Preliminary Drainage Report John Knowles & Associates, Inc. PO. Box 1328 Puyallup, WA 98371-0197 (253) 539-1400 FAX 539-1500 jkacivil@nwrain.com August 18,2000 Mr Tim Peterson City of Yelm Public Works Dept. POBox 479 Yelm, WA 98597 Re 16025 Mill Road S.E. Proposed Preliminary Plat Conceptual Storm Drainage Design - Letter Report JKA Project #0032 Dear Mr Peterson We have prepared this letter to present our proposal for the conceptual storm drainage, grading, and utility design associated with the subject project. This addresses the City's preliminary plat "checklist" requirement for a description of proposed improvements. Please consider this letter an abbreviated version of our future Storm Drainage Report for the final design of civil site improvements associated with the final plat. The information is presented in the format of the current WSDOE Stormwater Management Manual. Our stormwater calculations and design comply with the WSDOE Manual. A "Preliminary Drainage and Utility Plan" is enclosed for your reference PRELIMINARY DRAINAGE REPORT PART I - PROJECT DESCRIPTION Section 1 - Proposed Proiect Description The proponents, Group 2000 LLC, are applying for preliminary plat approval for the development of a 20-lot single-family subdivision on the property at the southwest corner of 10ih Loop S E. and Mill Road S E The site is comprised of approximately 492 acres The two tax parcels are 21725- 140400 and -140501 This project is located in the Northeast Quarter of Section 25, Township 17N, Range 1 E, W M The site is currently undeveloped Current comp plan zoning is R-4 Civil Engineering Project Management Construction Management Mr Tim Peterson 8/18/2000 Page 2 The proposal includes the construction of frontage improvements (curb, gutter, sidewalk, street trees, and street lights) along Mill Road S E to neighborhood collector standards, construction of full street improvements for the new onsite cul-de-sac roadway, constructed to "local access residential" standards, extension of water and STEP main lines from 10ih into the site, installation of stormwater collection, conveyance, treatment, storage, and underground infiltration trench facilities, minor grading associated with construction of the onsite road, and the installation of three street lights There would be a single vehicular access to 10ih Loop to serve lots 5-20, lots 1-4 would have direct access to 10ih Loop S E There are no frontage improvements proposed for 10ih Loop S E , curb and gutter exist on both sides of said street and a sidewalk is situated on the north side of the street. Water for fire protection and domestic services would be brought to the site from the existing 8" water main in 107th A fire hydrant is proposed for the end of the cul-de-sac, an existing hydrant is located on the north side of 10ih, just northeast of the intersection of the new onsite road with 10ih The City's STEP sewer system will be extended into the site by means of a 2" main installation with STEP services for each lot. Lots 1-4 will be served by the City's existing STEP and water mains in 10ih Proposed Storm water System Please refer to the attached Preliminary Drainage and Utility Plan for the following discussion Runoff generated on the proposed onsite roadway will be collected, stored, treated, and released as follows All onsite runoff from driveways and the new roadway will be collected in the site's public road stormwater drainage system, conveyed via underground piping and discharged to the site storm drainage treatment and infiltration trench facilities adjacent to the roadways The treatment element of the facility will consist of an underground pre-settling vault (preliminarily sized as 28' long x 8' wide x 3' deep concrete vault) followed by a water-quality infiltration trench The intent is to remove the suspended