAL OF OPTION 1)
APPLY EXPANDING FOAM TO
CLAMPS AND COVER WITH
INSULATION IN A CLEAN AND
WORKMAN LIKE MANNER.
(TYPICAL OF OPTION 1)
BOLT
THREADED
ROD (TYP)
TOP BEAM
CLAMP (TYP)
OPTION 1: VERTICAL REFRIGERATION PIPING MOUNTED TO WALL OPTION 2: VERTICAL REFRIGERATION PIPING SUSPENDED VIA HANGERS
1/2" RETAINING
NUT, UNISTRUT
P4010T
SQUARE WASHER,
UNISTRUT P1064
THREADED ROD
REFER TO HORIZONTAL
REFRIGERANT LINE
SUPPORT DETAIL. (TYP)
MAXIMUM 12" BETWEEN
HIGHEST PIPING JOINT AND
HORIZONTAL UNISTRUT.
(TYP)
12"
MAX
REFER TO UNISTRUT
PIPING SUPPORT DETAIL
UNISTRUT POST BASE (TYP)
VERTICAL PIPING SHALL
BE SQUARE WITH
FLOOR. (TYP)
MAXIMUM 12" BETWEEM
LOWEST PIPING JOINT AND
HORIZONTAL UNISTRUT.
(TYP)
12"
MAX
PROVIDE PIPE SUPPORT AT
INTERMEDIATE SUCTION
TRAP IF REQUIRED.
BOLT TO WALL STUD
ONLY
REFER TO LINE RACKING BEHIND
REFRIGERATED CASES DETAIL
OR VERTICAL FACE PIPING
SUPPORT DETAIL.
REDUCE RISER
PIPE SIZE AFTER
BASE TRAP
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
R3
REFRIGERATION
DETAILS
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
NTS5EVAPORATOR COIL CONDENSATE PIPING
NTS2EVAPORATOR FAN/COIL UNIT WITH CONTROL VALVES
NTS6HORIZONTAL REFRIGERANT LINE SUPPORT DETAIL
NTS4PIPE MOUNTING BEHIND REFRIGERATED CASES
NTS3UNISTRUT PIPING SUPPORT DETAIL
NTS1VERTICAL REFRIGERANT LINE SUPPORT
ISSUE BLOCK
NOTE
**NEW VALVE, HEAD FAN OR OIL SEPARATOR
***ADD BAFFLE PLATE TO COMPRESSORS WITH PART NUMBER NOTED
$$CHANGE COMPRESSOR FROM 06DR228 TO 06DR337 WITH NEW CONTACTOR & CCH AS PER ABOVE - RACK MAIN BREAKER FINE AS IS
Rev. Revision: Date By:
Refrigerant conversion from R404A to R448A4 05-31-23 LKW
Changes made per EOR specifications [HUSSMANN]5 4-23-24 AWC
115
-
-
-
170.4
100
R448A
OS4-07FAL
1-1/8"
N/A
Sporlan ORD-4-20
1-1/8"
1-3/8"
Water
12D13B
1-5/8"
1-5/8"
1-1/8"
1-3/8"
1-3/8"
DCR-969/SA-19S
-
A81B-7/8PX1 3/8C
ME19S270
7/8"
1-1/8"
Horizontal
H12x60
172
-23 Suction Group REQ 92.7
-23 Suction Group AVAIL 97.0
N/A
Rack Notes:
Heat Reclaim Receiver
Discharge
Dia. x Length
Lbs @ 80% PD
Horiz / Vert
LiquidGeneral Specifications
Manif Size
Drain Regulator
Master Sol
Drier / Sightglass
Surge Solenoid
Surge Ball Valve
Surge Check Valve
Line Size *
Outside Air Temp.
Rack MCA
"Motors" MCA
Defrost MCA
Total Rej. Heat (MBH)
Condensing Temp
Refrigerant Type
Bypass Regulator
Heat Reclaim Valve
Condenser Return
Condenser Supply
Isol Valve From
Isol. Valve To
Water / Air
Disch. Check Valve Spun
Oil Separator
Disch. Regulator
Manifold Size
*From Receiver
Subcooled Liquid Temp
-150
-129.0
-139.9
MOPD
Connected
MCA
460/60/3
Main Stand By
208/60/3
1) A8-21
1) BTAS-417SV
2-5/8"
-23
-
-
-
-
-23 Suction Group -
Saturated Temp
Filter
Accumulator
Manifold Size
Suction
50%
OE25S290(1)
E3S120
1-1/8"
1-1/8"
1-1/8"
50%
OE25S290(1)
1-1/8"
-
1-1/8"
1-1/8"
-
-
-
-
-
-
10
460/60/3
540
-
1240
15
7
BNQ-D04-A016-4-WNW
11.0
Condenser/Split
Max. Overcur Prot.
