Tami - 03/30/2016 - 225
OFFICE OF THE HEARING EXAMINER
CITY OF YELM
REPORT AND DECISION
CASE NO.
: SUB-05-0068-YL (part of MPD-05-0067-YL)
APPLICANT
:Tahoma Terra LLC
th
4200 6 Avenue SE, Suite 301
Lacey, WA 98503
SUMMARY OF REQUEST
:
The applicant is preliminary plat approval to allow construction of 89 single family units, on
approximately 20 acres. The applicant has applied for approval of a Conceptual Master
Plan Development of approximately 220 acres, Final Master Plan approval for
approximately 40 acres, and preliminary plat approval of approximately 20 acres. Included
in the Final Master Site Plan is the completion of commercial space and developed open
space.
SUMMARY OF DECISION
:
Request granted, subject to conditions.
PUBLIC HEARING
:
After reviewing Planning and Community Development Staff Report and examining
available information on file with the application, the Examiner conducted a public
hearing on the request as follows:
The hearing was opened on July 11, 2005, at 9:00 a.m.
Parties wishing to testify were sworn in by the Examiner.
The following exhibits were submitted and made a part of the record as follows:
EXHIBIT "1" - Planning and Community Development Staff Report and
Attachments
GRANT BECK appeared, presented the Community Development Department Staff
Report, and testified that this southwest area of Yelm was annexed in 1993 as an MPC.
The City has a blank slat for development with uses consistent with the comprehensive
plan. The MPC has its own zoning code with little direction for the first master plan. The
first subdivision must be consistent with the conceptual and final plan approval.
STEVE CHAMBERLAIN appeared on behalf of the request and testified that they have
developed a conceptual plan for the entire 220 acres, a final plan for the area east of
Thompson Creek, and a preliminary plat of 89 lots. The site previously supported a large
dairy farm and was purchased for the MPC. The site is generally level with rolling pasture
east of the creek. To the west of the creek the topography ascends to a higher plateau
covered with trees. Soils on the site consist of topsoil and sand and gravel which are
conducive to development. The dairy farm ceased operation in 1993 or 1994, but other
cattle have grazed on the site since then. They will use a natural feature design
incorporating the City design guidelines. They anticipate seven to ten years to develop the
entire site. They will locate the commercial area east of the creek and townhouses with
overlook the golf course. They anticipate between 700 and 1,200 dwelling units over the
220 acres. They will collect, treat, and discharge all stormwater drainage into the soil, and
will have a few ponds in the good soil areas. Sanitary sewers will serve the project as well
as a major arterial. The City will provide potable water and sanitary sewer service, and they
will construct parks throughout the development.
JEFF SCHRAMM, traffic engineer, appeared and testified that he has provided traffic
studies for the past ten years and conducted such study for the entire MPC. He evaluated a
conceptual analysis for all phases, and for Phases 1 and 2 east of the creek. They will
provide mitigation for this project in addition to the State and City plans. The entire traffic
analysis and development for the annexation area were considered by the City and the
State. The MDNS sets forth mitigating measures for traffic which includes an approximate
$1 million dollar impact fee in addition to the road improvements. The 89 lot subdivision will
require improvement of Longmire Street to Yelm Avenue to modified collector standards
with shoulders and bike lanes. They will improve the Yelm/Longmire intersection with a
center turn lane. Future development will require an extension of Killion Road as a new
road to serve the development. No development will occur west of the creek until the initial
connection is made. They will also install a new traffic signal and will widen both roads.
These improvements will accommodate Phases 3 through 5. For the balance of the site
they will improve Mosman Avenue and realign it to a four leg intersection which is also
consistent with the City TIP. They will provide access to SR-510 by either Mosman or the
new road connection to the south. All of the improvements are consistent with the City’s
plans and methods of determining mitigation.
STEVE SHANEWISE appeared and testified that he is a wetland scientist and studied the
wetlands on the site. A wetland near the south property line drains north to the creek and
the creek channel is in the wetland. All wetlands meet the definition of Category 2 for which
the ordinance requires a 75 foot wide buffer, as compared with their 100 foot wide buffer.
They will construct ballfields, park, and lawn in the creek bottom, and will remove fill from
the wetlands and will cross the creek with a bridge. Construction will affect .5 to .6 acres of
wetlands. They will restore two to four acres of drained wetlands.