solids from the runoff in the pre-settling basin (pre-treatment) prior to the runoff reaching the water-quality infiltration trench The pre-settling basin will be sized during final design per the WSDOE SWM Manual, during final design, the use of round aluminized CMP piping may be used for the pre-settling vault. The runoff will be further treated in the water quality infiltration trench by filtration through an 18" depth of loamy fine sand underlying the washed drainrock. The target infiltration rate of the fine sand layer is two inches per hour The treatment facilities will serve up to six month/24-hour storm event. Higher storm events will bypass the pre- Mr Tim Peterson 8/18/2000 Page 3 settling vault and water quality infiltration trench to prevent accumulation of silts from being flushed into the water quality infiltration trench Runoff bypassing the pre-settling vault and water quality infiltration trench will be directed to the "1 OO-year" infiltration trench on the west side of the roadway This trench will be approximately 200' long x 5' wide x 5' deep and designed to store and dispose of the 1 DO-year storm event. The roadway stormwater treatment and infiltration facilities discussed above were selected due to the presence of the well-draining Spanaway series soils During final design, soil test pits will be excavated and inspected by a soils professional to ensure that no impervious surface or high groundwater evidence is found within three feet of the bottom of the infiltration surfaces The 1 DO-year infiltration trench has been preliminarily sized based on 15" per hour infiltration rate Runoff from all roofs will be directed to individual onsite infiltration trenches or drywells, designed during the final plat phase of the project to WSDOE Manual standards The following is a summary of the onsite stormwater facility elevations Elevation of adjacent public roadway at sag in vertical curve (near lots 8, 9, 16, and 17) Rim Elev 35875 Overflow invert elevation to infiltration trench Elev 35575 Invert elevation to pre-settling vault Elev 3545 Bottom of drainrock for water-quality infiltration trench Elev 352 75 Bottom of drainrock for 1 DO-year infiltration trench Elev 35275 Section 2 - ExistinQ Conditions The irregular-shaped site is bordered by 10ih Loop S E. to the north and Mill Road S E to the east. Single-family zoning surrounds the balance of the site perimeter Site topography is of low relief, with low points (elevation 360) near the central portion of the site The high point of the site (elevation 366) is located along the east portion of the site, adjacent to Mill Road The site is currently vegetated with tall grasses and scattered trees There is an existing home onsite that is to be removed There is an existing storm drainage system in place associated with 10ih Loop S E The development of this project will maintain 10ih Loop runoff within the existing storm system There are no manmade drainage facilities onsite Mr Tim Peterson 8/18/2000 Page 4 Section 3 - Infiltration Rates/Soils Report The Soil Conservation Soil Survey of Thurston County maps the onsite soils as 41-A Spanaway Gravelly Sandy Loam This soil is defined by SCS as follows "In a typical profile, the surface layer is black gravelly, sandy loam 14" thick. The subsoil, to a depth of 18", is dark grayish-brown, very gravelly sandy loam The substratum, to a depth of more than 60", is light brown- gray, very gravelly sand Permeability is moderately rapid The available water capacity is low Surface runoff is slow and there is little erosion hazard The affective rooting depth is more than four feet." These soils have historically provided for the excellent application of stormwater infiltration facilities, as proposed in this project. During final design, soil test pits will be excavated in the