FLA
T.D.
Model #
Inverter
Weight
Solenoid
Pump Out Sol.
Isol. Valve From
Check Valve From
Isol. Valve To
FPI
VOLT
RPM
15.0/175006ER75060A 43.0 33.9/150.0 4045A 8 1YES YES FV1 1/2190E5S130
10.0/175006DR337 34.7 19.9/114.0 2530A 10 NOYES YES FV 1 190E5S130
6.5/175006DR7250DA367A 19.3 14.1/80.0 2520A 12 1YES YES FV 1/2 190E5S130
-23 Suction Designed @ -23/115 **************************************************************
EXISTING
06DA660104
06DA660104
PS315SLRWD LTC / WP #3
HP/RPMMBTUHCompressor
Model No:
RLA/LRA ContCB Wire UNLHFCCH
DeSuper Heat
Y1037ValveBaffle Plate
-23 Suction Group Loads MBTUH 92.7 **************************************************************************************************************************************************************************************************************************
LTC9
LTC8
LTC7
LTC6
LTC5
LTC4
LTC3
LTC2
LTC1
Application
Heat Dist
NozValve
Expansion
Exchr.ModelNo
Sys Defrost
Volts/∅Amps
Fans
Amps Volts/∅DEF°F
Evap
MBTUH
Branch
Riser Bran.Main
Liquid
SuctionLiquid
Refrigeration Valves
length
Est.
Riser
Trunk
Horiz
Trunk
Suction
Branch
Horiz
Wal*Mart 176-2005 Supercenter #3705
Yelm, Washington
36398
Jeff Frasier 08/17/06 See Remote Manifold
LTC / WP #3
460/60/3
CONYERS, GEORGIA 30013
(770)285-3100 Fax: (770)285-3076
709 SIGMAN ROAD
Job #:
Quote #:
Store / Cust:
Location:
Prepared By: Date: Field Connection: Rack Voltage:
®
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.R4
REFRIGERATION
SUBMITTALS
HEI
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
HEI
ISSUE BLOCK
NO
T
E
:
F
O
R
I
N
F
O
R
M
A
T
I
O
N
O
N
L
Y
TH
E
I
N
F
O
R
M
A
T
I
O
N
O
N
T
H
I
S
S
H
E
E
T
I
S
S
U
P
P
L
I
E
D
B
Y
T
H
E
OE
M
,
A
N
D
D
E
S
C
R
I
B
E
S
T
H
E
C
O
M
P
R
E
S
S
O
R
S
,
R
A
C
K
S
,
A
N
D
HO
U
S
E
S
.
T
H
E
E
Q
U
I
P
M
E
N
T
W
I
L
L
B
E
P
U
R
C
H
A
S
E
D
B
Y
OW
N
E
R
,
A
N
D
I
S
T
O
B
E
I
N
S
T
A
L
L
E
D
B
Y
T
H
E
R
E
F
R
I
G
E
R
A
T
I
O
N
CO
N
T
R
A
C
T
O
R
;
R
E
F
E
R
T
O
S
P
E
C
I
F
I
C
A
T
I
O
N
S
.
T
H
E
IN
F
O
R
M
A
T
I
O
N
O
N
T
H
I
S
S
H
E
E
T
I
S
S
U
B
J
E
C
T
T
O
C
H
A
N
G
E
.
CO
N
T
R
A
C
T
O
R
S
H
A
L
L
O
B
T
A
I
N
A
N
D
V
E
R
I
F
Y
A
L
L
A
S
-BU
I
L
T
IN
F
O
R
M
A
T
I
O
N
F
R
O
M
O
E
M
B
E
F
O
R
E
I
N
S
T
A
L
L
A
T
I
O
N
.
NOTE
EQUIPMENT
LOCATION A
SEISMIC CABLE BRACE WITH HOOK
ONLY SHOWN IN TWO DIRECTIONS
FOR CLARITY. ADDITIONAL
BRACING IS REQUIRED AS SHOWN
IN PLAN VIEW BELOW.