MR. CHAMBERLAIN reappeared and testified that they will utilize purple pipe or recycled
water from the sewer treatment plant for irrigation. While the water is not considered
drinkable, it is treated to that standard.
BOB DROLL, landscape architect, appeared and testified that 80% of his work is in the
park and recreational fields. Larger developments can impact a City. They propose 60
acres of open space and parks and about 25% will be developed into active recreational
areas. The balance will consist of habitat and open space. Neighborhood parks will contain
playground apparatus for elementary children. They will also have activities for adults and
seniors to include over a mile of walking trails consisting of paved, boardwalk, and crushed
rock. They will have pocket parks within subdivisions also. The main park will have two
picnic shelters.
MR. CHAMBERLAIN reappeared and testified that the applicant has 60 years experience in
developing property and in home building. This will be the most unique development in the
City and Quadrant Homes will build all of the residential dwellings. Phase 1 will consist of
89 lots. They will carry the same theme throughout the development starting with the
residences in Phase 1 which will be single family residential exclusively. The primary
access for the subdivision will be from Longer and they will work with adjoining property
owners to minimize the impacts of construction. They will also bring utilities down Longer
and will accommodate storm drainage on site.
JIM STROTT, Quadrant Homes, testified that his company is the largest home builder in
the State and that they offer an entry level product. They have a mix of lots on this site and
buyers can determine the size and quality of the home. They will have competitive pricing.
They anticipate constructing two homes per week to manage the growth. They anticipate
home sizes of 1,800 square feet which will sell for between $150,000 and $175,000 and
3,200 square foot homes which will sell for $300,000 or more.
MR. BECK reappeared and testified that SEPA review has required different conditions for
different phases. They have tied the MDNS measures to the number of trips generated not
to the phases. Police stations in the area are substandard and the applicant will pay a
police facility charge of $310 per unit for replacement of the existing structure. Staff finds
the project consistent with the comprehensive plan and the applicant had to provide more
units to obtain the minimum four dwelling units per acre. The Land Use Element promotes
mixed uses such as townhouses and neighborhood commercials, but not to compete with
the downtown businesses. They will have a range of housing and housing prices. They will
also provide parks and open space, but install the parks before development as they go
along. The dairy farm had water rights and transferred them to the applicant. A condition of
approval requires that development beyond the 89 units have a water transfer. The final
development plan contains fixed development regulations for the phases covered. The
Master Site Plan limits the size of the neighborhood commercial to ensure that it will not
compete with downtown businesses. The pocket parks will be constructed in individual
neighborhoods throughout all phases so that children don’t need to go far from home. The
subdivision conditions are straight forward and staff recommends approval subject to the
mitigating measures and conditions.
MARGARET CLAPP appeared and testified that she is very impressed with the proposal
and served on the Planning Commission during the southwest annexation. This MPC is
what the commission members desired, and it meets all of the tests to include significant
open space. She wants to see the wetland mitigation work and believes the applicant has
done a first class job and will provide all infrastructure.
DIANE D’ACUTI appeared and concurs with Ms. Clapp. She did has transportation
questions as she does not believe one stop light will handle the increased traffic. She also
discussed the setbacks from Thompson Creek and ascertained that the applicant is vested
under the old ordinance which requires less of a buffer. Thompson Creek will not flow
unless someone cleans it out. Adding more water will cause the creek to back up and the
streets to flood.
JAMES ZUKOWSKI appeared, asked questions, and obtained the following answers. The
conceptual plan covers 220 acres and will result in construction of 800 to 1,200 residential
units. The final plan covering the area east of the creek will result in approximately 216
units to include townhomes and commercial. He believes the Mosman extension a problem
due to ownership issues. The critical areas located at the north end of the Thompson
ballfields are still within a 100 foot buffer. He questioned the geotechnical hazard area for
the extension of the boulevard. He questioned how trails would cross the creek and
whether the picnic shelters would be for general citizen use or just for residents of the MPC
and who is in charge.
JEAN HANDLEY appeared and testified that she was at the last Planning Commission
meeting which updated the Critical Areas Ordinance. Now a subcommittee will testify as to
the new regulations. The present regulations are outdated and she is concerned about
retention of trees and the road widening. She questioned the source of funds which the City
will use to build improvements. With the new population growth, Yelm will compete with
other cities for grants. No one has discussed the impact on the fire department, but it will
have a large impact and create a large burden. The fire department may need another
building in addition to the police department. She questioned whether emergency vehicle
access would be a problem for the lots. If an earthquake occurs, the State will not have
any funds for this project. The City should stop the MPC if the State can’t fund the
improvements. She referred to the United States Supreme Court decision in the Mosman
Road issue and requested a condition prohibiting the City from exercising eminent domain.