vicinity of the infiltration facilities to confirm that adequate clearance Will exist between the bottom of the infiltration surfaces and impervious/mottling Section 4 - Wells and Septic Systems Any and all domestic wells onsite will be abandoned in accordance with Thurston County Environmental Health Services and DOE criteria. The site will be served by City of Yelm Public Water All onsite sewage disposal systems shall be abandoned in accordance with Thurston County Environmental Services Department criteria. The site will be served by the City's public STEP system Section 5 - Fuel Tanks Any underground fuel tanks located on the site must be removed or abandoned In accordance with WSDOE regulations Section 6 - Sub-Basin Description There is no significant offsite runoff tributary to this site The runoff within 10th Loop is currently collected within an existing public storm system Runoff generated from Mill Road S E. currently drains to a roadside ditch where the drainage appears to infiltrate Adjacent properties, east, south, and west of the site, do not contribute significant amounts of sheetflow to the site based on the well-draining characteristics of the Spanaway series soils Section 7 - Analysis of 1 DO-Year FI~od The FEMA Flood Insurance Rate Map for the area confirms that the site is located in a "C" flood zone Mr Tim Peterson 8/18/2000 Page 5 Section 8 - Aesthetic Considerations of Facilities The stormwater treatment and infiltration systems will be underground All other elements of the storm drainage system will be underground as well in the form of catch basins and piping Section 9 - Downstream Analvsis All runoff from storms up to the 1 DO-year frequency shall be collected onsite, stored, and discharged via infiltration Thus, no discharge of runoff is anticipated to offsite properties or adjacent right-of-ways. Section 10 - Covenants. Dedications. and Easements All drainage facilities, including underground piping, catch basins, stormwater treatment basins, and the infiltration pond, will require routine maintenance These facilities (other than the onsite individual roof drain drywells/infiltration trenches) will be maintained by the City of Yelm Appropriate easements will be provided to the City to allow access to the infiltration and treatment facilities that are located outside the proposed street right- of-way During final design, a detailed list of maintenance procedures and inspection checklists shall be prepared and submitted to the City for review Section 11 - Conclusion Every effort will be made during final design to comply with the current WSDOE Stormwater Management Manual requirements for stormwater collection, conveyance, treatment, storage, and discharge The preliminary design presented in this letter and on the "Preliminary Drainage and Utility Plan" complies with the intent of the WSDOE Manual and the City of Yelm Development Guidelines By complying with state-of-the art design criteria, stormwater systems for this project will minimize the impact of this development on downstream properties and the underlying aquifer with respect to erosion control, flood impacts, and water quality Mr Tim Peterson 8/18/2000 Page 6 PART II - EROSION CONTROL Section 1 Project design shall include site grading and erosion control measures to contain silt and soil within the project boundaries during construction until permanent erosion control is in place in the form of landscaping, hydroseeding, and roadway paving Erosion/sediment control shall be achieved by a combination of structural and vegetative cover measures and construction practices tailored to fit the site Best management practices (BMPs) will be employed to allow proper clearing and grading of the site and scheduling of construction activities Before any construction begins onsite, appropriate erosion control facilities shall first be installed The planned construction sequence may be as follows 1 Obtain City of Yelm Grading and/or Site Development Permit. 