Traffic Impact Analysis
July, 2001
Engineering • Planning • Environmental Sciences
®The Shea Group
a Parametrix com/~any
August 7, 2001
PMX# 244-1781-017
Cathie Carlson, Community Development Director
City of Yelm
P O Box 479
Yelm, WA 98597
8830 Tallon Lane, Suite B, Lacey, WA 98516 • PO Box 3427, Lacey WA 98509-3427
Re: Yelm Avenue Walgreens Transportation Impact Analysis
Dear Cathie:
We are pleased to present the Transportation Impact Analysis for the proposed Yelm Avenue
Walgreens.
Our analysis indicates that the Yelm Avenue Walgreens will add approximately 76 new PM peak hour
trips to the area roadways after completion. The study indicates that the increase in traffic generated by
the proposed project will be accommodated by the planned roadway improvements within the area.
Traffic generated by the proposed Walgreens will have a measurable impact on the local roadway
system. The project should be required to construct half street frontage improvements along the
property frontage on Creek Street and Yelm Avenue and to pay a Transportation Facility Charge to the
City of Yelm.
°.
Sincerely,
-, ~
Geor .e- mith
Transportation Planner
cvc\gls
(k:\1781\Walgreens tia\Carlson 080701)
360.459-3609 • 360-459-0154 fax
Engineering • Panning • Environmental Sciences
TRANSPORTATION IMPACT ANALYSIS
Yelm Avenue Walgreens
Yelm, WA
July, 2001
Project Information
Project: Yelm Avenue Walgreens
Prepared for: City of Yelm Community Development Deparhnent
Contact: Cathie Carlson, Community Development Director
City of Yelm
P O Box 479
Yelm, WA 98597
(360) 458-8408
Project Engineer
Prepared by: The Shea Group
8830 Tallon Lane, Suite B, Lacey, WA 98516
P.O. Box 3427
Lacey, WA 98509-3427
(360) 459-3609 FAX (360) 459-0154
Contact: Perry A. Shea, P.E., Principal
George Smith, Transportation Planner
Shea Group Project: 244-1781-017
File Number: k:\1781\Contracts\Walgreens TIA
~~~~~
C ~ ~ _.~®~
Yelm Avenue Walgreens Traffic Impact Analysis
TABLE OF CONTENTS
I. INTRODUCTION ................................................................................................................................1
PROJECT OVERVIEW ............................................................................................................................. ..'I
STUDY CONTEXT ................................................................................................................................. ..')
II. PROJECT DESCRIPTION ................................................................................................................ ..3
DEVELOPMENT PROPOSAL .................................................................................................................... ..3
III. BACKGROUND INFORMATION .................................................................................................... ..5
AREA LAND USES ................................................................................................................................ ..5
ROADWAY INVENTORY ......................................................................................................................... ..5
TRAFFIC VOLUME DATA ....................................................................................................................... ..5
PUBLIC TRANSPORTATION .................................................................................................................... ..8
IV. PROJECT TRAFFIC CHARACTERISTICS .................................................................................... ..8
TRAFFIC GENERATION .......................................................................................................................... .. $
TRIP DISTRIBUTION .............................................................................................................................. ..9
V. FUTURE TRAFFIC CONDITIONS ................................................................................................... 12
ROADWAY IMPROVEMENTS ................................................................................................................... 12
PIPELINE DEVELOPMENT PROJECTS ........................................................................................................ 'I Z
PROJECTED TRAFFIC VOLUMES ............................................................................................................. 'I4
VI. TRAFFIC OPERATIONS ANALYSIS .............................................................................................. 17
SIGNALIZED INTERSECTIONS .................................................................................................................. 'I8
SITE DRIVEWAY ANALYSIS ................................................................................................................... ZO
VII. MITIGATION ................................................................................................................................... 22
VIII. CONCLUSIONS ................................................................................................................................23
The Shea Group - a Parametrix company Page I
July, 2001
Yelm Avenue Walgreens Traffic Impact Analysis
List of Figures
Figure 1 Site Vicinity Map
Figure 2 Preliminary Site Plan
Figure 3 Existing 2001 PM Peak Hour Traffic Volumes
Figure 4 Site-Generated Traffic Volumes
Figure 5 Site Generated Traffic Volumes -Site Detail
Figure 6 Pipeline Development Traffic
Figure 7 Projected 2002 PM Peak Hour Traffic Volumes Without Project
Figure 8 Projected 2002 PM Peak Hour Traffic Volumes With Project
Appendices
Appendix A Turning Movement Count Worksheets
Appendix B Capacity Analysis Worksheets
The Shea Group - a Parametrix company
July, 2001
Page ii
Yelm Avenue Walgreens Traffic Impact Analysis
I. INTRODUCTION
Project Overview
The Yelm Avenue Walgreens project will consist of a 14,490 square foot drugstore on 1.86 acres
at the NW corner of Yelm Avenue and Bald Hill Road-Creek Street in Yelm. Access to the
project will be provided through a driveway to Creek Street and a driveway directly onto Yelm
Avenue. Figure 1 illustrates the site vicinity and the transportation network serving the project
area.
Study Context
This report by The Shea Group documents the results of a Traffic Impact Analysis (TIA) of
existing and future traffic conditions in the project vicinity. The study was prepared according to
City of Yelm TIA guidelines for new developments as part of the required environmental review
submittal for the proposed project. Two intersections in the study area were analyzed. The
project is expected to be completed by 2002, which was used as the horizon year for this study.
The work scope for this study was determined through a scoping process involving
representatives of the developer, the City of Yelm, and The Shea Group. The intersections to be
analyzed were identified with input from City staff.
The Shea Group - a Parametrix company
July, 2001 Page 1
W
~ ~~
C7
Z
Q
U
O
J
i-
~~c ~, % = o ~~o
~J a`' Cy J ~ `~~ ~~ ~ pla'.~'~~~
G 1
4
\
Q' /~
~
~
; 1
V
BV
~ zr oho J - + if' L1~
~ ~' ~ bJS`JY aW `~ ~~ ~
m ~ ~
E ~
`
~K ~`S'
W
~ ONOV .
Z
~yy ~J ~, ~
~ o"G
<
e g ; ~
1] 138
t;
/
Sk a 3 e °°W
' 1J fJ ` ~~Otl N08NINlIM
w~ 1] ago 3
`4
x3N3%
au ]3in]
d 8 0
`
/
3 J J ~
"S' ~ u
w
P ~\~ `~
.
i
~
b3 ~Y=.~ ~
,
_ tlMh]
~
J
C~
3 ~i4
~
,
80 M31 hiYl
I
u ~ w
s n sioi ~.u ~.6 ~
~ 6
e ~
~ ~~
_ _~
~~ / h~HO t
~~ ~
~ ~
Odd: ~
~~
s ~.~ ; ~
~ 5
u
1 ~ ,~,.
