Re: 20140303 – Project Review Schedule for Twisted Donuts II
Attached is the LAND USE application packet for the above referenced project. After your initial review of the
information submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project.
January
5, 2015 – Notice of Application distributed – begin 15 day comment period.
January 14, 2015 - SPRC Project Review. Department comments/conditions of approval for staff report.
January
21 - SPRC project review. Complete Staff report.