20130320 – Project Review Schedule for River Run Apartments
Site Plan Review
Attached is the application packet for the above referenced project. After your initial
review of the information submitted, if you need additional information from the applicant, please let me
know as soon as possible. The following is the tentative review schedule for the project.
September 11, 2013 – Notice of Application distributed – begin 15 day comment period.
September 25, 2013 - SPRC Environmental Review. Department comments/mitigation requirements for
Environmental Review.
Environmental Determination issued by Planning Department.
SPRC project review. Department comments/conditions of approval for staff report.