20100095 COY Cmt Ltr 05262011City of Yelm Community Development Department 105 Yelm Avenue West Yelm, WA 98597 May 26, 2011 Andy Markos, AICP Senior Planner Puget Sound Energy, Inc. 3130 South 38th St Tacoma, WA 98409 RE: PSE Yelm Switching Station - 20100095 Review No. 3 of Civil Construction Documents The City of Yelm has completed the third review of the civil plans for PSE Yelm Switching Station. We have signed the grading portion of the plans, this constitutes your clearing and grading permit. Please provide the City with five (5) copies of the signed grading plans. We have reviewed the remainder of the plans for compliance with the City of Yelm Development Guidelines, the DOE Stormwater Manual and general standards of civil engineering practice. The enclosed red lines need to be addressed before the plans may be approved for construction. In addition to redline plans, there are comments from our peer review engineer (letter attached) that must still be addressed. Please revise your plans to address the enclosed redlines and engineer comments. When the project is resubmitted you will need to submit 5 sets of plans and 2 sets of reports, plus send back original red lines. The project engineer should include a written response with the resubmittal, indicating how all the redlines and review comments above have been addressed or responded to. This will significantly expedite our review of the project. If you have any additional questions or comments please do not hesitate to call or contact me at karenb@ci.yelm.wa. us. Sincerely, ~~~~=~ ~~ Tami Merriman Associate Planner .,... SHEA-CARR-~1EWELL ENGINEERING AND PLANNING SERVICES May 16, 2011 Mrs. Karen T. Bennett Administrative Support City of Yelm Community Development Department 105 Yelm Avenue West Yelm, WA 98597 Re: Peer Review #2 PSE Yelm Switching Station Dear Karen: As you requested, Shea Carr Jewell has reviewed the resubmittal of the PSE Yelm Switching Station project, which addresses the comments from our first peer review. The review documents included: • Civil engineering plans signed April 20, 2011 • Stormwater Drainage and Erosion Control Plan Report dated April 2011 Our comments are as follows: Drainage Report 1. Appendix C-The StormShed modeling for the open infiltration pond receiving drainage from the driveways indicates an infiltration vault with a 40% void ratio. This is a very conservative analysis of the actual design. Because this is an open pond and not an infiltration trench, this could be modeled as a trapezoidal pond with no void ratio. This modification should help with the following comment. 2. Appendix C -Per Section III-3.4 of the 1992 DOE Manual, infiltration BMPs are recommended to have one foot of freeboard. Typically, 0.5 feet of minimum freeboard has been allowed. The current design of the infiltration trench for the SPCC area and the infiltration pond for the driveways does not provide for any freeboard. Please revise the design of these systems to include a minimum of 0.5 feet of freeboard. A redesign for the driveway pond is likely not required given comment #1. 3. Appendix C -Per Section III-3.6.3 of the 1992 DOE Manual, please demonstrate a drawdown time of 24 hours for the 10-year storm and 48 hours for the 100-year storm for all infiltration facilities. 4. Appendix C -The side slopes for the linear infiltration pond adjacent to the truck turn-around road are too steep. Per Figure III-3.7 of the 1992 DOE Manual, the maximum allowed side slope is 3:1. Currently 2:1 side slopes are proposed. 2102H Carriage Drive 5W -Olympia, WA 98502 Office: 360352.1465 I Fax: 360352.1509 I Email info(alsheacarrjewelLcom ~ wwwsheacarrjewell com ~ .~ Karen Bennett May 16, 2011 Page 2 of 2 Construction Plans: Drawing D-152331 of 5: 5. The Conditions of Approval of this project {Condition #2) waive construction of frontage improvements but do require dedication of any associated ROW. Therefore, an 8-foot dedication of right-of-way is a requirement of this project (potentially more will be required at the area of the intersection). No improvements related to the PSE Switching Station project should be placed within this area. Drawing D-15233 2 of 5: 6. Although shown in the road detail, there is no mention of the infiltration ponds adjacent to the driveway on this plan. As this is the drainage plan, it should be noted to ensure it is not overlooked. Drawing D-15233 4 of 5: 7. Update detail #4 to show a minimum 3:1 side slope in the proposed infiltration ponds. Drawing D-15236 2 of 4: 8. The water meter note has been changed to indicate that the water meter shall be purchased from the City, but it does not indicate that it should also be installed by the City. Please update. Should you have any questions or comments, please contact me at {360) 352-1465 at your earliest convenience. Sincerely, Shea Carr Jewell Amy iW. Piea`si;_P~ Associate Principal N:\Projects\0605 City of Yelm\605-OS Civil Plan Reviews\Phase 26 - Yelm Substation\Correspondence\L-2011 0516 Bennett 2nd review comment Itr.doc