4
~'
NS
hJ
~~
~
~, ~ ~ -~
W
O
~ ~
CQ J_
G Q
W
I"' w
Z z
U W
W
Q ~~.
~~
~~
~~
a N
Q E
0
L U O
/ R ` C
V °'
n, E
E o
0
o '>
a- w
(~ o ~•
c
v J ~
c
a
rn
c
c
.~
^ ~
c
Yelm Avenue Walgreens Traffic Impact Analysis
II. PROJECT DESCRIPTION
Development Proposal
The Yelm Avenue Walgreens project consists of construction of a 14,490 square foot Walgreen's
drugstore with adrive-through pharmacy and 57 parking spaces. The site is located on 1.86 acres
at the northwest corner of the intersection of SR 507 and Bald Hills Road-Creek Street. Access
to the site will be from two driveways, one from Yelm Avenue (SR 507) and one from Creek
Street. The project site is located within the C-1 Commercial Zone in Yelm's Mixed Use
Downtown District. A drugstore with drive-through is a permitted use in this zone.
The site is currently occupied by a 10-unit apartment complex and a small commercial building.
All of the existing buildings will be removed prior to constructing the Walgreens project. There
are several existing driveway access points on Yelm Avenue and Creek Street serving the subject
property. The existing accesses will be replaced by the two access points shown on the proposed
site plan.
A reduced copy of the site plan showing the proposed building configuration and internal
roadway network is provided on Figure 2.
The Shea Group - a Parametrix company
July, 2001 Page 3
N
raw-s~ ~
Z
CREEK STREET
W
O ~
~ N
0
C~ ~
.~
~_
~~~~~ ~ !%
~~ ; ~,-~
~~~ / ~I/
J 7
I f
•~ I
s, o`~
i,
j~. !;'r
/ `~.
/%, i ?
0
z N
~_
J
Q
Z
a
Z ~
Q
a"
~~
d~
W ~
f" ~
N ~
~ ~
~ ~
a~
ZW
W
~~
_~
W ~
W
~ Z
W
Q
J
W
Q a
U
X
.~.
u
0
a
O
W
^
y!
N
U
N ~
O
C
O~
~~ ~
W
C
C i
d i
Yelm Avenue Walgreens Traffic Impact Analysis
III. BACKGROUND INFORMATION
Area Land Uses
Prairie Plaza, a strip mall containing several small retail uses, is located immediately north of the
project site. A Chevron station is situated across Creek Street from the project site, and an Arco
station is located at the southeast corner of the Yelm AvenueBald Hill Road-Creek Street
intersection. A mobile home park is located across Yelm Avenue from the subject property.
Other commercial uses are located along Yelm Avenue.
Roadway Inventory
Creek Street NE is a two-lane roadway running north-south between SR 507 (Yelm Avenue) and
103rd St. It is designated a commercial collector, with shoulders on both sides of the road and a
sidewalk on the east side. There is a stop sign on Creek St. at 103rd St. SE. The intersection at
Yelm Avenue and Creek St. is signalized. There is a center turn lane along the portion of Creek
Street near Yelm Avenue, extending from the intersection to Prairie Plaza. The posted speed
limit is 25 mph.
103rd Avenue
103rd Avenue is a two-lane roadway which runs east-west between Yelm Avenue and Bridge St.
SE. In the project vicinity, 103rd Avenue has no shoulders, and the posted speed limit is 25 mph.
There is a stop on 103rd Avenue at Grove Rd. SE. The intersection at Yelm Avenue is under stop
sign control.
Morris Road
Morris Road begins just south of the intersection of SR 507/Creek St. NEBaId Hill Road SE,
and runs southerly from its intersection with Bald Hill Road. It is a two-lane roadway with
paved shoulders. There is a stop-sign on Morris Road at the intersection with Bald Hill Road.
Bald Hills Road
Bald Hills Road runs generally east-west from the intersection of SR507/Creek St. NE. It is a
two-lane roadway with paved shoulders.
Yelm Avenue (SR 507)
Yelm Avenue (State Route 507) is a State facility classified as an urban arterial. There are no
bike lanes or sidewalks in the immediate vicinity of the project site. East of the project site,
Yelm Avenue has two lanes and a posted speed limit of 35 mph. West of the site, the roadway
has athree-lane section and a speed limit of 25 mph.
Traffic Volume Data
Trafficount, a local traffic data collection firm, provided evening peak period turning movement
counts for the following locations:
• Yelm Avenue/First Street
• Yelm AvenueBald Hill Road-Creek Street
The Shea Group - a Pararnetrix company
July, 2001
Page 5
Yelm Avenue Walgreens Traffic Impact Analysis
These traffic volumes were used for our base year operations analysis, and as the basis for future
year traffic volume projections. Figure 3 represents the 2001 base year peak hour traffic
volumes for this study. The turning movement count worksheets are provided in Appendix A.
Public Transportation
Public Transit is provided to the site by Intercity Transit via Yelm Avenue. Two routes serve the
area: The South County Special, Route 92, provides mid-day service one day a week, on Friday.
Route 94 provides two morning and two afternoon commuter hour runs to Yelm on weekdays,
terminating at the Nisqually Plaza on Yelm Avenue.
The Shea Group - a Parametrix company
July, 2001
Page 6
Yelm Avenue Walgreens Traffic Impact Analysis
IV. PROJECT TRAFFIC CHARACTERISTICS
The two project-related characteristics having the most effect on area traffic conditions are peak
hour traffic generation and the directional distribution of these traffic volumes.
Traffic Generation
Vehicle trip generation was calculated for this project using the current edition of the Trip
Generation report by the Institute of Transportation Engineers (ITE). The Pharmacy/Drugstore
with Drive-Through Window land use (land use code 881) was determined to be the most
applicable to the project. The trip generation rate used for this analysis is shown below in Table
1.
Table 1
Trip Generation Characteristics
Yelm Avenue Walgreens
ITE Land Use PM Peak Hour
(L.U. Code) Daily Trip Rate Trip Rate Inbound Outbound
PharmacylDrugstore with
Drive-Through Window 88.16 per 1,000 10.40 per 1000
(L.U. 881) square feet square feet 49% 51%
The total trip generation expected from this development is calculated by applying the total
square footage to the appropriate trip generation rate. It is expected that some of the project
traffic will constitute pass-by traffic as described below.
Pass-by Traffic
A project such as a drugstore with adrive-through pharmacy tends to attract a large amount of
traffic from people already driving on the area roadways. These trips are not new trips added to
the local roadways (primary trips) but represent "pass-by" trips according to the following
definition:
Pass-bv Triers are trips made as an intermediate stop from an origin to a primary
destination (i.e. stopping to shop on the way home from work) by vehicles
passing directly by the project driveway.