45.00°
ALLTHREAD
ROD TYP
SEISMIC CABLE
BRACE TYP
SEISMIC JOIST
ATTACHMENT
HARDWARE TYP
45°±15°
AIRCRAFT CABLE BY
SEISMIC RESTRAINT
MANUFACTURER
MAXIMUM 4 IN.
ALLTHREAD ROD
SEISMIC
SOLID
BRACE
STEEL BRACE
SEISMIC JOIST
ATTACHMENT
HARDWARE
45°±15°
PIPE CLAMP MAY BE
ROTATED TO GAIN ACCESS
TO STRUCTURE ABOVE
MAXIMUM 4"
ALLTHREAD ROD
SEISMIC CABLE
BRACE HOOK
TYP
PIPE CLAMP MAY BE ROTATED TO GAIN ACCESS
TO STRUCTURE ABOVE
SEISMIC CABLE
BRACE TYP
45°±15°
SEISMIC JOIST
ATTACHMENT
HARDWARE TYP
AIRCRAFT CABLE
BY SEISMIC
RESTRAINT
MANUFACTURER
SEISMIC STEEL BRACE ONLY SHOWN IN
TRANSVERSE DIRECTION FOR CLARITY.
ADDITIONAL BRACING IS REQUIRED AS
SHOWN IN PLAN VIEW BELOW.
TRAPEZE SUPPORT
SEISMIC SOLID
BRACE TYP
PIPE CLAMP
OR U-BOLT
SEISMIC JOIST
ATTACHMEN
HARDWARE
STEEL BRACE
45°±15°
ALLTHREAD ROD
SEISMIC CABLE BRACE WITH HOOK
ATTACHMENT ONLY SHOWN IN
TRANSVERSE DIRECTION FOR CLARITY.
ADDITIONAL BRACING IS REQUIRED AS
SHOWN IN PLAN VIEW BELOW.
TRAPEZE SUPPORT
PIPE CLAMP
OR U-BOLT
ALLTHREAD
ROD TYP
SEISMIC CABLE
BRACE TYP
SEISMIC JOIST
ATTACHMENT
HARDWARE TYP
SEISMIC CABLE
BRACE HOOK TYP
45°±15°
AIRCRAFT CABLE BY
SEISMIC RESTRAINT
MANUFACTURER
TRAPEZE SUPPORT
SEISMIC SOLID
BRACE TYP
PIPE CLAMP
OR U-BOLT
SEISMIC JOIST
ATTACHMEN
HARDWARE
STEEL BRACE
45°±15°
ALLTHREAD ROD
TRAPEZE SUPPORT
PIPE CLAMP
OR U-BOLT
ALLTHREAD
ROD TYP
SEISMIC CABLE
BRACE TYP
SEISMIC JOIST
ATTACHMENT
HARDWARE TYP
SEISMIC CABLE
BRACE HOOK TYP
45°±15°
AIRCRAFT CABLE BY
SEISMIC RESTRAINT
MANUFACTURER
SEISMIC JOIST
ATTACHMENT
HARDWARE
SEISMIC
SOLID BRACE
STEEL BRACE
45°±15°
ALLTHREAD ROD
PIPE HANGER
ALLTHREAD ROD
SEISMIC CABLE
BRACE TYP
SEISMIC CABLE BRACE HOOK
TYP
PIPE HANGER
AIRCRAFT CABLE BY
SEISMIC RESTRAINT
MANUFACTURER
SEISMIC JOIST
ATTACHMENT
HARDWARE TYP
45°±15°
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
NOT FOR
CONSTRUCTION
SR1
SEISMIC
RESTRAINT
WMK
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
EJM
THE MECHANICAL, ELECTRICAL, AND REFRIGERATION SYSTEMS
FOR THIS PROJECT SHALL BE SEISMICALLY RESTRAINED. THIS
SHEET DEPICTS SCHEMATIC INSTALLATION DETAILS AND IS FOR
INFORMATIONAL PURPOSES ONLY. SPECIFIC INSTALLATION
INFORMATION REGARDING SEISMIC RESTRAINT SHALL BE
OBTAINED FROM THE SEISMIC RESTRAINT MANUFACTURER.
REFER TO THE SPECIFICATIONS FOR FURTHER INFORMATION.
