20110166 Amended Proj Rev Memo 08102011City of Yelm
Community Development Department
105 Yelm Ave W
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: SPRC
From: Tami Merriman, Associate Planner
Date: August 10, 2011
Re: 20110166 – Amended Project Review Schedule for Yelm Daycare Center
Attached is the LAND USE application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant,
please let me know as soon as possible. The following is the tentative review schedule for the project.
August 10, 2011 – Notice of Application distributed – begin 15 day comment period.
August 31, 2011 - SPRC Project Review. Department comments/conditions of approval for staff report.
September 7, 2011 - Complete Staff report for public hearing and contact Hearing Examiner to schedule hearing.
Public Hearing Notice to Paper/Mailing/Post site. (Publish 10 days prior to hearing)
Public Hearing in front of Hearing Examiner
Hearing Examiner approval completed.