Documentation provided by the Institute of Transportation Engineers (ITE) indicates land uses
such as pharmacies with drive-through windows commonly experience pass-by rates of 50 to
60%. In previous discussions between the developer and the City of Yelm, a pass-by rate of 50%
was agreed to. For this analysis, we have reduced the total project trips by 50% to reflect the
occurrence of pass-by trips. Project traffic volumes after this reduction represent the "new-to-
network" trips. The project trip generation calculations are shown on Table 2.
The Shea Group - a Parametrix company
July, 2001 Page 8
Yelm Avenue Walgreens Traffic Impact Analysis
Table 2
Project Trip, Generation
Yelm Avenue Walgreens
PM Peak Hour Trip Generation
Total
Driveway New-to-
Land Use (LU) Unit (SF) Trips Network Trips Enter Exit
Pharmacy/Drugstore with
Drive-Through Window
(L.U.881) 14,490 152 76 37 39
Trip Distribution
The vehicle directional trip distribution to and from the site will distribute onto the area
roadways based primarily on the following factors:
• the area street system characteristics
• current travel patterns on the area roadways
• the proposed access system for the project
• locations of residential areas, employment bases, and shopping/commercial centers
For this analysis, the directional distribution of traffic to and from the proposed project was
estimated using the regional transportation model. The Thurston Regional Planning Council
(TRPC) created the area-wide transportation model with cooperation from the local jurisdictions
within the County. The model, developed using the Tmodel2 software package, has been
calibrated to accurately represent the existing vehicle travel patterns throughout the entire
county.
In the transportation model, the county-wide transportation network is divided into 483 "Traffic
Analysis Zones" (TAZs). The Yelm Avenue Walgreens property is located within TAZ number
397. A distribution analysis was performed for this project by conducting a "Select Zone
Analysis" for TAZ 397. This feature of the TMode12 software package allows all of the traffic
into and out of a particular zone to be isolated and shown separately from the rest of the traffic
on the network. This graphically shows the percentage of vehicles currently using each of the
available routes into and out of the area (SR 507, Morris Road SE, Bald Hill Road SE, Creek
Street, 103rd Street, etc.). From this information we calculated distribution percentages for future
traffic from the proposed Yelm Avenue Walgreens project. The "pass-by" trips were distributed
onto the roadway network based on current PM peak hour directional traffic volumes on Yelm
Avenue and Bald Hill Road. The new-to-network distribution for this project is shown on
Figure 4, with a site area detail, including pass-by trips, on Figure 5.
The Shea Group - a Parametrix company
July, 2001 Page 9
0
.~ ail ~ ~.... ~ ~ N
z Q
0
M
O ~
O
~'~' 4 GROVE RD
~
r W ~ ~
~ N
v
U ~
¢ QW~ ~
~ ~
a
~- cn -- co
F ~
w z
~ ~ r
~
0 Y
0 ~
~
t4
Q
~ 0
m M ~
~-
~ 2 CREE
w
w
o K ST
Z ~-
z a
N
C~ I ~ PLAZA DR
I ~ ~~
IW- Z 0] ~
N Z ~ ~ 2 VANCIL RD
~ L~
~
~~ ~ ~~
~
~~
~ ~ CLARK RD
^~ 1 ~ ~
o ~ ~
~ N
~~~ ~
~ ^
~
s
~s
~
R
0 0
~
~
~ ~~ ~
~I ~s
`~ y~x ~ O
01 1~ 11~ Z
~ `o ~
~ s W
J~ ~`S'J -1
,1~
v~ ~~
~~" '~S
~S!
~
~
~
O
~ ~
l"'
~p
0
~" 2 MORRIS RD
2 --
0
L!~
O
O
~ i
v
~ N
c
O 0 U
0 ~
(~ o 0
x aci
V U
J u c
(U ~ o
o !-
o ~
y c
r~ a
V J ~
c
~~ ~
o+
.~
~~ c
a+
^I ~
c
w
0
z ~
/a ~I vi
,nrti.. ~
Z
~-- 6
~- 8 CREEK ST `~ 2
8 -~ 6 -- ~-
N
0
w
J
Q
N
PLAZA DR y ~ 2
~ 2 7, f~
~
j
1
U
Q
Q
Q N ,~
r
L~ ~ p~ O~ ~ O~ ~
a ~ ~ ~ ~ ~
~
Y p d p } p
~
O Z
~ ~
H Z
~ Q
~ Z
~ W
>
W O O O
~ Q
Q ~ m M m m~ j m ~
~
w Z O
O ~
N p
O ~
p O
0 w
r
Z ~
O Q J
W F- p a p ~ p
~
W
Z
~
p
Z O
F-
Z
O
.~
o
~ O O r7 ~ OM
F- Z m ~] m
~ Z Z Z
~ I
M
r 13(11)
8'~ h ~ (12)101
(11)6 --
_
M
N
~ v ~~ ~~1
~ ~ ~~ /
U
~
w
~ >
~ ~ (0)O.t
(16)15
0_ o Z ~~ ~
011
~
~~ ~
A
~1
O
~ ~~1
t
O
r
W ~ I
r
~
J
Z
M
d
W
V ~
~ ~
Q ~
Q
~-
(3) W ~
3
`~ (1590) ~ 6 F`
~
W l
~
c" ~
~1 ~ ~ (30~) 6 -~- ~ H
N w
w
~-Oa ~ ~
~~
Z ~
W'
W
~ ;
~
w'
W ¢~
N ~~
W
>- 1
N
a 0
o z
IIAA
W !
nn
V
J
Q ^h
^~
z
W
Q
k-
Z
W
U
~ W W
w
~ N na a
~ w F- Z
J ~ Z O
~ J U ~
~ o ~ m
~ N
~ a ~ °
~ U
F-- ~ m ~
Q f--' F- Q
~ N ~ ~
W Q] ~ ~]
U
W N W N
F- Q ~ Q
v> a r- a
~ ~' °
x
..
X X
v
NI
U
C
~ ~
O ~ U ~
a N
S.. o
/~ V
V x a~i ~
w E~
m c~
~ oI
o :~
a° c
w
o .
~ ~~
~,
~~
c
-a°~
c;
a`~
.~
°' I
~~
Yehn Avenue Walgreens Traffic Impact Analysis
V. FUTURE TRAFFIC CONDITIONS
Roadway Improvements
The City of Yelm, in conjunction with the Washington State Department of Transportation
(WSDOT), has identified several improvements that will be required to maintain acceptable
traffic flows along the SR 507 corridor. The initial phase of improvements has been completed,
and the City has received a grant to widen Yelm Avenue (SR 507) to urban arterial standards
between 3rd Street and Five Corners (the intersection of Yelm AvenueBald Hill Road-Creek
Street).
