Loading...
09 Habitat for Humanity Yelm - Infiltration Verification Testing Memo Tumwater, WA SageGeotechnical.com March 4, 2025 Transmitted via email to: ben@spshabitat.org South Puget Sound Habitat for Humanity P.O. Box 2225 Olympia, WA 98507 Attn: Ben Fransua, Director of Construction Re: Verification Testing Services Yelm Planned Residential Development Yelm, Washington Sage Project No. 052002 Dear Mr. Fransua: At the request of South Puget Sound Habitat for Humanity (SPS Habitat, project owner), Sage Geotechnical, LLC (Sage) completed verification testing in support of the Yelm Planned Residential Development project. The results of the verification testing are summarized herein. PROJECT UNDERSTANDING SPS Habitat is developing a 2.3-acre parcel located at 407 Longmire Street Northwest in Yelm, Washington (site). The City of Yelm has required verification testing of two existing stormwater infiltration ponds. The approximate locations of the ponds are shown on Attachment 1. VERIFICATION TESTING The stormwater pond in the western half of the site has a 300-square-foot (sf) base and 3 horizontal to 1 vertical side slopes partially vegetated with grass. The stormwater pond in the eastern half of the site has a 200-sf base with gentle slopes covered in mulch. On February 27, 2025, Sage completed verification tests of the two stormwater ponds. Testing was completed in accordance with the U.S. Environmental Protection Agency’s (EPA) falling head percolation test procedure. The test procedure and locations were selected by LDC, Inc. (project civil engineer). The verification tests included multiple trials; during each trial, 6 inches of water was infiltrated into the base of the pond. The trials were repeated until they yielded similar infiltration rates. Yelm Planned Residential Development March 4, 2025 2 SageGeotechnical.com March 4, 2025 Infiltration rates were calculated in accordance with the EPA’s falling head percolation test procedure. This procedure does not include correction factors or factors of safety. Sage calculated a field infiltration rate of 15.8 inches per hour for the western pond and 9.6 inches per hour for the eastern pond. CLOSING We trust that this letter provides you with the information needed to proceed with the project. If you have questions or comments, please contact the undersigned at lancel@sagegeotechnical.com. SAGE GEOTECHNICAL, LLC Lance Levine, PE Senior Geotechnical Engineer LGL/MCS/DCS [HTTPS://SAGEGEOTECHNICAL.SHAREPOINT.COM/SITES/SAGEGEOTECHNICAL/SHARED DOCUMENTS/PROJECTS/052 SOUTH PUGET SOUND HABITAT FOR HUMANITY/002 YELM PLANNED RESIDENTIAL DEVELOPMENT/R/YELM PRD VERIFICATION TESTING LETTER 3.4.2025.DOCX] Attachments: Attachment 1. Plan Sheet DR-01 ATTACHMENT 1 Plan Sheet DR-01 ROAD A DRYWELL TABLE 12/18/2023 Expires Approved for Construction Civil Review Engineer Reza R. Roukerd 7/23/2023 Infil-1 Infil-2