20070057 HoffmanYELMsewerWater.o BOWEN CONSTRUCTIOt IN,
PO Box 42 Date
Buckley Wa 98321
CONSTRUCT ON, INC. one 360 829 6632 Fax 360 829 6635
LAND CLEARING HAULING SITE PREP
ROAD BUILDING LOGGING GENERAL EXCAVATION
Hoffman
9405 Cullens Road SE Yelm
Sewer
Quantity
Unit
Unit Price
Amount
Tie ins
2
EA
$800.00
$1,600.00
3" PVC
190
L F
$14.00
$2)660.00
2" PVC
400
L F
$13.00
$5)200.00
1" PVC
600
LF
$8.00
$4,800.00
3" Gate Valve
1
EA
$450.00
$450.00
2" Gate valve
2
EA
$350.00
$700.00
Air release
1
LS
$3)000.00
$3)000.00
Services
15
EA
$400.00
$6,000.00
Test and TV
1
LS
$400.00
$400.00
Sub -Total
$249810.00
*Marked Items are Taxable
8.7%
*Sales Tax
$29158.47
Total
$269968.47
Water Supply System
Quantity
Unit
Unit Price
Amount
Tie ins
2
EA
$800.00
$1,600.00
8" PVC
590
L F
$21.00
$12)390.00
6" DIP
60
L F
$27.00
$1)620.00
M isc fittings
1
LS
$3)900.00
$3)900.00
Blow off
1
LS
$2,200.00
$2,200.00
Air Vac
1
LS
$3)000.00
$3)000.00
Services
15
EA
$800.00
$12,000.00
Irrigation service
1
EA
$1)500.00
$1)500.00
Sub -Total
$389210.00
*Marked Items are Taxable
8.7%
*Sales Tax
$39324.27
Total
$419534.27
Grand Total Budget
Sanitary Sewer I I 1 1 $269968.47
Water System $419534.27
Total $689502.74