In addition to the Yelm Avenue improvements, the City of Yelm has identified other roadway
improvements in the project area. These include the following;
• 103rd St. from West Road to Creek Street -widen to urban standards
• West Road from 4r'' Avenue to 103rd St. -widen to minor arterial standards
Pipeline Development Projects
A pipeline development project is defined as a development in the project area that is either
under construction, approved for construction, or in the permitting process. In the study area,
three pipeline projects were identified that will add traffic to the study area. A fast food
restaurant will be constructed on Yelm Avenue at Plaza Drive, and a 48-unit apartment complex
is planned on Vancil Road. The third pipeline project is Prairie Park mixed use development.
The first phase of Prairie Park, a cinema, has been completed. Phase 2 consists of
retail/commercial uses. Table 3 below shows an estimate of the new-to-network trips these
projects will add to the area roadway network.
Table 3
Pipeline Projects
PM Peak Hour Trip. Generation
Project New-to-Network Trips Inbound Outbound
Apartments 29 19 10
Fast Food Restaurant 42 21 21
Prairie Park Phase 2 263 124 139
Total 334 164 170
The traffic volumes in Table 3 were distributed onto the roadway network using the same
methodology described for projected Yelm Avenue Walgreens site traffic. The total pipeline
traffic volumes used for this analysis are shown on Figure 6.
The Shea Group - a Parametrix company
July, 2001 Page 12
iar-aw N
H ~
Z ~ ~O
v
v Q
~'~ ~Fy
~- 145 `v
_
j ~, j 26
CREEK ST ~-
190 ~ f~ ~- ~ ~ MORRIS RD
Z I I N N
~j~
~~ ~~
in r
~~
U
_
W~ ',
~
o~ _
~ ° 7'
~~`
PLAZA DR
VANCIL RD
~~~
S S` ~~~~~
~~
~~
0,
~~
v~~ S~sJ~
~ ~`~~s^
~l)
Q
LI__I
LLI
N ~
W W
~ ~
J
O ~
> ~
O
U_ 2
W Y
L~ Q
Q W
d
~ ~
~ ~
O
= z
Y Q
Q
a cn
d. J
x I
X
Yelm Avenue Walgreens Traffic Impact Analysis
Projected Traffic Volumes
In addition to traffic from the identified pipeline developments, it is anticipated that background
traffic growth will occur within the study area. To estimate the traffic volumes that will be
present at the study intersections during the 2002 project horizon year, we applied a growth rate
of 4% to the base year traffic volumes. The 4% growth rate is based on historical growth trends
and was determined by the City of Yelm. The projected 2002 traffic volumes without the Yelm
Avenue Walgreens project are shown on Figure 7. We then added the estimated traffic from the
proposed Yelm Avenue Walgreens project to calculate the horizon year total traffic assignment.
The projected 2002 traffic volumes including project site traffic are shown on Figure 8.
The Shea Group - a Parametrix company
July, 2001 Page 14
vi
z
~O
1` ~ ~
~ ~~o
~~
MORRIS RD
~`
S sS~
l
1 ~
~~
~~
~v~
.~.
0
v
W
Q
~ VANCIL RD
N N
W ~
~ ~
J ~.
1
U_ 2
4- Y
l~ Q
Q W
~ W
~ ~
O
2 Z
Y Q
Q F
W
a N
~ w
a ~
x I
x
x
v~
r
z
~-- 145
0
Q
CREEK ST ,~ 25
190 -. h ~
10 ~, o
w
t-
Nr
F-
U ~
W
o~
a°
PLAZA DR
o`n~n X25
~'n~' x-55
~! ~, y r 265
so ~' ~ } r-
90 --
60~ o ~
~~ M
~
~O
~
~
_ 1` ~
30 7, ,,~0~
VANCIL RD
~~
~~
S ~ ~ ~ ~~
s0``S'~ ~Op`~'~
~~
X01 ~~~ ~O
h ~
~~~ o
S
~~v"~ WSJ ~~
~s
'~S
z
W
W
J
N N
W ~-
~ ~
J W.
0 ~
0
U 2
~ Y
Q
~ W
r a
~ ~
0
_ z
Y Q
Q
W
d N
~ w
a ~
X I
X
~o
v
O
~~v
MORRIS RD
N
V
~ ~~
~,
p Vi
O a NI
L o of
U C
x a~ ~
EI.
~ ~ ~~
o;
a ~€
° c~
a w;
~/~ o •
cI
V J °1
'c
o~
o~
d
c!
'rn;
^ °' ;
c~
w.
Yelm Avenue Walgreens Traffic Impact Analysis
VI. TRAFFIC OPERATIONS ANALYSIS
Traffic analyses were conducted to determine any capacity deficiencies within the study area for
the base year 2001 and project completion 2002 horizon year. The acknowledged source for
determining overall capacity for arterial segments and independent intersections is the current
edition of the Highway Capacity Manual. Capacity analyses were completed for the base year
2001 and projected 2002 peak period traffic volume scenarios.
Capacity analysis results are described in terms of Level of Service (LOS). LOS is a qualitative
term describing operating conditions a driver will experience while traveling on a particular
street or highway during a specific time interval. It ranges from A (very little delay) to F (long
delays and congestion). Level of Service C is the concurrency standard for the City of Yelm,
with the exception of the designated "urban core" area, which includes the Yelm Avenue
corridor. The City has adopted a lower service level (LOS F) for this area of the city.
The capacity analyses were completed for traffic volume conditions expected to occur during the
evening peak period at all study intersections. The analyses were performed using Highway
Capacity Software for stop sign controlled intersections and Signa12000 software for the
signalized intersections. The capacity analysis worksheets are provided in Appendix B.
Following is a description of the level of service analysis for the study intersections.
The Shea Group - a Parametrix company
July, 2001
Page 17
Yelm Avenue Walgreens Traffic Impact Analysis
Signalized Intersections
Yelm Avenue/First Street
This operates under actuated traffic signal control with protected left-turns at each approach.
The eastbound and westbound approaches on Yelm Avenue each have single exclusive lanes for
each movement. The northbound and southbound approaches on First Street provide exclusive
left-turn lanes and shared through-right lanes. The intersection currently operates at a LOS D
condition during the evening peak hour. By the 2002 horizon, the intersection will degrade to a
LOS E condition with the addition of background and pipeline traffic growth. After completion
of the proposed Walgreens project the intersection delay will increase slightly, but the
intersection will remain at a LOS E condition.
There is an existing concern at this intersection involving the turning radius of the westbound to
northbound right-turn movement. Because of the limited turning radius, trucks occasionally
cross the sidewalk with the back axles of the trailer. The awning on the adjacent building has
been damaged by encroaching trucks. The City, in conjunction with WSDOT, has plans to
improve the intersection by re-striping the southbound approach on First Street to narrower 11-
foot lanes, and to move the southbound left-turn lane stop bar a few feet further back from the
intersection. These improvements will give trucks more room to maneuver while making their
turn. Even with these improvements, it is anticipated that larger vehicles may encroach onto the
sidewalk area, but the number of occurrences will be reduced.