NTS9
ALL-DIRECTIONAL SEISMIC CABLE
BRACE FOR SUSPENDED EQUIPMENT
NTS8
LONGITUDINAL SEISMIC SOLID BRACE
FOR CLEVIS SUPPORTED PIPE/CONDUIT
NTS7
LONGITUDINAL SEISMIC CABLE BRACE
FOR CLEVIS SUPPORTED PIPE/CONDUIT
NTS6
ALL-DIRECTIONAL SEISMIC SOLID BRACE
FOR TRAPEZE SUPPORTED PIPE/CONDUIT
NTS5
ALL-DIRECTIONAL SEISMIC CABLE BRACE
FOR TRAPEZE SUPPORTED PIPE/CONDUIT
NTS4
TRANSVERSE SEISMIC SOLID BRACE
FOR TRAPEZE SUPPORTED PIPE/CONDUIT
NTS3
TRANSVERSE SEISMIC CABLE BRACE
FOR TRAPEZE SUPPORTED PIPE/CONDUIT
NTS2
TRANSVERSE SEISMIC SOLID BRACE
FOR CLEVIS SUPPORTED PIPE/CONDUIT
NTS1
TRANSVERSE SEISMIC CABLE BRACE
FOR CLEVIS SUPPORTED PIPE/CONDUIT
ISSUE BLOCK
NOTE
E
E
E
E
EE
C
J
1
H
J
ED
CF
16.725
C-1
H4B1-37,39,41
16.530
24
16.780A
16.145
22(CF)
(ED)33
PROVIDE CEILING MOUNTED MANUAL SWITCH 'HUBBELL' CLASS
HBLDS3 OR 'EATON' CLASS AHDS30, IF OVER 30 AMPS PROVIDE
'HUBBELL' CLASS HBLDS6 OR 'EATON' AHDS60, WITH NEMA 4
WATERTIGHT NON-METALLIC ENCLOSURE FOR CONNECTION OF
EVAPORATOR COIL FANS (CF) AND/OR ELECTRIC DEFROST (ED),
(WHERE SHOWN ON DRAWINGS). PROVIDE PLACARD ON
CEILING DETAILING PURPOSE OF EACH MANUAL SWITCH AND
THE ELECTRICAL SOURCE (PANEL AND CIRCUIT NUMBER).
NOTE: DO NOT LOCATE WP JUNCTION BOX DIRECTLY IN FRONT OF DISCHARGE FAN, OFFSET TO SIDE.
TYPICAL COIL
EMT CONDUIT AND WIRING TO NEXT
COIL POWER JUNCTION BOX ON SAME
SYSTEM WHEN MULTIPLE COILS ARE IN
SAME COOLER/FREEZER BOX. POWER
CONDUIT AND WIRING SAME SIZE AND
QUANTITY AS WIRING TO PANEL.
1" EMT CONDUIT
PENETRATION SEALED
WITH SILICONE SEALANT.
NOTE: TAP DEFROST CIRCUIT IN
JUNCTION BOX WITH #10 AWG FOR
CONNECTION TO UNIT. MAXIMUM
LENGTH OF TAP CONDUCTOR 18"
CONDULET AT CEILING PENETRATION
FILLED WITH SILICONE
COIL FAN/DEFROST POWER EMT CONDUIT
AND WIRING TO DESIGNATED PANEL VIA
WALK-IN FAN/DEFROST CONTROL DEVICE.
FINAL CONNECTION BY RC.
COOLER/FREEZER BOX CEILING
CEILING MOUNTED WP JUNCTION BOX WITH THREADED HUBS
AND GASKETED COVERPLATE. SEAL TOP OF JUNCTION BOX
TO COOLER/FREEZER CEILING WITH SILICONE SEALANT.
1" LIQUID-TIGHT FLEXIBLE METAL CONDUIT
TO KNOCKOUT ON UNIT. FINAL
CONNECTION TO COIL BY RC.
t
w
12
0
1
t
h
i
r
d
a
v
e
n
u
e
,
s
u
i
t
e
6
0
0
se
a
t
t
l
e
,
w
a
s
h
i
n
g
t
o
n
9
8
1
0
1
20
6
.
4
4
8
.
