Review Memo 2 Planning
CIVIL PLAN ROUTING SHEET
City of Yelm
Community Development Department
20100177 – Salmon Run Apartments June 20, 2011
Project Name Date
Plans Routed To: Prev. Response
Department: No. of Plans Reports Comments Letter
( Public Works
Water __
Sewer __
Planning X X_ X
Other __
Type of Distribution:
First Review
Second Review
Third Review
Approved for Construction
As-Builts
Fourth Review
Redlines need to be submitted back to Karen Bennett / CDD by: June 28, 2011
Please remember this review is REDLINE comments. If you have any question concerning this review process please give me a call at 360-458-3835.
(Please note that this project will be reviewed on June 29, 2011 at the SPR Meeting, in the City Hall Conference Room.
NEW RESOURCES:
Our review documents will now be available for viewing on YelmWeb. Projects will be viewed under Plan Review. If you have any question or have issues viewing documents, please give
me a call.