2. Install rock construction entrance at the permanent access location off 10ih Loop S E Use quarry spalls or rip rap in accordance with the "temporary rock construction entrance" detail included in the final civil plans 3 Designate an area for washing of equipment and concrete trucks to control runoff and to eliminate entry into the storm drainage systems and wetland buffers 4 Install filter fabric fencing around lower portions of the site, as needed to inhibit silt- laden runoff from contaminating offsite areas and ditches 5 Construct temporary sedimentation traps or sediment ponds, as necessary 6 Clear developed areas of vegetation (grubbing and rough grading) 7 Install stormwater system, construct stormwater treatment/control facility, and fine grade site Protect underground stormwater conveyance, storage, and treatment facilities from silt-laden runoff, using BMPs depicted on the final civil engineering plans 8 During November 1 st through March 31 st, all disturbed areas greater than 5000 square feet that are subject to erosion shall be stabilized by mulch, hydroseeding, sodding, or plastic covering 9 Complete construction of storm drainage facilities and other underground improvements 10 Complete road improvements 11 Place landscaping and hydroseed all disturbed areas Complete perimeter and internal landscaping and buffer requirements so as to minimize long-term erosion potential. 12. Maintain all erosion control facilities until the entire site is stabilized and silt-laden runoff ceases Mr Tim Peterson 8/18/2000 Page 7 Section 2 - Trappina Sediment The onsite soils belong to the Spanaway series and have potential for erosion Filter fabric fencing shall be installed as needed around the perimeter of the site to control erosion, the final civil plans will depict the location and will provide details for fencing A stabilized construction entrance will be installed with permanent access to the roadway to prevent vehicles from tracking soil away from the disturbed areas, if sediment is tracked offsite, sediment shall, on a daily basis, be swept or shoveled from the public roadway surface prior to washing down said pavement. Section 3 - Permanent Erosion Control and Site Restoration All disturbed areas will be paved, surfaced with gravel, hydroseeded, covered with landscaping, or developed as building site Section 4 - Inspection Sequence In addition to normal City inspections for grading and erosion control, the project engineer must be notified by the contractor to observe the facilities related to stormwater treatment, storage, and conveyance during construction At a minimum, the following items should be observed at the time specified 1 The following erosion control measures shall be installed by the contractor and inspected by the City before start of clearing and grading a) Construction entrance b) Filter fabric fences 2. The contractor must notify the project engineer to observe construction of the project drainage facilities to ensure the following are in working order' a) Catch basin and pipe conveyance system b) Stormwater infiltration trenches c) Pre-settling basins It is the responsibility of the contractor to inform the project engineer of the timing of the above construction phases A final site visit will be performed to verify grades, drainage construction, and all of the necessary information to complete a project engineer's Project Observation Report. The owner is responsible for advising the contractor of his responsibility to notify the engineer regarding construction progress Mr Tim Peterson 8/18/2000 Page 8 Section 5 - Control of Pollutants Other Than Sediments Washout from concrete trucks