HENRY DRAGT appeared and testified that he owned and ran the dairy on the site, and
sold the property in December. The sale was a fulfillment of his plans for the site since
1993. The City annexed the parcel in October, 2004, and approved the southwest area for
a conceptual master plan for development to include this parcel. The critical areas study
determined no significant impact. He believes the plan a great benefit for the City.
JENISE MUGLER appeared and testified that she owns the property south of the
development and that the MDNS is out of date. In 1999 the checklist showed the
development plans with more open space along the borders. The townhouses have now
changed to a high density development. The applicant must revisit the plan as the
apartments are shown right on her property line along the south border. The creek goes
through the corner and she desires more open space. Either offset the apartments or
provide a greenbelt. The apartments are part of Phase 2.
ROSALIE SAECKER appeared and testified that she regularly uses Longmire. The
applicant should construct all road improvements to include bike paths and sidewalks along
Longmire. They should provide a bus stop at Yelm Avenue and Longmire. She questioned
how the development will minimize traffic on Berry Valley Road.
GEORGE SWARTZ appeared and testified that he owns the property shown by red line
and that he was left out of the loop. His concern is eminent domain because his parcel is
necessary to extend Mosman Street.
MR. CHAMBERLAIN reappeared and testified that the current code requires a buffer of 75
feet, but they have expanded the buffer to at least 100 feet. The ballfields are outside of the
100 foot buffer. The impact of cattle on the creek is considerably greater than urban
development. Their development will be compatible with the creek. Phase 1 consists of 89
lots. The picnic shelters are primarily for the use of the residents, but others can use them
as well. The homeowner’s association can rent the shelters to outside organizations. Trees
lost on the site will be due to roads and development, but they will not lose that many trees.
The site was logged many years ago, and they will replant trees where they can. The
development will pay for its impacts with the taxes, impact fees, and required mitigation.
They have worked with the City to mitigate impacts on the fire department and police
department. They are looking at an area within the commercial portion of the MPC for the
police department. They do not want to compete with downtown business. They do not
propose a big box store, just neighborhood area uses. Such would prevent residents from
having to go to SR-510 or SR-507. The townhomes can enhance the MPC by providing a
mixed residential use. The townhomes are compatible with the creek and the golf course
and will contain 18 to 20 units. They have no other opportunities for townhomes on Phases
1 and 2. All internal roads will have sidewalks and bike paths. Longmire will be the
preferred route which will keep traffic off of Berry Valley. The timing of construction will
direct traffic to the boulevard, and neither Longmire nor Berry Valley will serve as the main
access. They will regrade the steep areas to balance the site to minimize traffic during the
construction period. They have elevated the trails through the wetlands and across the
creek. Critical areas abut the south side of the site, and the nearest townhouse will be set
back 50 feet from the property line.
MR. BECK reappeared and testified that both the comprehensive plan and GMA require the
applicant to use the best available science. Wetland restoration is a big part of the project.
Impacts on the fire department had a large amount of discussion in the MDNS, but the City
can’t justify the use of impact fees. The issue is the number of firefighters and not the fire
department’s capital facilities. The fire department has no plan to increase capital facilities.
Most of the infrastructure will be located in Thurston Highlands and will be in place for that
development. They could condition the south property line setback. The standards for that
development are in the guidelines. They could codify that requirement which would concern
the non-golf course property. The State does not allow eminent domain for business or
economic purposes. The decision on Mosman is seven to ten years down the road.
MS. MUGLER reappeared and testified that the townhouses should measure 100 feet from
the off-site wetlands.
MS. HANDLEY reappeared and testified that the applicant evaluated the creek in a drought
and did not get a true picture of its flow.
MS. KELLY PETERSON appeared and questioned the impact of 1,200 homes on the water
supply.
MR. BECK testified that the City would have the right to the water, but the depth of
withdrawal is not decided. The City could draw from other aquifers.
MS. NEWBY appeared and testified that she resides on Longmire Street and that trucks
pass 25 feet from her window. A restaurant already exists at the Killion extension. She sees
years of traffic and wants Berry Valley extended.
DARLENE BAKER appeared and testified regarding drinking water wells.
