20090061 Engineers Letter Hodge engineering inc. g g 12-4-08 � Letter# 8731 B L 1. RE: Tenant Improvement Yelm Office Building 718 W Yelm Ave Upset Beam / Gusset and Cut Truss Tails To Whom It May Concern: At the request of the builder I have provided a structural observation of the office building remodel at 718 W Yelm. The builder is upsetting a beam by cutting truss tails to supnnrt a removed hearing wall. The beam is being upset to provide adequate head height. The builder is removing 10'8" of bearing wall and replacing it with a beam. In previous engineering support letter 87311 sized the required beam with 15' of tributary roof load with concrete tile as a 5-1/8"x10-1/2" GLB 24F-1.8E. The beam is to post down on double 2x6 studs nailed together with (2) 10d nails at 8" on center. The studs are adequately supported by the existing footing and stemwall below. As an option the builder may solid block between the truss top and bottom cord and add 7/16" sheathing to one side of the trusses and hang the cut trusses off the 5-1/8"x10-1/2" upset glulam beam. The 7/16" sheathing shall 18" wide and be nailed with (2) rows 8d nails at 6" on center to both top bottom truss cords. This configuration will provide greater strength to the trusses than the original. See attached etail for truss gusset nailing configuration. Please cont wit v questions regarding this project. 1 12-4-08 Letter#8731 B,. inn, �,,37b86 t� ,tili t John Hodge P.E. This letter is the professional opinion of the engineer of record and regards his engineering only. This letter does not allow the builder to disregard Code requirements. Any schedule or cost impact is the responsibility of the builder or owner. The Building Inspector has the final authority to allow field changes to approved building plans. Hodge k 3 . _Inc. 6oi.Jahn Ave NW Ste, Ni Gig Hai-bor,WA 98335 I ;�a ` Bs: ®`5; a? 7"49 1� 1 7 N� ry� OUl ZU :z II II � Z Z Ja 1 LU II II p O NZ v � CS) w c � @ -A (S) cvZ N 1— Z � �4 i I I j �I Hodge engineering + inc. 10-22-08 Letter# 8731 p RE: Tenant Improvement Yelm Office Building 718 W Yelm Ave To Whom It May Concern: At the request of the builder I have reviewed the attached tenant improvement for the office building at 718 W Yelm Ave. The builder is removing 10'8" of bearing wall and replacing it with a beam. I have sized the required beam with 15' of tributary roof load with concrete tile as a 5-1/8"x10-1/2" GLB 24F-1.8E. The beam is to post down on double 2x6 studs nailed together with (2) 10d nails at 8" on center. The studs are adequately supported by the existing footing and stemwall below. See attached engineering calculations and builder provided plan views. Please c tact_me with any questions regarding this project. J 10-2 -08.. T' ' . John 1od ? Thi Vetter is the pro ssiona 'ion he engineer of record and regards his engineering only. This letter does noft allow the ljltier to disreg2ft t;od requirements. Any schedule or cost impact is the responsibility t e bpi owrW The Buildu o Spector has the final authority to allow field changes to approved ns a �E ` � ! 1 g fBel1 g' 110. '26o 4.. alin Ave NNV Ste. M Gib;IdarPaor,�� 9�33 •x. � .<F (25-3)857-70r),,-)Fax(25 3) 857-7599 RECEIVED 1,0/2212008 10:34 2530577599 HODGE ENGINEERING wiiuuarric 1c s dtiid.4bH. 73:9R r. 2 r I COMPANY PROJECT r Hodge Engineering Inc. Yelm Office Building Wood �o r k Gig Jahn Ave 98 Suite Al Roof Load y j(4J! J Gig Harbor,WA 98335 Beam1 SOETWAREMN WOOD DWC& 253-857-7055,857-7599 fax Oct.22,2008 14:16 Design Check Calculation Sheet Sizer 8.0 LOADS: Load Type Distribution Pat- Location [ft) Magnitude Unit tern Start End Start End T.oadl Dead Full Area 15.00(15.00)* psf Load2 Snow Full Area 30.00(15.00)* psf Monier Tile Dead Full Area 10.00(15.00)* psf *Tributary Width (ft) MAXIMUM REACTIONS(lbs)and BEARING LENGTHS(in) : r a 10' 10'-8' Dead 2000 2000 Live 2400 2400 Total 4466 4466 Bearing: Load Comb #2 #2 Length 1.34 1.34 Cb 1.00 1.00 Glulam-Bal.,West Species,24F-1.8E WS, 5-1/8x10-112" Self-weight of 12.39 plf included in loads; Lateral support:top=at supports,bottom=at supports; Analysis vs.Allowable Stress (psi) and Deflection(in) using NDS 2005: Criterion Analysis Value Desi n Value Anal sis/Desi n Shear fv = 104 Fv' - 305 fv/Fv' = 0.34 Bending(+) fb = 1518 Fb' = 2713 fb/Fb' = 0.56 Live Defl'n 0.15 = L/869 0.36 = L/360 0.41 Total Defl'n 0.34 = L/379 0.53 = L/240 0.63 ADDITIONAL DATA: FACTORS: F/E CD CM Ct CL CV Cfu Cr Cfrt Notes Cn LC# Fv' 265 1.15 1.00 1.00 - - - - 1.00 1.00 1.00 2 Fb'+ 2400 1.15 1.00 1.00 0.983 1.000 1.00 1.00 1.00 1.00 - 2 Fcp' 650 - 1.00 1.00 - - - - 1.00 - - - E' 1.8 million 1.00 1.00 - - - - 1.00 - - 2 Emin' 0.85 million 1.00 1.00 - - - - 1.00 - - 2 Shear : LC #2 = D+S, V = 4466, V design = 3733 lbs Bending(+) : LC #2 = D+S, M = 11910 lbs-ft Deflection: LC #2 = D+S EI = 890e06 lb-in2 Total Deflection = 1.50(Dead Load Deflection) + Live Load Deflection. (D=dead L=live S=snow W=wind I=impact C=construction Lc=concentrated) (All LC's are listed in the Analysis output) Load combinations: ICC-IBC DESIGN NOTES: 1. Please verify that the default deflection limits are appropriate for your application. 2.Glulam design values are for materials conforming to AITC 117-2001 and manufactured in accordance with ANSI/AITC A190.1-1992 3.GLULAM:bxd=actual breadth x actual depth. 4. Glulam Beams shall be laterally supported according to the provisions of NDS Clause 3.3.3. 5.GLULAM:bearing length based on smaller of Fcp(tension),Fcp(comp'n).