shall not be dumped into the storm drainage system or onto soil or pavement, which carries stormwater runoff Washout can be dumped into a designated area to be later backfilled or hardened and broken up for disposal into a landfill or concrete recycling facility The owner shall designate a wash-down area for equipment and concrete trucks Extra copies of the "Preliminary Drainage and Utility Plan" are enclosed for your reference. Please give us a call if you have any questions, concerns, or suggestions related to our preliminary design. Thank you very much. Sincerely, JOHN KNOWLES & ASSOCIATES, INC Ae.. ~ fDllscott Danielson Project Engineer ~~ President enc. cc: 80 Norbjerg (w/plan) Arne Riipinen (w/plan) (c:\winwordlJ EKfiles\0032816P.ltr) Preliminary Storm DrainaQe Calculations 16025 Mill Road SE Plat AUQust. 2000 Criteria / References . WSDOE SWM Manual . SCS Soils Mapping . WaterWorks Software . SBUH Method w/ Type 1a Storm . Yelm Development Guidelines Area Summary' Area to Infiltration System 2 92 Acres Landscaping 068 Acres Pavement (Including Driveways) Total = 360 Acres (Includes offsite, % Acre) Area to Presettling Basin and Water Quality Infiltration Basin Trench 2.92 Acres Landscaping 068 Acres Pavement (Including Driveways) Total = 360 Acres (Includes offsite, % Acre) CN Values Landscaping = 80 ~averflent and Roof = 98 I EXPIRES: PRESETTLlNG VAULT. As Qo w As = E = Qo = As = Based upon design criteria for BMP RD 10 = -(QJw) x Ln (I - E) = A vg release rate = 'i.. 1c! = Settling velocIty of soil particle (use 0004 fps for silt) Surface area required. Trap efficiency = 80% = 8 v = 4790 CF (6 mo. storm vol.) = 200 CF/hr = 0 056 cfs - . 1c! 24 hr -( 056/0004) x Ln(1- 8) = 225 sf Use a settling vault with a 225 square foot settling area. 16025 Mill Road SE BO Norbjerg Plat -8/ --------------------------------------------------------------------- --------------------------------------------------------------------- BASIN SUMMARY NAME: DEVELOPED 100YR BASIN ID: D100 SBUH METHODOLOGY TOTAL AREA.......: RAINFALL TYPE.. ..: PRECIPITATION.... : TIME INTERVAL. . BASEFLOWS: 3.60 Acres TYPE1A 4 10 inches 10 00 min AREA. : CN... . TC. . . . : ABSTRACTION COEFF: TcReach - Sheet L: TcReach - Shallow L: TcReach - Shallow L: PEAK RATE. 1.47 cfs 0.20 300.00 100.00 38 00 VOL: ns:0.1500 p2yr: 2.00 ks:11.00 s:O 0250 ks 27 00 s 0.0066 0.74 Ac-ft TIME: NAME: DEVELOPED 6MONTH BASIN ID: D6 SBUH METHODOLOGY TOTAL AREA.......: RAINFALL TYPE. . PRECIPITATION.... : TIME INTERVAL..... BASEFLOWS: 3.60 Acres TYPE1A 1 28 inches 10 00 min AREA.. : CN .. : TC.. .: ABSTRACTION COEFF. TcReach - Sheet L. TcReach - Shallow L. TcReach - Shallow L PEAK RATE. 0 17 cfs 0.20 300.00 100.00 38.00 VOL: ns:0.1500 p2yr: 2.00 ks'll 00 s.0.0250 ks:27 00 s 0.0066 o 11 Ac-ft TIME 0.00 cfs PERV 2 92 Acres 80.00 33.10 min s:0.0170 480 min o 00 cfs PERV 2 92 Acres 80.00 33.10 min s:0.0170 480 min IMP o 68 Acres 98.00 5 00 min IMP o 68 Acres 98 00 5.00 min 8/15/00 2 . 31 : 54 pm 16025 Mill Road SE Shareware Release Bo Norbjerg Plat page 2 --------------------------------------------------------------------- --------------------------------------------------------------------- HYDROGRAPH No Peak runoff: TIME (min) DESIGN RUNOFF (cfs) TIME (min) 1 DESIGN RUNOFF (cfs) DETAIL HYDROGRAPH SUMMARY 0.0684 cfs TIME (min) DESIGN RUNOFF (cfs) TIME Total Vol: (min) DESIGN RUNOFF (cfs) TIME (min) 0.11 ac-ft DESIGN RUNOFF (cfs) --------------------------------------------------------------------------------------- --------------------------------------------------------------------------------------- 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 o 0005 o 0015 o 0029 o 0044 o 0062 o 0079 o 0092 o 0105 o 0117 o 0127 o 0137 o 0146 o 0154 o 0161 o 0169 o 0181 o 0199 o 0213 o 0222 o 0228 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 