No one spoke further in this matter and so the Examiner took the request under
advisement.
NOTE
: A complete record of this hearing is available in the City of Yelm Community
Development Department
FINDINGS, CONCLUSIONS AND DECISION
:
FINDINGS
:
1. The Hearing Examiner has admitted documentary evidence into the record, viewed
the property, heard testimony, and taken this matter under advisement.
2. The City’s SEPA Responsible Official issued and published a Mitigated
Determination of Nonsignificance on May 24, 2005, based on Section 197-11-158
WAC.
3. A Notice of Public Hearing was mailed to the applicant and parties of record on June
20, 2005. This notice was also posted at City Hall and on the City of Yelm web site
on the same date, and published in the Nisqually Valley News on June 24, 2005.
4. The applicant has a possessory ownership interest in an irregularly shaped, 15 acre
parcel of property abutting the west side of Durant Street, the south side of Berry
Valley Road, and the north side of Longmire Street within the southwest portion of
the City of Yelm. The applicant requests preliminary plat approval to allow
subdivision of the site into 89 single family residential lots with an average lot size of
5,500 square feet.
5. The proposed preliminary plat is Phase 1 of the Tahoma Terra Master Planned
Community (MPC) which contemplates between 800 and 1,200 residential units on
220 acres. Tahoma Terra has received conceptual master plan approval for the
entire 220 acres and final master plan approval for Phases 1 and 2 located east of
Thompson Creek. The preliminary plat is in accordance with the approved final
master plan.
6. The preliminary plat map shows access provided from Longmire Street and Berry
Valley Road. An internal plat road extends between said roads and four internal plat
roads extend to the west property line of Phase 1 and will provide access into Phase
2 upon its development. The site is located within the Low Density Residential (R4-
6) classification of the Tahoma Terra Final Master Plan Development Guidelines.
Said classification authorizes residential single family subdivisions as outright
permitted uses and allows a minimum density of four dwelling units per gross acre
and a maximum density of six dwelling units per gross acre. The applicant proposes
a residential single family subdivision at a density of 5.9 dwelling units per gross
acre. Said classification provides building height, off-street parking, lot access, and
setback requirements which all lots and structures thereon must meet.
7. Chapter 14.12 of the Yelm Municipal Code (YMC) requires new subdivisions to
provide a minimum of 5% of the gross area as usable open space. While the
preliminary plat shows no open space, the Tahoma Terra MPC provides
approximately 60 acres of open space land which includes Thompson Creek and its
associated floodplain and wetland system. The applicant will enhance this area with
park facilities and footpaths. The conceptual and final master plans require a
minimum of one pocket park for every 50 dwelling units, or a combination of pocket
parks with a centrally located larger park serving the subdivisions. Such will ensure
that the plat makes appropriate provision for open spaces, parks and recreation, and
playgrounds.
8. A mitigating measures in the MDNS requires the applicant to enter a school
mitigation agreement with the Yelm School District. Entry of such agreement will
ensure appropriate provision for schools and school grounds.
9. The applicant has elected to use City street standards for all interior, local access,
residential streets within the subdivision. The applicant will construct all streets to
the local access standard which includes two, 11 foot wide travel lanes; two, seven
foot wide parking lanes; concrete, rolled edge curb and gutter; six foot wide planter
strip with street trees 35 feet on center; five foot sidewalk on one side of the street;
and street lighting. The applicant will dedicate all streets to the City upon final plat
approval. As previously found, the subdivision provides for continuation of streets to
adjoining subdivisions. The conceptual plan shows a street grid system and
continuation of all streets throughout future development within the MPC. The
preliminary plat will comply with the City’s Transportation Facility Charge, and will
also construct the traffic improvements required by the MDNS. These measures
include the reconstruction of Longmire Street to a modified collector standard from
the project entry to SR-510. Furthermore, the MDNS requires that prior to approval
th
of any development permit which includes the 90 peak p.m. trip generated from the
project, the applicant must construct a center left turn lane on SR-510 at the
Longmire Street intersection with sufficient storage to serve anticipated traffic
volumes. According to the applicant’s traffic study, Phase 1 will generate 90 p.m.
peak hour trips, and therefore prior to final plat approval, the applicant must
reconstruct Longmire Street and install a center left turn lane. Such improvements
and payments will ensure that the Phase 1 preliminary plat makes appropriate
provision for streets, roads, alleys, and other public ways.