3
3
7
6
h
a
r
g
i
s
.
b
i
z
E
N
G
I
N
E
E
R
S
SHEET:
DRAWN BY:
CHECKED BY:
PROTO CYCLE:
DOCUMENT DATE:
CO
N
S
U
L
T
A
N
T
S
ST
I
P
U
L
A
T
I
O
N
F
O
R
R
E
U
S
E
PR
O
T
O
:
JO
B
N
U
M
B
E
R
:
TH
I
S
D
R
A
W
I
N
G
W
A
S
P
R
E
P
A
R
E
D
F
O
R
US
E
O
N
A
S
P
E
C
I
F
I
C
S
I
T
E
A
T
:
CO
N
T
E
M
P
O
R
A
N
E
O
U
S
L
Y
W
I
T
H
I
T
S
I
S
S
U
E
DA
T
E
O
N
A
N
D
I
T
I
S
N
O
T
SU
I
T
A
B
L
E
F
O
R
U
S
E
O
N
A
D
I
F
F
E
R
E
N
T
PR
O
J
E
C
T
S
I
T
E
O
R
A
T
A
L
A
T
E
R
T
I
M
E
.
U
S
E
OF
T
H
I
S
D
R
A
W
I
N
G
F
O
R
R
E
F
E
R
E
N
C
E
O
R
EX
A
M
P
L
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
RE
Q
U
I
R
E
S
T
H
E
S
E
R
V
I
C
E
S
O
F
P
R
O
P
E
R
L
Y
LI
C
E
N
S
E
D
A
R
C
H
I
T
E
C
T
S
A
N
D
E
N
G
I
N
E
E
R
S
.
RE
P
R
O
D
U
C
T
I
O
N
O
F
T
H
I
S
D
R
A
W
I
N
G
F
O
R
RE
U
S
E
O
N
A
N
O
T
H
E
R
P
R
O
J
E
C
T
I
S
N
O
T
AU
T
H
O
R
I
Z
E
D
A
N
D
M
A
Y
B
E
C
O
N
T
R
A
R
Y
T
O
TH
E
L
A
W
.
EXISTING CONDITIONS WERE TAKEN FROM
ORIGINAL DRAWINGS AND MAY NOT REFLECT
EXACT "AS-BUILT" CONDITIONS. CONTRACTOR
SHALL FIELD VERIFY ALL EXISTING CONDITIONS
PRIOR TO SUBMITTING FINAL BIDS. CONTRACTOR
SHALL CAREFULLY COORDINATE NEW WORK AND
DEMOLITION WITH ALL OTHER DISCIPLINES AND
EXISTING CONDITIONS.
EACH SUBCONTRACTOR IS RESPONSIBLE FOR HAVING
A THOROUGH KNOWLEDGE OF ALL DRAWINGS AND
SPECIFICATIONS IN THEIR RELATED FIELD. THE FAILURE
TO ACQUAINT THEMSELF WITH THIS KNOWLEDGE DOES
NOT RELIEVE THE RESPONSIBILITY OF PERFORMING
THE WORK PROPERLY. NO ADDITIONAL
COMPENSATION SHALL BE ALLOWED BECAUSE OF
CONDITIONS THAT OCCUR DUE TO FAILURE TO
FAMILIARIZE WORKERS WITH THIS KNOWLEDGE.RE1
REFRIGERATION
ELECTRICAL
PLAN
AT
YE
L
M
,
W
A
24
-
6
X
1
.
2
3
YE
L
M
,
W
A
04
/
2
5
/
2
4
04/25/24
ST
O
R
E
N
O
:
0
3
7
0
5
-
10
0
3
CA
P
-
X
03/29/24
RS
ISSUE BLOCK
1/8" = 1'-0" 1 REFRIGERATION ELECTRICAL PLAN
12" = 1'-0" 2 EVAPORATOR COIL WIRING
1. COORDINATE ALL WORK WITH REFRIGERATION
CONTRACTOR (R.C.) PRIOR TO INSTALLATION.
2. REFRIGERATED CASES: E.C. SHALL PROVIDE CONDUIT
AND WIRE FOR REFRIGERATED CASE FANS, LIGHTS
AND ANTI-SWEAT HEATERS, AND (IF APPLICABLE)
ELECTRICAL DEFROST. PROVIDE ADEQUATE
CONDUCTOR LENGTH TO ALLOW TERMINATION.
NEATLY BUNDLE CIRCUITS AND CLEARLY TAG AND
LABEL EACH CIRCUIT WITH BRANCH CIRCUIT
DESIGNATION AND REFRIGERATION SYSTEM NUMBER
FOR FINAL TERMINATION AT CASE BY R.C. REF CASE
CONNECTION WIRING DETAIL.