o 0291 o 0295 o 0300 o 0310 o 0332 o 0358 o 0392 o 0441 o 0497 o 0543 o 0567 o 0581 o 0595 o 0608 o 0621 o 0632 o 0638 o 0642 o 0647 o 0651 o 0656 o 0660 o 0664 o 0667 o 0671 o 0675 o 0679 o 0682 o 0683 o 0683 o 0682 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 o 0682 o 0678 o 0673 o 0669 o 0665 o 0661 o 0659 o 0659 o 0658 o 0658 o 0659 o 0660 o 0660 o 0662 o 0663 o 0665 o 0666 o 0666 o 0662 o 0655 o 0647 o 0639 o 0630 o 0623 o 0619 o 0617 o 0616 o 0616 o 0616 o 0616 o 0615 o 0612 o 0613 o 0613 o 0609 o 0604 o 0602 o 0600 o 0597 o 0596 1210 1220 1230 1240 1250 1260 1270 1280 1290 1300 1310 1320 1330 1340 1350 1360 1370 1380 1390 1400 1410 1420 1430 1440 1450 1460 1470 1480 1490 1500 1510 1520 1530 1540 1550 1560 1570 1580 1590 1600 o 0594 o 0592 o 0591 o 0590 o 0589 o 0588 o 0587 o 0587 o 0586 o 0586 o 0586 o 0585 o 0585 o 0585 o 0582 o 0579 o 0576 o 0572 o 0569 o 0565 o 0561 o 0558 o 0555 o 0552 o 0549 o 0543 o 0531 o 0515 o 0497 o 0479 o 0460 o 0442 o 0423 o 0405 o 0388 o 0371 o 0355 o 0339 o 0324 o 0309 1610 1620 1630 1640 1650 1660 1670 1680 1690 1700 1710 1720 1730 1740 1750 1760 1770 1780 1790 1800 1810 1820 1830 1840 1850 1860 1870 1880 1890 1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 o 0295 o 0282 o 0269 o 0257 o 0246 o 0176 o 0030 o 0005 o 0001 290 300 310 o 0233 320 o 0239 330 o 0244 340 o 0250 o 0256 o 0263 o 0269 o 0275 o 0281 o 0286 350 360 370 380 390 400 700 710 720 o 0682 730 o 0681 o 0681 o 0681 o 0682 o 0682 o 0683 o 0684 o 0684 740 750 760 770 780 790 800 8/15/00 2 . 31 : 54 pm 16025 Mill Road SE Shareware Release Bo Norbjerg Plat page 3 ~==================================================================== HYDROGRAPH No Peak runoff: TIME (min) DESIGN RUNOFF (cfs) TIME (min) 2 DESIGN RUNOFF (cfs) DETAIL HYDROGRAPH SUMMARY o 9904 cfs TIME (min) DESIGN RUNOFF (cfs) TIME Total Vol. TIME (min) DESIGN RUNOFF (cfs) (min) o 74 ac-ft DESIGN RUNOFF (cfs) --------------------------------------------------------------------------------------- --------------------------------------------------------------------------------------- 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 o 0015 o 0062 o 0120 o 0214 o 0334 o 0408 o 0463 o 0511 o 0548 o 0622 o 0712 o 0748 o 0764 o 0793 o 0812 o 0822 o 0840 o 0855 o 0858 o 0873 o 0884 o 0944 o 1038 o 1088 o 1153 o 1221 o 1294 o 1643 o 2106 o 2310 o 2476 o 2666 o 2834 o 2938 o 2990 o 3102 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 o 3224 o 3353 o 3465 o 3690 o 4076 o 4622 o 5380 o 6531 o 7915 o 9068 o 9651 o 9849 o 9904 o 9844 o 9721 o 9522 o 9203 o 8820 o 8447 o 8099 o 7784 o 7495 o 7220 o 6968 o 6745 o 6553 o 6393 o 6235 o 6050 o 5854 o 5673 o 5511 o 5367 o 5244 o 5140 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 810 820 830 840 850 860 870 o 4705 o 4575 o 4446 o 4325 o 4215 o 4128 o 4081 o 4063 o 4058 o 4061 o 4071 o 4084 o 4098 o 4114 o 4129 o 4144 o 4160 o 4137 o 4033 o 3879 o 3715 o 3442 o 2292 o 3166 o 2990 o 3480 o 3330 o 3569 o 3517 o 3523 o 3314 o 3275 o 3576 o 3569 o 2763 o 3087 o 3100 o 3095 o 3122 1210 1220 1230 1240 1250 1260 1270 1280 1290 1300 1310 1320 1330 1340 1350 1360 1370 1380 1390 1400 1410 1420 1430 1440 1450 1460 1470 1480 1490 1500 1510 1520 1530 1540 1550 1560 1570 1580 1590 1600 o 3119 o 3137 o 3135 o 3132 o 3151 o 3146 o 3144 o 3162 o 3157 o 3154 o 3172 o 3167 o 3164 o 3059 o 2876 o 2788 o 2720 o 2678 o 2656 o 2616 o 2608 o 2602 o 2580 o 2582 o 2585 o 2114 o 1348 o 0966 o 0732 o 0527 o 0397 o 0287 o 0216 o 0156 o 0117 o 0085 o 0064 o 0046 o 0035 o 0025 1610 1620 1630 1640 1650 1660 1670 1680 1690 1700 1710 1720 1730 1740 1750 1760 1770 1780 1790 1800 1810 1820 1830 1840 1850 1860 1870 1880 1890 1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 o 0019 o 0014 o 0010 o 0007 o 0006 o 0004 o 0003 o 0002 o 0002 o 0001 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 660 670 680 690 700 710 720 730 740 750 760 o 5051 770 780 o 4979 o 4920 o 4872 o 4810 790 800 880 890 900 910 920 930 o 3117 8/15/00 2.31 55 pm Shareware Release Bo Norbjerg Plat page 4 16025 Mill Road SE =============================================================~~~~==== STORAGE STRUCTURE LIST ~ RECTANGULAR VAULT ID No. lOa-wsw Description: 100YR TRENCH including sidewal Length: 200.00 ft. width: 5.00 ft. voids: 0.400 RECTANGULAR VAULT ID No. WQTR Description WATER QUAL TRENCH Length: 100.00 ft. width 5 00 ft voids' o 400 8/15/00 2 . 