Review Memo 1 WaterI OF THFp~~
4~ 9~
YELM
WASHINGTON
CIVIL PLAN ROUTING SHEET
City of Yelm
Community Development Department
BSP-08-0347-YL Eagle Plaza February 10, 2009
Project Name Date
Plans Routed To: Prey. Response
Department: No. of Plans Reports Comments Letter
^ Public Works
Water - Smitty/John Ivey 1
Sewer
^ Engineering (Steve)
^ Planning (Nisha)
^ Shea Carr Jewell
^ Other
Type of Distribution:
^ First Review ^ Approved for Construction
^ Second Review ^ As-Builts
^ Third Review
^ Fourth Review
Redlines need to be submitted back to Karen Bennett /CDD by: February 24, 2009
Please remember this review is REDLINE comments. If you have any question
concerning this review process please give me a call at 360-458-3835.
Please note that this project will be reviewed on February 24, 2009 at the Project
Plan Review Meeting, 2:00 pm in the City Hall Conference Room.
H:\CDD Projects\BSP Binding Site Plan\20080347 Eagle Plaza\Civil\Construction Plan Review\Review No 1\Department
Routing\Review Memo #1 Water.doc