3. IF NEW CASES ARE PROVIDED WITH A FACTORY
INSTALLED TERMINAL STRIP AND JUMPERS FOR
CONNECTION TO A SINGLE CIRCUIT FOR 120V CASE
LOADS. RC SHALL REMOVE FACTORY INSTALLED
JUMPERS AS REQUIRED TO UTILIZE EXISTING
SEPARATE 120V FAN/LIGHT/ANTI-SWEAT CIRCUITS AS
INDICATED ON PLANS AND/OR PANELBOARD
SCHEDULES. ANY EXISTING ANTI-SWEAT CONTROL
(SWEATMISER) SHALL BE BY-PASSED. CASES UTILIZING
ELECTRICAL DEFROST WILL BE PROVIDED WITH
SEPARATE 208V TERMINATIONS AT THE TERMINAL
STRIP FOR CONNECTION TO THE 208V ELECTRIC
DEFROST CIRCUIT. RC SHALL MAKE FINAL
TERMINATIONS OF 120V AND 208V POWER CIRCUIT(S)
AT CASE TERMINAL STRIP. REFER TO CASE
CONNECTION SCHEMATIC ON REFRIGERATION
SHEETS.
4. WALK-IN UNITS: PROVIDE CONDUIT AND WIRE FOR
EVAPORATOR COIL FANS (CF) AND (IF APPLICABLE)
ELECTRIC DEFROST (ED). PROVIDE ADEQUATE
CONDUCTOR LENGTH TO ALLOW TERMINATION.
NEATLY BUNDLE CIRCUITS AND CLEARLY TAG AND
LABEL EACH CIRCUIT WITH BRANCH CIRCUIT
DESIGNATION AND REFRIGERATION SYSTEM NUMBER
FOR FINAL TERMINATION AT COIL BY R.C. REF
EVAPORATOR COIL WIRING DETAIL.
5. ROUTE REFRIGERATED CASE AND WALK-IN UNIT COIL
FAN, LIGHTS, ANTI-SWEAT AND DEFROST BRANCH
CIRCUITS TO WIREWAYS PROVIDED AT
REFRIGERATION EQUIPMENT AND/OR PANELBOARDS
AS REQUIRED.
6. REFRIGERATED CASE WIRING COMPARTMENT
REPRESENTED ON DRAWING BY JUNCTION BOX.
7. KEEP PENETRATIONS THROUGH WALK-IN UNITS
TO A MINIMUM. ROUTE ALL CONDUITS SERVING
FREEZERS AND COOLERS ON INSIDE OF BOX.
8. ALL CONDUITS INSTALLED ON TOP OF WALK-IN UNITS
SHALL BE A MINIMUM OF 6" FROM ANY EDGE TO ALLOW
SPACE FOR EDGE PROTECTION NETTING. DO NOT
ROUTE CONDUITS ABOVE THE CEILING GRID ACCESS
UNLESS CONDUITS ARE INSTALLED IN JOIST SPACE,
REF ARCH.
9. UNDERSLAB CIRCUITS SHALL NOT BE ROUTED UNDER
WALK-IN FREEZERS AND SHALL BE ROUTED ABOVE
REFRIGERANT LINES WHERE THEY CROSS.
10. CIRCUITS FOR REFRIGERATED CASES SERVED BY
UNDERSLAB REFRIGERATION PIPING ARE TO BE
ROUTED UNDERSLAB AND EXTENDED TO THE FIRST
CASE IN EACH SYSTEM. WIRING AND CONDUIT FOR
SLAVE WIRING BETWEEN CASES SHALL BE PROVIDED
BY R.C. REFER TO UNDERSLAB CASE CONNECTION
WIRING DETAIL.
11. ALL UNDERSLAB CONDUITS SHALL BE 3/4" MIN.
12. CIRCUITS FOR REFRIGERATED CASES SERVED BY
OVERHEAD REFRIGERATION PIPING ARE TO BE
ROUTED DOWN FROM STRUCTURE AT THE SAME
LOCATION AS THE REFRIGERATION PIPING AND
EXTENDED TO THE FIRST CASE IN EACH SYSTEM. WIRE
AND CONDUIT FOR SLAVE WIRING BETWEEN CASES
SHALL BE PROVIDED BY THE R.C. REFER TO
OVERHEAD CASE CONNECTION WIRING DETAIL.
13. ON GROUPS OF THREE OR MORE REFRIGERATED
CASES WITH ELECTRIC DEFROST, R.C. SHALL
CONNECT CASES TO CREATE A THREE-PHASE HEATER
CIRCUIT. HEATER LOADS SHALL BE BALANCED
BETWEEN PHASES AS EVENLY AS POSSIBLE. REF
CASE DEFROST WIRING DETAIL.