As mentioned previously, the Yelm Avenue corridor has an adopted LOS standard of LOS F.
The City, in conjunction with WSDOT and the Federal Highway Administration (FHWA), has
plans to construct two bypass routes (known as Y-2 and Y-3) around the downtown area.
Construction of the bypass routes will reduce the traffic demand on Yelm Avenue and will
improve the operation of the intersections through the downtown core area. The two bypass
routes are in the preliminary planning stages with no specific construction timeline.
The following table summarizes the LOS Analysis results for the intersection:
Table 4
Yelm Avenue/First Street
LOS Operational Summary
PM Peak Hour
Base Year 2001 Projected 2002 W/O
Project Projected 2002 with
Project
Approach LOS (Delay) LOS (Delay) LOS (Delay)
Southbound D (50) E (67) E (67)
Northbound D (45) D (55) E (57)
Westbound D (36) D (43) D (44)
Eastbound D (44) E (64) E (66)
Total Intersection D (42) E (56) E (58)
The Shea Group - a Parametriz company
July, 2001 Page 18
Yelm Avenue Walgreens Traffic Impact Analysis
Yelm Avenue/Bald Hill Road -Creek Street
This intersection operates under actuated traffic signal control. The east-west approaches on
Yelm Avenue operate with protected left-turns and concurrent through movements. The
northbound and southbound approaches (Bald Hill Road and Creek Street, respectively) operate
under split phase timing. The eastbound and westbound approaches on Yelm Avenue each have
single exclusive lanes for each movement. The northbound and southbound approaches on Creek
Street and Bald Hill Road provide exclusive left-turn lanes and shared through-right lanes.
For existing 2001 PM peak hour conditions, the intersection operates at a LOS C condition. By
the 2002 horizon, with the addition of background and pipeline development traffic, the
intersection will remain at LOS C. When the Walgreens project is completed in 2002, overall
delay at the intersection will increase slightly, but the intersection will remain at a LOS C
condition.
The following table summarizes the LOS analysis for the intersection.
Table 5
Yelm Avenue/Bald Hill Road -Creek Street
LOS Operational Summary
PM Peak Hour
Base Year 2001 Projected 2002 W/O
Project Projected 2002 with
Project
Approach LOS (Delay) LOS (Delay) LOS (Delay)
Southbound D (50) D (49) D (38)
Northbound D (38) D (45) D (45)
Westbound C (24) C (26) C (32)
Eastbound C (23) C (25) C (30)
Total Intersection C (28) C (30) C (34)
The Shea Group - a Parametrix company
July, 2001 Page 19
Yelm Avenue Walgreens Traffic Impact Analysis
Site Driveway Analysis
As described previously, the proposed project will have two access points: one onto Yelm
Avenue and one onto Creek Street. The following is a description of the anticipated operation of
the project driveways.
North Site Driveway/Creek Street
This driveway will be located on Creek Street approximately 330 feet north of Yelm Avenue.
The intersection will function as astop-controlled `tee' intersection. Along the project frontage
Creek Street has a single through lane in each direction, and atwo-way center turn lane. Just
north of the proposed driveway the roadway narrows to two lanes. At project completion the
driveway is expected to operate at a LOS B for the eastbound left-turn movement.
South Driveway/Yelm Avenue
This access will be located on Yelm Avenue approximately 380 feet west of Creek Street. The
intersection will function with stop control for the southbound driveway approach. Based on the
anticipated traffic volumes, the left-turn movement from the site driveway would operate at a
LOS F condition. The right-turn movement from the driveway access would operate at a LOS B
condition.
Because of the poor level of service anticipated for the left-turn movement at this driveway, we
have evaluated the potential safety of that movement from the driveway access. There are a
number of factors that indicate that prohibiting the southbound left-turn movement would
improve the overall safety and flow of the site.
• Poor Level of Service. Because of the high traffic volume on Yelm Avenue, the southbound
left-turn movement from the site driveway would operate at a poor LOS F condition at
project completion in 2002.
• Conflict with Eastbound Vehicles on Yelm Avenue at Creek Street. The proposed site
driveway location is approximately 360 feet west of the eastbound through lane stop bar at
Creek Street. Based on vehicle "queuing" estimates (the number of vehicles waiting during
the red phase of the signal) shown on the Level of Service Worksheets in Appendix B,
vehicles in the eastbound through lane will regularly queue past the proposed Walgreens
driveway. This condition would make it very difficult for vehicles to turn left onto Yelm
Avenue, even when gaps in the westbound traffic flow occur.
• Internal Site Circulation. The site design will accommodate a significant vehicle queue for
the southbound approach at this driveway. However, the internal access from the south
parking area to the Yelm Avenue Site Driveway would be blocked by a queue of two or three
vehicles waiting to turn left onto Yelm Avenue.
• Other Option Available. The site access to Creek Street would allow another option for
vehicles with a destination eastbound on Yelm Avenue or southbound on Bald Hill Road.
Rather than turn left from the site driveway on Yelm Avenue, vehicles could circulate to the
Creek Street access and utilize the existing traffic signal at the Yelm Avenue/Creek Street
intersection.
The Shea Group - a Parametrix company
July, 2001 Page 20
Yelm Avenue Walgreens Traffic Impact Analysis
Based on the factors described above, we recommend that the south site driveway onto Yelm
Avenue be constructed to allow full movements inbound, but be limited to only right-turn
movements outbound. The additional traffic load at the Creek Street driveway access is reflected
in our site-generated traffic distribution.
Table 7 shows a summary of the operations analysis results for all study intersections. The
capacity analysis worksheets are provided with this report.
Table 7
Level of Service (LOS) Summary
PM PeakHour
Existing Projected 2002 Volumes
Intersection
Control Type 2001
Volumes Without
Project
With Project
Yelm Avenue/1St Street Signal D (42) E (56) E (58)
Yelm Ave/Creek Street Signal C (28) C (30) C (34)
Site Driveway/Creek Street Stop Sign B (11)
Site Driveway/Yelm Avenue Stop Sign B (11)*
*reflects-the. minor street right turn movement.
The Shea Group - a Parametrix company
July, 2001 Page 21
Yelm Avenue Walgreens Traffic Impact Analysis
VII. MITIGATION
Traffic generated by the proposed project will have a measurable impact on the area roadways
and intersections. Analysis described in the previous section indicates that the area roadways
can accommodate the additional traffic generated by the proposed Yelm Avenue Walgreens.
Although the project will not create any unacceptable traffic impacts, the project proponent will
be responsible for some mitigation to offset the addition of traffic to the area roadway network.
Construct Frontage Improvements
The project developer will be responsible for half-street frontage improvements along the
property frontage on Creek Street and Yelm Avenue.
