Attached is the LAND USE application packet for the above referenced project. After your initial review of the information
submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project.
January 5,
2015 – Notice of Application distributed – begin 15 day comment period.
January 14, 2015 - SPRC Environmental Review. Department comments.
January 21, 2015 – SEPA Determination
February
4, 2015 - SPRC Project Review. Department comments/conditions of approval for staff report.
February 11, 2015 - SPRC Project Review. Department comments/conditions of approval
for staff report.
Department comments, complete Staff report.