Letter to PacWest
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
August 29, 2003
Matthew Ruettgers, PLS
PacWest Engineering
5009 Pacific Highway East, Unit 9-0
Fife, WA 98424
Dear Matthew:
This letter is a follow-up to the meeting on Wednesday the 14th of March regarding Newman’s Addition and my letter dated February 28.
After we had reviewed each of the concerns raised by the Department in the preliminary review of your application for a Planned Residential Development, it was determined that PacWest
Engineering would be preparing a revised site plan and a special report pursuant to Section 14.08.070 (A) YMC. While the application will technically be on hold until a revised site
plan is submitted, the Community Development Department will continue to review the expanded Environmental Checklist, including the Traffic Impact Analysis, in order to keep the permit
review process moving and to avoid delay’s upon resubmission of the site plan and special reports.
If you have any questions while you are revising the application materials, please don’t hesitate to contact the Department.
Sincerely,
Grant Beck
Community Development Department