31 : 55 pm Shareware Release Bo Norbjerg Plat page 5 16025 Mill Road SE --------------------------------------------------------------------- --------------------------------------------------------------------- STAGE DISCHARGE TABLE DISCHARGE LIST ID No. WQTRNCH Description: BOTTOM OF WQTRENCH STAGE <--DISCHARGE---> STAGE <--DISCHARGE---> STAGE <--DISCHARGE---> STAGE <--DISCHARGE---> (ft) ---cfs-- ------- (ft) ---cfs-- ------- (ft) ---cfs-- ------- (ft) ---cfs-- ------- =======~=====~========================================================================================== 352 75 0 0230 353 60 0 0393 354 90 0 0563 356 00 0 0734 352 60 0 0236 353 90 0 0406 355 00 0 0579 356 10 0 0749 352 90 0 0253 354 00 0 0424 355 10 0 0594 356 20 0 0765 353 00 0 0269 354 10 0 0439 355 20 0 0610 356 30 0 0760 353 10 0 0264 354 20 0 0455 355 30 0 0625 356 40 0 0796 353 20 0 0300 354 30 0 0470 355 40 0 0641 356 50 0 0611 353 30 0 0315 354 40 0 0466 355 50 0 0656 356 60 0 0627 353 40 0 0331 354 50 0 0501 355 60 0 0672 356 70 0 0642 353 50 0 0346 354 60 0 0517 355 70 0 0667 356 75 0 0850 353 60 0 0362 354 70 0 0532 355 80 0 0703 353 70 0 0377 354 80 0 0548 355 90 0 0718 8/15/00 2 31:55 pm Shareware Release Bo Norbjerg Plat page 6 16025 Mill Road SE --------------------------------------------------------------------- --------------------------------------------------------------------- STAGE DISCHARGE TABLE DISCHARGE LIST ID No. tr-sw Description: BOTTOM & 1/2 sidewall STAGE <--DISCHARGE---> STAGE <--DISCHARGE---> STAGE <--DISCHARGE---> STAGE <--DISCHARGE---> (ft) ---cfs-- ------- (ft) ---cfs-- ------- (ft) ---cfs-- ------- (ft) ---cfs-- ------- -------------------------------------------------------------------------------------------------------- -------------------------------------------------------------------------------------------------------- 352 75 0 3500 354 00 0 5225 355 30 0 7019 356 60 0 8813 352 80 0 3569 354 10 0 5363 355 40 0 ?I57 356 70 0 8951 352 90 0 3707 354 20 0 5501 355 50 0 7295 356 80 0 9089 353 00 0 3845 354 30 0 5639 355 60 0 7433 356 90 0 9227 353 10 0 3983 354 40 0 5777 355 70 0 7571 357 00 0 9365 353 20 0 4121 354 50 0 5915 355 80 0 7709 357 10 0 9503 353 30 0 4259 354 60 0 6053 355 90 0 7847 357 20 0 9641 353 40 0 4397 354 70 0 6191 356 00 0 7985 357 30 0 9779 353 50 0 4535 354 80 0 6329 356 10 0 8123 357 40 0 9917 353 60 0 4673 354 90 0 6467 356 20 0 8261 357 50 I 0055 353 70 0 du 355 00 0 6605 356 30 0 8399 357 60 I 0193 353 80 0 4949 355 10 0 6743 356 40 0 8537 357 70 I 0331 353 90 0 5087 355 20 0 6881 356 50 0 8675 357 75 I 0400 v 8/15/00 2-31 56 pm Shareware Release Bo Norbjerg Plat page 7 16025 Mill Road SE --------------------------------------------------------------------- --------------------------------------------------------------------- LEVEL POOL TABLE SUMMARY MATCH INFLOW -STO- -DIS- <-PEAK-> OUTFLOW STORAGE <--------DESCRIPTION---------> (cfs) (cfs) --id- --id- <-STAGE> id (cfs) VOL (cf) ------------------------------------------------------------------------------------- ------------------------------------------------------------------------------------- o 00 1 47 lOa-wsw tr-sw 357 39 2 o 07 585 73 cf o 99 1856 25 cf WATER QUAL DESIGN 100YR TRENCH o 00 0 17 WQTR WQTRNCH 355 68 1