please add the text below to the olympic pipeline civil plan distribution
Follow Up Flag:
Follow up
Flag Status:
Flagged
Categories: Red Category
Please route city staff... does not go out for peer review.
Attached are construction plans for a motor - operated valve project for the Olympic Pipe line.
We met with the representatives and determined that the installation of the valve is for regular maintenance and safety
update. We are not requiring a land use permit. We are reviewing the plans for the improvement to driveway entrance,
site improvements, such as fencing and landscape buffers, as well as continued access to the stormwater facilities on sit.