14. PROVIDE A SEPARATE NEUTRAL FOR EACH NEW
BRANCH CIRCUIT SERVING REFRIGERATED CASES OR
WALK-IN UNITS AS INDICATED ON PLANS.
15. PROVIDE CIRCUIT BREAKER LOCKING DEVICE (LOCK-
OFF FOR MAINTENANCE) ON NEW AND/OR EXISTING
CIRCUIT BREAKERS SERVING REFRIGERATED CASES.
16. REFERENCE ARCHITECTURAL DEMOLITION PLANS FOR
FULL EXTENT OF DEMOLITION WORK REQUIRED.
GENERAL REFRIGERATION
ELECTRICAL NOTES
12.21.18
ALL CONDUCTOR SIZES ARE BASED ON 75 DEG C RATED
TERMINATIONS AND TYP THHN/THWN-2 INSULATION; FOR
TERMINATIONS OR INSULATION TYPES RATED LESS THAN
75 DEG C. MODIFY SIZES ACCORDING TO NFPA 70.
CIRCUIT SCHEDULE
XXXX
INDICATE WIRE SIZE FOR CIRCUIT HERE.
AS REQUIRED FOR CASE/COIL FAN AND
DEFROST FED FROM RACK CONTROLLERS.
KEYNOTES
16.145 CONNECT CIRCUIT(S) TO EXISTING BRANCH
CIRCUITRY. MINIMUM WIRE SIZE AND
PANELBOARD CIRCUIT ARE NOTED. VERIFY SIZE,
RATING AND CONDITION OF EXISTING BRANCH
CIRCUIT CONDUIT AND WIRE PRIOR TO USE TO
ENSURE THAT THEY MEET REQUIRED SIZE, AND
ALL U.L. RATINGS AND REPLACE AS REQUIRED.
16.530 AIR DOOR AND CONTROL PANEL: PROVIDE
POWER FROM DISCONNECT TO AIR DOOR
CONTROL PANEL. PROVIDE AND INSTALL ALL
INTERCONNECT WIRING BETWEEN THE
CONTROL PANEL, AIR CURTAIN AND DOOR
INTERLOCK SWITCH PER MANUFACTURER’S
INSTRUCTIONS.
16.725 ROUTE COIL FAN (CF) AND/OR ELECTRIC
DEFROST (ED) CIRCUITS FROM THE BAS
CONTROLLER. FINAL TERMINATIONS AT
ENCLOSURE BY R.C.
16.780A E.C. SHALL REMOVE EXISTING CONTACTOR IN
RACK CABINET AND CONNECT CIRCUITRY
DIRECTLY TO CIRCUIT OVERCURRENT
PROTECTION DEVICE. REFRIGERATION SYSTEM
EVAPORATOR FAN/DEFROST CIRCUITS SHALL BE
CONTROLLED BY FACTORY INSTALLED
CONTROLS IN NEW CASES OR BY FIELD
INSTALLED CONTROLS AT WALK-INS. IF
REQUIRED, E.C. SHALL INSTALL NEW VENDOR
FURNISHED OVERCURRENT PROTECTION
DEVICE FOR REFRIGERATION SYSTEM
EVAPORATOR FAN/DEFROST CIRCUIT. PROVIDE
A NEW NEMA 1 ENCLOSURE FOR FAN/DEFROST
CIRCUIT OVERCURRENT PROTECTION DEVICE, IF
NEEDED. MOUNT NEMA 1 ENCLOSURE AS CLOSE
AS POSSIBLE TO EXISTING RACK CABINET.
REFER TO REFRIGERATION LEGEND(S).
FEEDER OR GROUND SIZE
ALL CONDUIT AND CONDUCTOR SIZES ARE BASED ON EMT WITH 40%
FILL, 75ºC RATED TERMINATIONS AND TYPE THHN/THWN-2 INSULATION.
FOR NON-EMT CONDUIT OR TERMINATIONS OR INSULATION TYPES
RATED LESS THAN 75ºC, MODIFY SIZES ACCORDING TO NEC.
FEEDER SCHEDULE
22 (2)#12, (1)#12 G, 1/2" C
24 (4)#12, (1)#12 G, 1/2" C
33 (3)#10, (1)#10 G, 1/2” C
4/23/24