10. The City of Yelm will provide both domestic and fire flow to the site, and the
applicant will decommission any existing water wells pursuant to Department of
Ecology (DOE) standards. The applicant will assign/dedicate water rights
associated with said wells to the City which shall use said water to supply Phase 1.
The applicant will also use reclaimed water from the City’s wastewater treatment
plant for irrigation, decorative fountains, street cleaning, dust control, firefighting,
and other uses with the exception of public consumption. The City will also provide
sanitary sewer service to each lot. The preliminary plat makes appropriate provision
for potable water supplies and sanitary waste.
11. The applicant will design the storm water drainage system to City standards as set
forth in the 1992 Department of Ecology Stormwater Manual. Said standards
requires all development to both treat and control stormwater. The conceptual
design provides both treatment and infiltration and includes low impact development
technologies for stormwater treatment to include rain gardens. The City has
reviewed the conceptual report and finds it appropriate. The plat makes appropriate
provision for drainage ways.
12. The applicant will construct sidewalks on at least one side of internal plat roads and
will provide adequate street lighting to include street lights at internal street
intersections and pedestrian scale lighting along internal portions of residential
streets. The plat makes appropriate provision for safe walking conditions.
13. The applicant will comply with all City landscaping standards and has proposed a
street tree planting plan which incorporates such requirements. The applicant will
also landscape the open space areas and storm water facilities. The perimeter must
have Type 2 landscaping or a fence.
CONCLUSIONS
:
1. The Hearing Examiner has jurisdiction to consider and decide the issues presented
by this request.
2. The proposed preliminary plat makes appropriate provision for the public health,
safety, and general welfare for open spaces, drainage ways, streets, roads, alleys,
other public ways, transit stops, potable water supplies, sanitary waste, parks and
recreation, playgrounds, schools and school grounds, and safe walking conditions.
3. The proposed subdivision is in conformity with the Low Density Residential zone
classification of the Tahoma Terra Development Guidelines.
4. All public facilities impacted by the subdivision are adequate and available to serve
the development.
5. The project is within the City’s sewer service area and said system has capacity to
serve all lots.
6. The proposed preliminary plat will serve the public use and interest by providing an
attractive location for a single family residential subdivision and by helping
implement the Tahoma Terra Master Planned Community, and therefore should be
approved subject to the following conditions:
1. The proponent shall comply with the mitigation requirements of the MDNS
issued on May 24, 2005, which include:
The developer shall mitigate transportation impacts through the
payment of a transportation facility charge (TFC) pursuant to
Chapter 15.40 YMC. The fee shall be paid at the time of building
permit issuance.
The applicant shall be responsible for the following transportation
improvements:
Prior to the final subdivision approval of any lots the
o
applicant shall reconstruct Longmire Street to a modified
collector standard from the project entry to Yelm Avenue
West (SR 510).
Prior to the approval of any development permit (including a
o
final subdivision) which includes the 90th peak P.M. trip
generated from the project, the applicant shall construct a
center left-turn lane on Yelm Avenue West (SR-510) at the
Longmire Street intersection with sufficient storage to serve
the anticipated traffic volumes generated by the project.
Prior to the approval of any development permit (including a
o
final subdivision) which includes the 513th peak P.M. trip
generated from the project, construction of the Killion Road
Boulevard extension from the property to Yelm Avenue West
(SR-510) along with the realignment of Killion Road, a traffic
signal, and left turn lanes on all four legs of the intersection
with sufficient storage to serve the anticipated traffic volumes
generated by the project.
Prior to the approval of any development permit (including a
o
final subdivision) which includes the 1,100th peak P.M. trip
generated from the project, reconstruct Mosman Avenue to
modified collector standards from Longmire Street to 1st
Avenue (SR-507) and the Mosman Avenue/1st Avenue
intersection to include realignment and a center left-turn lane
on 1st Avenue (SR-507) with sufficient storage to serve the
anticipated traffic volumes generated by the project.
Prior to the approval of any development permit (including a
o
final subdivision) which includes the 1,301st peak P.M. trip
generated from the project, define and construct the
Mosman Avenue connector between Longmire Street and
Solberg Street OR; continue the Boulevard to SR 507
through the Thurston Highlands property.
Plans for approval of all transportation improvements associated
with Yelm Avenue (SR 510) and 1st Avenue (SR 507) shall be
submitted to the Washington Department of Transportation and the
City of Yelm for review and approval and all required improvements
shall be constructed by the applicant pursuant to approved plans,
and inspected and approved by the City of Yelm and Washington
Department of Transportation.
