20070404 Rev Memo 3 Sewer 01062010
CIVIL PLAN ROUTING SHEET
City of Yelm
Community Development Department
SPR-07-0404-YL Creek Road Mixed Use – Phase II January 6, 2010
Project Name Date
Plans
Routed To: Prev. Response
Department: No. of Plans Reports Comments Letter
( Public Works
Water __
Sewer Jim D X __
Planning __
Shea
Carr Jewell __
Other __
Type of Distribution:
First Review
Second Review
Third Review
Approved for Construction
As-Builts
Fourth Review
Redlines need to be submitted back to Karen Bennett / CDD by: January 14, 2010
Please remember this review is REDLINE comments. If you have any question concerning
this review process please give me a call at 360-458-3835.
(Please note that this project will be reviewed on January 13, 2010 at the SPR Meeting, 2:00 pm in the City Hall Conference
Room.