Pay Cif of Yelm Transportation Facility Charge (TFC)
To help fund system-wide roadway improvements, the developer of the Yelm Avenue Walgreens
will be responsible for a transportation facility charge payment to the City of Yelm. The actual
amount will be based on the current city ordinance and will be calculated by City staff.
The project developer may be eligible for an existing traffic use credit based on the current
apartment and small business usage of the property. An analysis of the existing trip generation
of the site would be required to determine the actual traffic credit allowed.
Construct the South Site Driveway on Yelm Avenue to Prohibit Left-Turn Movements Out of the
Site
This driveway location should be designed to prohibit southbound left-turns from the parking
area onto Yelm Avenue. The design would include raised curbing and signage, and would
require approval of City of Yelm Public Works staff prior to construction.
The Shea Group - a Parametrix company
July, 2001 Page 22
Yelm Avenue Walgreens Traffic Impact Analysis
VIII. CONCLUSIONS
The Yelm Avenue Walgreens proposal will consist of one 14,490 square foot drugstore with
drive-through pharmacy and 57 parking spaces on a 1.86 acre site at 10540 Hwy 507 SE. This
development, which is consistent with the City's land use zoning, will add traffic to the local
roadway network. This study has analyzed the peak traffic potential to/from the site following
construction. Results of the analysis indicate that the planned roadway improvements within the
area will accommodate the increase in traffic generated by the proposed project.
The Shea Group - a Parametrix company
July, 2001 Page 23
Yelm Avenue Walgreens Traffic Impact Analysis
Appendix A
Turning Movement Count Worksheets
The Shea Group - a Parametrix company Appendix A
July, 2001
YELM, WASHINGTON
1ST ST
YELM AVE
LOC # 01P SHG01199M
TRAFFICOUNT, INC.
4820 YELM HWY B-195
LACEY, WASHINGTON 98503
360-491-8116
!]rnnnc Drinfnri_ DRIMARV
File Name : SHG20001P
Site Code :00000001
Start Date :07/19/2001
Page No : 1
1ST ST YELM AVE 1ST ST YELM AVE
From North From East From South From West
StartTime Right Thru Left Truck App. Right Thro Left Truck APp' Right Thru Left Truck App' Right Thru Left Truck App.
T
t
l Fxclu.
l
T
t Inclu.
T
l
t Int.
T
t
l
Total Total Total a
o o
a o
a o
a
Factor 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
04:OOPM 24 12 14 0 50 9 97 34 3 140 67 17 37 2 121 29 114 25 3 168 8 479 487
04:15 PM 25 9 14 0 48 6 94 42 4 142 38 10 22 3 70 25 134 44 2 203 9 463 472
04:30 PM 27 15 14 0 56 5 111 45 3 161 46 21 29 4 96 23 123 35 1 181 8 494 502
04:45 PM 24 19 10 0 53 5 87 38 1 130 52 15 28 1 95 26 131 22 4 179 6 457 463
Total 100 55 52 0 207 25 389 159 11 573 203 63 116 10 382 103 502 126 10 731 31 1893 1924
05:00 PM 24 13 SO 1
05:15 PM 24 8 21 1
05:30 PM 12 12 13 0
05:45 PM 17 13 12 0
3 181
3 176
2 208
1 179
Total 77 46 56 2 179 32 398 170 9 600 ~ 160 80 112 9 352 ( 75 531 138 9 744
Grand Total 177 101 108 2 386 57 787 329 20 1173 363 143 228 19 734 178 1033 264 19 1475
Apprch % 45.9 26.2 28.0 4.9 67.1 28.0 49.5 19.5 31.1 12.1 70.0 17.9
Total % 4.7 2.7 2.9 10.2 1.5 20.9 8.7 31.1 9.6 3.8 6.1 19.5 4.7 27.4 7.0 39.1
11 473 484
7 461 468
5 499 504
6 442 448
29 1875 1904
60 3768 3828
1.6 98.4
1ST ST
From North YELM AVE
From East 1ST ST
From South YELM AVE
From West
StartTime Right Thru Left App. Total Right Thrlt Left App. Total Right ThN Left App. Total Right Thru Left App. Total
reaK Hour rrom u4:vu rm to ua:4a rm - reaa i or i
Intersection 04:00 PM
Volume 100 55 52
Percent 48.3 26.6 25.1
04:30Valume 27 15 14
Peak Factor
High Int 04:30 PM
Volume 27 15 14
Peak Factor
Peak Hour From 04:00 PM to 05:45 PM -Peak 1 of 1
By Approach 04:30 PM
Volume 99 55 55
Percent 47.4 26.3 26.3
High Int. 04:30 PM
Volume 27 15 14
Peak factor
47 6 94 42 5 142 44 21 38 2 103 20 131 30
53 9 94 49 2 152 34 21 25 1 80 16 128 32
37 11 112 37 0 160 52 20 22 3 94 21 144 43
42 6 98 42 2 146 30 18 27 3 75 18 126 33
207 25 389 159
4.4 67.9 27.7
56 5 111 45
04:30 PM
56 5 111 45
0.924
05:00 PM
209 32 398 170
5.3 66.3 28.3
05:30 PM
56 11 112 37
0.933
573 203 63 116
53.1 16.5 30.4
161 46 21 29
04:00 PM
161 67 17 37
o.8so
04:00 PM
600 203 63 116
53.1 16.5 30.4
04:00 PM
160 67 17 37
0.938
382 103 502 126
14.1 68.7 17.2
96 23 123 35
04:15 PM
121 25 134 44
o.76s
04:15 PM
382 94 519 131
12.6 69.8 17.6
04:15 PM
121 25 134 44
0.789
InL Total
731 1893
181 494
0.958
203
o.soo
744
203
0.916
YELM, WASHINGTON
1ST ST
YELM AVE
LOC # 01P SHG01199M
1ST ST
T al
14 421
Right Thru Left
~ M
~ ~ C
~ -'
u
Nortn ~ ~,
W ~
m
g G u°~ L-/ /19101 4:00:00 PM ~-- c `'' D
w ~ /19/01 4:45:00 PM m
Y ~ rr r.
O t
~ ~ ~ ~ IM ~~
o rr `° ~~~fff
~, T ~-
T
1
L7
Out In Total
1ST ST
From North YELM AVE
From East 1ST ST
From South YELM AVE
From West
StartTime Right Thru Left App. Total Right Thru Left App. Total Right Thru Left App.TOtal Right Thru Left App.
Peak Hour From u4: W PM to Ub:4b rm - PeaK l or 1
Intersec0on 04:00 PM
Volume 100 55 52
Percent 48.3 26.6 25.1
04:30 Volume 27 15 14
Peak Factor
High Int. 04:30 PM
Volume 27 15 14
Peak Factor
TRAFFICOUNT, INC.
