20050028 Plan Review Notes
October 20, 2004
Tom Jensen
115 N. McCormick
Olympia, WA 98506
Subject: Golden Dragon
Tom,
As we discussed this morning here are the initial comments on the Golden Dragon
Drawings you submitted to me:
1.Drawing need to be signed by a licensed architect unless the project is design
build by you and has a structural stamp
2.Kitchen Details are unclear. Need finished kitchen details and Health Department
Sign Off. Hood suppression may be submitted later, but hood details and required
make up air must be part of the submitted drawings
3.Need plumbing riser drawings
4.Need hardware schedule for egress review
5.Need to show how 5A requirement for a one hour exterior wall and roof are met
6.Public restrooms need to be dimensioned to verify ADA requirements. A
separate detail should show counter, fixture and accessory heights.
7.Cooler door in the open position does not allow the required unobstructed space
of the egress path
8.Mechanical access must be either 22x30 inches or larger to accommodate the
removal of the largest piece of the furnace system. Verify.
9.Need energy and lighting calculations.
10.Need completed civil drawings for the final approval of drawings to verify egress
outside of the building.
Thanks, I will continue my review of the drawings, but do not anticipate many other
comments after these have been completed by you.
Gary