To mitigate previous impacts from agricultural activities to surface
waters, plant communities and animal communities along the
Thompson Creek corridor and its associated wetlands, the
applicant has prepared a mitigation and enhancement plan to
improve the surface water features of the site for both habitat and
recreation purposes. Each Final Master Site Plan shall include a
schedule for implementing improvements tied to the number of
dwelling units of each subdivision within the Master Planned
Community.
The developer shall enter into an agreement with Yelm Community
Schools to mitigate project impacts to the School District.
Prior to the approval of any development permit (including a final
subdivision) beyond the 89th lot, the applicant shall convey water
rights to the City of Yelm sufficient to serve the proposed use within
that area of the final master site plan and the first 89 lots. The
conveyance shall be made to the City through a water rights
agreement between Tahoma Terra, LLC and the City of Yelm. This
condition is not applicable if the City obtains water rights through
the Department of Ecology which are sufficient to serve the
projected density of the City, its urban growth area, and the subject
property.
Prior to disturbance of any identified geologic hazard area, the
applicant shall submit to the City of Yelm Community Development
Department a geotechnical report that identifies established best
management practices for all activity within the geologic hazard
areas and only allows activities which:
will not increase the threat of the geological hazard to
o
adjacent properties beyond pre-development conditions;
will not adversely impact other critical areas;
o
are designed so that the hazard to the project is eliminated
o
or mitigated to a level equal to or less than pre-development
conditions;
are certified as safe as designed by a qualified engineer or
o
geologist.
Prior to building permit issuance, the applicant shall enter into a
mitigation agreement with the City of Yelm which includes a
mitigation fee toward the replacement of a police station required to
be expanded in order to serve the proposed development. The
mitigation fee shall be based on the applicant’s aliquot impact on
the need for replacement police station, which is $310 per housing
unit.
2. Each dwelling unit with the subdivision shall connect to the City water
system. The applicant has provided to the City a “Water Right Conveyance
and Right-of-Entry Agreement”. This conveyance establishes the water
connection fees.
3. The existing wells shall be abandoned per Washington State Department of
Ecology standards. Any water rights associated with the well shall be
deeded to the City of Yelm.
4. All conditions for cross connection control as required in Section 246-290-490
WAC.
5. Each dwelling within the subdivision shall connect to the City S.T.E.P. sewer
system. The connection fee and inspection fee will be established at the time
of building permit issuance. Existing septic systems shall be abandoned per
the Thurston County Department of Health standards.
6. The applicant shall connect to the City’s reclaimed water system. All
irrigation systems for planting strips and required landscaping located within
any open space, stormwater tracts, and the Boulevard shall be served by an
irrigation system utilizing reclaimed water where available. The civil plans
shall identify proposed reclaimed water lines, meters, and valves.
7. The applicant shall provide a final landscape and irrigation plan for this
subdivision as a part of civil plan submission. Landscape plans shall meet
Chapter 17.80 YMC, or as amended in the Final Master Plan approval.
8. The applicant shall provide for a minimum of one “pocket park” for the
preliminary plat of 89 lots, and the completion of the proposed three (3) acres
of open space area located at the southwest end of Longmire Street.
9. The proponent shall design and construct all stormwater facilities in
accordance with the 1992 DOE Stormwater Manual, as adopted by the City
of Yelm, and as amended in the Final Master Plan Approval. Best
Management Practices (BMP’s) are required during construction.
10. The final stormwater plan shall be submitted with civil engineering plans and
shall include an operation and maintenance plan.
11. Storm water facilities shall be located in a separate recorded tract owned and
maintained by the homeowners association.
12. All roof drain runoff shall be infiltrated on each lot utilizing individual drywells.
13. The stormwater system shall be held in common by the Homeowners
Association. The Homeowners Agreement shall include provisions for the
assessment of fees against individual lots for the maintenance and repair of
the stormwater facilities.
14. The proponent shall submit a fire hydrant plan to the Community
Development Department for review and approval as part of the civil
engineering plans prior to final subdivision approval.
15. The proponent shall submit fire flow calculations for all existing and proposed
hydrants. All hydrants must meet minimum City standards.
16. The proponent shall be responsible for the installation of hydrant locks on all
fire hydrants required and installed as part of development. The proponent
shall coordinate with the Yelm Public Works Department to purchase and
install required hydrant locks. Hydrant lock details shall be included in civil
plan submission.