4820 YELM HWY B-195
LACEY, WASHINGTON 98503
360-491-8116
207 25 389 159
4.4 67.9 27.7
56 5 111 45
04:30 PM
56 5 111 45
0.924
573 203 63 116
53.1 16.5 30.4
161 46 21 29
04:00 PM
161 67 17 37
0.890
File Name : SHG20001P
Site Code :00000001
Start Date : 07/ 19/2001
Page No : 2
382 103 502 126
14.1 68.7 17.2
96 23 123 35
04:15 PM
121 25 134 44
0.789
Total Int. Total
731 1893
181 494
0.958
203
0.900
YELM, WASHINGTON
NE CREEK ST
YELM AVE
LOC# 02P SHG01199M
TRAFFICCUNT, INC.
4820 YELM HWY 6-195
LACEY, WASHINGTON 98503
360-491-8116
l3 rni~nc Prin4cri_ PRIMGRY
File Name : SHG20002P
Site Code :00000002
Start Date :07/19/2001
Page No :1
NE CREEK ST YELM AVE BALD HILL RD SE YELM AVE
From North From East From South From West
StartTime Right Thru Left Truck App' Right Thru Left Truck App. Right Thru Left Truck App' Right Thru Left Truck App'
T
t
l Fxclu.
Total Inciu.
Totai Int
Totai
Total Total Total o
a
factor 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
04:00 PM 14 12 9 0 35 10 113 li 1 134 8 12 36 2 56 73 92 14 2 179 5 404 409
04:15 PM 21 13 12 0 46 11 119 10 6 140 6 10 40 3 56 88 89 19 8 196 17 438 455
04:30 PM 11 17 14 0 42 10 107 14 1 131 11 14 53 2 78 64 103 SO 2 177 5 428 433
04:45 PM 20 19 20 5 59 12 116 9 3 137 12 14 53 2 79 66 117 19 5 202 15 477 492
Total 66 61 55 5 182 43 455 44 11 542 37 50 182 9 269 291 401 62 17 754 42 1747 1789
05:00 PM 17 14 13 1 44 8 127 14 4 149 7 9 60 0 76 89 123 9 4 221 9 490 499
05:15 PM 9 19 12 0 40 14 111 11 3 136 5 11 67 1 83 82 117 7 3 206 7 465 472
05:30 PM 12 20 10 0 42 12 115 11 1 138 2 13 43 0 58 88 118 13 4 219 5 457 462
05:45 PM 20 22 9 1 51 4 117 13 1 134 7 12 57 1 76 84 92 13 8 189 11 450 461
Totai 58 75 44 2 177 38 470 49 9 557 21 45 227 2 293 343 450 42 19 835 32 1862 1894
Grand Total 124 136 99 7 359 81 925 93 20 1099 58 95 409 11 562 634 851 104 36 1589 74 3609 3683
Approh % 34.5 37.9 27.6 7.4 84.2 8.5 10.3 16.9 72.8 39.9 53.6 6.5
Total % 3.4 3.8 2.7 9.9 2.2 25.6 2.6 30.5 1.6 2.6 11.3 15.6 17.6 23.6 2.9 44.0 2.0 98.0
NE CREEK ST
From North YELM AVE
From East BALD HILL RD SE
From South YELM AVE
From West
StartTime Right Thru Left App. Total Right Thru Left App. Total Right Thru Left App. Total Right Thru Left App
reaK Hour rrom ug:uu rm m uo:vo rm - reaR i ui a
Intersection 04:45 PM
Volume 58 72 55
Percent 31.4 38.9 29.7
05:00 Volume 17 14 13
Peak Factor
High Int. 04:45 PM
Volume 20 19 20
Peak Factor
Peak Hour From 04:00 PM to 05:45 PM -Peak 1 of 1
By Approach 04:15 PM
Volume 69 63 59
Percent 36.1 33.0 30.9
High Int 04:45 PM
Volume 20 19 20
Peak Factor
185 46 469 45
8.2 83.8 8.0
44 8 127 14
05:00 PM
59 8 127 14
0.784
04:45 PM
191 46 469 45
8.2 83.8 8.0
05:00 PM
59 8 127 14
0.809
560 26 47 223
8.8 15.9 75.3
149 7 9 60
05:15 PM
149 5 li 67
0.940
04:30 PM
560 35 48 233
11.1 15.2 73.7
05:15 PM
149 5 11 67
0.940
296 325 475 48
38.3 56.0 5.7
76 89 123 9
05:00 PM
83 89 123 9
0.892
04:45 PM
316 325 475 48
38.3 56.0 5.7
05:00 PM
83 89 123 9
0.952
.Total Int Total
848 1889
221 490
0.964
221
0.959
848
221
0.959
YELM, WASHINGTON
NE CREEK ST
YELM AVE
LOC# 02P SHG01199M
185 46 469 45
8.2 83.8 8.0
44 8 127 14
05:00 PM
59 8 127 14
0.784
TRAFFICOUNT, INC.
4820YELM HWY B-195
LACEY, WASHINGTON 98503
360-491-8116
NE CREEK ST
From North YELM AVE
From East BALD HILL RD SE
From South YELM AVE
From West
Start Time Right Thru Left App Total Right Thru Left App. Total Right Thru Left App. Total Right Thru Left App.
reaK Hour rrom ua:uu rm to uo:v5 rm - reaK i or i
Intersection 04:45 PM
Volume 58 72 55
Percent 31.4 38.9 29.7
05:OOVOIume 17 14 13
Peak Factor
High Int. 04:45 PM
Volume 20 19 20
Peak Factor
560 26 47 223
8.8 15.9 75.3
149 7 9 60
05:15 PM
149 5 11 67
0.940
File Name : SHG20002P
Site Code :00000002
Start Date : 07/ 19/2001
Page No : 2
296 325 475 48
38.3 56.0 5.7
76 89 123 9
05:00 PM
83 89 123 9
0.892
NE CREEK ST
I 1411
Right Thru Left
:.°. °~'
F°-
~ ~~
W J
Q ~ r ~
r----/
w ~
} ~ ~ L
~ M O)~
C• ~
~°'
~ A {
m
r
~-~ ~ ~ ~ D
m
r
~~ A
North
/19101 4:45:00 PM
!19/01 5:30:00 PM
~ T r
r
2
Out In Total
8AI r) HII L RD SF
Total Int. Total
848 1889
221 490
0.964
221
0.959
Yelm Avenue Walgreens Traffic Impact Analysis
Appendix B
Capacity Analysis Worksheets
The Shea Group - a Parametrix company Appendix B
July, 2001
Yelm Avenue Walgreens TIA 07/26/01
First Street/Yelm Avenue 14:42:38
PM Peak Hour; Existing 2001 traffic volumes
SIGNAL2000/TEAPAC[Ver 1.01.00] - Capacity Analysis Summary
Intersection Averages for Int # 1 - .
