Mt.Sunrise 2 Revised Preliminary Punchlist for Sound BuiltHomes
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
March 9, 2009
Sound Built Homes
12915 Canyon Road East
Puyallup, WA 98328
RE: Mountain Sunrise Phase 2 – Pre Punchlist
City of Yelm Project No. SUB-02-8329-YL
Dear Mr. Cline:
Our department has conducted a brief drive thru on the above mentioned project. The following items were discovered during this brief drive thru, these items must be completed first,
before we call for a final walk thru and inspection of the project.
Clean up entire project of all garbage, debris and left over materials and plastic strung out from material piles.
Remove Rock and concrete piles. This is a hazardous condition along with being a safety and liability issue.
Clean up storm ponds and cut down weeds.
Replace dead trees around storm pond 7 to 10 trees are dead.
Remove street signs post near intersection of 91st and Wilkensen Rd.
Relocate utility box in driveway.
Remove construction lot signs.
Fix and lower exposed irrigation line on pond access road.
Remove metal fence stakes next to sidewalk on 91st.
Please complete 100% of the above items before contacting our department for a final walk thru and inspection. If you have any questions or comments, please call me at (360) 458-8423
and I will be happy to further assist you.
Respectfully
City of Yelm Community Development
Steve Harrington
Engineering / Civil Inspector