20150182 Email From Chad Bedlington on Rev 03092017Karen Bennett
From: Chad Bedlington
Sent: Thursday, March 09, 2017 9:41 AM
To: Tami Merriman; Maryanne Zukowski
Cc: Karen Bennett; Grant Beck
Subject: RE: Civil Plan Review
Attachments: RE: Crowe Law Office civil plan 2nd review
I can finish the review on this one since I did the civil plan review back in January 2016 and sent comments.
Tami: Could I get the water /sewer comments that were sent separately to you at that time so I can run through our
requests with the plans? Thanks!
Maryanne: Your off the hook on this one ;)
Regards,
Chad A. Bedlington, Public Works Director
City of Yelm 1901 Rhoton Road SE I Yelm, WA 98597
(360) 458 -8412, office 1 (360) 999 -0496, cell I chadb @ci.yelm.wa.us
From: Tami Merriman
Sent: Thursday, March 09, 2017 9:27 AM
To: Chad Bedlington; Maryanne Zukowski
Cc: Karen Bennett; Grant Beck
Subject: FW: Civil Plan Review
UH OH. We dropped the ball on this one.
The Crowe Law Office submitted civil plans for frontage improvements back in October. As it is frontage and no
water /sewer, Chad was going to review. Somehow we never got any review comments back to them.
This is Molly Carmody's project, so expedited review should occur. Please let me know how I can help, or if you need
history of the project.
VIEWING RESOURCES:
Our review documents are available for viewing in Laserfiche. This project can be viewed
under:
City- of -Yelm \Community Development \Permits \20150182 SPR Crowe Law
Off ice \Civil \Construction Plan Review \Review No 3 \Scanned Submittal
If you have any question or have issues viewing documents, please give Karen a call at
(360)458 -3835.
Tami Merriman
Associate Planner
City of Yelm
105 Yelm Ave W
Yelm, WA 98597
(360) 458 -8496
tamim @ci.yelm.wa.us
r �
yx}
From: Tami Merriman
Sent: Thursday, March 09, 2017 9:11 AM
To: Molly Carmody
Cc: Karen Bennett
Subject: Civil Plan Review
Molly
We owe you a huge apology. Karen and I did track down the civil plans that were submitted. The plans were distributed
for review, but in the mix of folks leaving, staff turnover and Chad trying to figure out Public Works after Ryan left, the
review fell through the cracks. It dropped off all of our radar that it wasn't done.
Maryanne, Chad, Karen and I are working on civil plan review process and tracking so these issues will not happen
again. I know this doesn't help your review, but we will get right on it! With Maryanne being a PE the review should be
way more efficient and accurate.