17. Street lighting will be required. Civil plan submittal shall include a lighting
design plan for review and approval.
18. Prior to the submission of final plat application, the proponent will provide the
Community Development Department an addressing map for approval.
19. Prior to the submission of final plat application, a subdivision name must be
reserved with the Thurston County Auditor’s Office.
20. The proponent shall submit a final landscaping and irrigation plan for this plat,
along with the phased open space improvements with civil engineering plans.
21. The proponent shall provide a performance assurance device in order to
provide for maintenance of the required landscaping for this plat, until the
tenant or homeowners’ association becomes responsible for landscaping
maintenance. The performance assurance device shall be 150 percent of the
anticipated cost to maintain the landscaping for three years.
DECISION
:
The request for preliminary plat approval of Phase 1 of the Tahoma Terra Master Planned
Community is hereby granted subject to the conditions contained in the conclusions above.
nd
ORDERED
this 2 day of August, 2005.
_____________________________________
STEPHEN K. CAUSSEAUX, JR.
Hearing Examiner
nd
TRANSMITTED
this 2 day of August, 2005, to the following:
APPLICANT
:Tahoma Terra LLC
th
4200 6 Avenue SE, Suite 301
Lacey, WA 98503
ENGINEER
: SCA Consulting Group
th
4200 6 Avenue SE, Ste. 301
Lacey, WA 98503
OTHERS
:
Jenise Mugler Darlene Baker
15009 Highway 507 SE P.O. Box 727
Yelm, WA 98597 Yelm, WA 98597
Margaret Clapp Henry and Jane Dragt
th
18309 Cook Road SE 5815 95 Avenue SW
Yelm, WA 98597 Olympia, WA 98512
Steven Chamberlain Jean Handley
th
4200 6 Avenue SE P.O. Box 1657
Lacey, WA 98057 Yelm, WA 98597
Diane D’Acuti Larry Schamm
rd
19436 93 Avenue SE 18217 Highway 507 SE
Yelm, WA 98597 Yelm, WA 98597
George Swartz James Zukowski
2410 Crestline Drive NW P.O. Box 858
Olympia, WA 98502 Yelm, WA 98597
Rosalie Saecker Linda J. Powell
412 SW McKenzie Avenue P.O. Box 891
Yelm, WA 98597 Yelm, WA 98597
Bob Droll Gaye Newby
th
4405 7 Avenue SE 15105 Longmire Street SE
Lacey, WA 98503 Yelm, WA 98597
Mary Lou Clemens Curtis Smelser
15030 Longmire St. 1201 Third Avenue, Ste. 3400
Yelm, WA 98597 Seattle, WA 98101
John Turner City of Yelm
545 Mcphee Road SW Tami Merriman
Olympia, WA 98502 105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
CASE NO.: SUB-05-0068-YL (part of MPD-05-0067-YL)
NOTICE
RECONSIDERATION
1.: Any interested party or agency of record, oral or
written, that disagrees with the decision of the hearing examiner may make a written
request for reconsideration by the hearing examiner. Said request shall set forth specific
errors relating to:
A. Erroneous procedures;
B. Errors of law objected to at the public hearing by the person requesting
reconsideration;
C. Incomplete record;
D. An error in interpreting the comprehensive plan or other relevant material; or
E. Newly discovered material evidence which was not available at the time of
the
hearing. The term “new evidence” shall mean only evidence discovered after the hearing
held by the hearing examiner and shall not include evidence which was available or which
could reasonably have been available and simply not presented at the hearing for whatever
reason.
The request must be filed no later than 4:30 p.m. on August 15, 2005 (10 days from
mailing) with the Community Development Department 105 Yelm Avenue West, Yelm, WA
98597. This request shall set forth the bases for reconsideration as limited by the above.
The hearing examiner shall review said request in light of the record and take such further
action as he deems proper. The hearing examiner may request further information which
shall be provided within 10 days of the request.
APPEAL OF EXAMINER'S DECISION
2.: The final decision by the Examiner
may be appealed to the city council, by any aggrieved person or agency of record, oral or
written that disagrees with the decision of the hearing examiner, except threshold
determinations (YMC 15.49.160) in accordance with Section 2.26.150 of the Yelm
Municipal Code (YMC).
NOTE:
In an effort to avoid confusion at the time of filing a request for
reconsideration, please attach this page to the request for reconsideration.