Degree of Saturation (v/c) 0.75 Vehicle Delay 42.3 Level of Service D+
-------------------------------------------------------------
Sq 64 ~ Phase l ~ Phase 2 ~ Phase 3 ~ Phase 4 ~ Phase 5
* I ~ + + I ~ ^
~ * i ~++ I ~ ++++~
v ****
I ~ I I ^ I++++ v I I
North
+ ~ * + +
+ ~ * + +
-------------------------
G/C=0.056 ~ G/C=0.044
G= 5.0" ~ G= 4.0"
Y+R= 4.0" Y+R= 4.0"
OFF= 0.0% ~ OFF=10.0%
C= 90 sec G= 70.0 sec
* *,
* *
* *
G/C=0.178
G= 16.0"
Y+R= 4.0"
OFF=18.9%
77.8% Y=2
I I****> I
+++v
-------------------------
G/C=0.144 ~ G/C=0.356
G= 13.0" ~ G= 32.0"
Y+R= 4.0" I Y+R= 4.0"
OFF=41.1% ~ OFF=60.0%
-------------------------
0.0 sec = 22.2% Ped= 0.0 sec
0.0%
---------
Lane ----------------------
(Width/I g/C ~ ---------
Service -----------
Rate Adj --------
~
~ -------
HCM ----
~ L ---------
I Queue
Group
--------- ~ Lanesl Reqd
-------------- Used ~
-------- @C (vph)
--------- @E
---- ~Volume
------- v/c ~
-------- Delay
------- ~ S
---- Model
------ 1~
---
N Approach 50.0 D
---------
~RT+TH --------------
~ 12/1 0.222 --------
0.178 ~ ---------
113 ~ ----
216 -------
~ 172 --------
0.751 ~ -------
48.1 ----
~ D ------
~ 211 ---
ft~
LT
--------- ~ 12/1 0.141
-------------- 1
0.056 ~
-------- 1 ~
--------- 70
---- ~ 56
------- 0.636 ~
------- 55.9
-------- ~*E+
---- ~ 73
------ ft~
---
S Approach 45.1 D
---------
RT+TH --------------
~ 12/1 0.304 -------
0.267 ----------
~ 244 ~ ----
356 -------
300
I -------
0.843 --------
~ 47.8 ----
~*D ------
~ 366 ---
ft~
LT
--------- ~ 12/1 10.170
-------------- 0.144
------- ~ 65 ~
---------- 216
---- 128
------- 0.557
------- ~ 38.8
-------- ~*D+
---- ~ 146
------ ft~
---
E Approach 35.5 D+
-------------------------------------------------------------------------------
RT ( 12/1 0.136 0.356 ~ 315 ~ 405 28 0.069 ~ 19.2 ~ B ~ 22 ftl
TH ~ 12/1 0.328 0.356 ~ 487 ~ 596 433 0.727 ~ 29.6 I C ~ 441 ftf
LT ~ 12/1 '0.197 0.144 ~ 65 ~ 216 178 0.774 ~ 52.2 I*D ~ 223 ft~
-------------------------------------------------------------------------------
W Approach 44.0 D+
--------------------- -
RT ~ 12/1 0.173 --------
0.356 ~ ----------------------------
406 ( 507 I 117 0.231 ~ --------------------
20.6 ~ C+~ 97 ft
TH ~ 12/1 0.392 0.356 ~ 487 ~ 596 ~ 556 0.933 ~ 49.8 ~*D ~ 688 ft
LT ~ 12/1 0.175
----------------------- 0.144 ~
-------- 65 ~ 216 ~ 139 0.604 ~
---------------------------- 40.6 ~ D+~ 161 ft
--------------------
Yelm Avenue Walgreens TIA 07/26/01
First Street/Yelm Avenue 14:42:54
PM Peak Hour; Existing 2001 traffic volumes
SIGNAL2000/TEAPAC[Ver 1.01.00] - Summary of Parameter Values
Intersection Parameters for Int # 1
METROAREA CBD
SIMULATION PERIOD 15
LEVELOFSERVICE C S
NODELOCATION 0 0
QUEUEMODELS 1 90 25 40
Approach Parameters
APPLABELS N E S W
GRADES 0.0 0.0 0.0 0.0
PEDLEVELS 0 0 0 0
BIKEVOLUMES 0 0 0 0
PARKINGSIDES BOTH BOTH BOTH NONE
PARKVOLUMES 10 20 0 20
BUSVOLUMES 0 0 0 0
RIGHTTURNONREDS 0 0 0 0
UPSTREAMVC 0.00 0.00 0.00 0.00
Movement Parameters
MOVLABELS RT TH LT
VOLUMES 100 55 50
WIDTHS 0.0 12.0 12.0
LANES 0 1 1
GROUPTYPES NORM NORM NORM
UTILIZATIONS 0.00 0.00 0.00
TRUCKPERCENTS 2.0 2.0 2.0
PEAKHOURFACTORS 0.90 0.90 0.90
ARRIVALTYPES 3 3 3
ACTUATIONS YES YES YES
REQCLEARANCES 4.0 4.0 4.0
MINIMUMS 5.0 5.0 5.0
STARTUPLOST 2.0 2.0 2.0
ENDGAIN 2.0 2.0 2.0
STORAGE 0 0 0
INITIALQUEUE 0 0 0
IDEALSATFLOWS 1900 1900 1900
FACTORS 1.00 1.00 1.00
DELAYFACTORS 1.00 1.00 1.00
NSTOPFACTORS 1.00 1.00 1.00
SATURATIONFLOWS 0 1287 1593
RT TH
25 390
12.0 12.0
1 1
NORM NORM
0.00 0.00
2.0 2.0
0.90 0.90
3 3
YES YES
4.0 4.0
5.0 5.0
2.0 2.0
2.0 2.0
0 0
0 0
1900 1900
1.00 1.00
1.00 1.00
1.00 1.00
1140 1676
Phasing Parameters
SEQUENCES 64 64
PERMISSIVES NO NO NO
OVERLAPS NO NO NO
CYCLES 90 90 30
GREENTIMES 5.00 4.00 16.00
YELLOWTIMES 4.00 4.00 4.00
CRITICALS 3 9 8
EXCESS 0
LT
160
12.0
1
NORM
0.00
2.0
0.90
3
YES
4.0
5.0
2.0
2.0
0
0
1900
1.00
1.00
1.00
1593
NO
NO
13.00 32.00
4.00 4.00
6 11
RT TH LT
205 65 115
0.0 12.0 12.0
0 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
0 1337 1593
LEADLAGS
OFFSET
PEDTIME
RT TH LT
105 500 125
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1425 1676 1593
NONE NONE
o.o0 1
0.0 0
Yelm Avenue Walgreens TIA
First Street/Yelm Avenue
PM Peak Hour; Projected 2002 volumes w/o project
SIGNAL2000/TEAPAC[Ver 1.01.00] - Capacity Analysis Summary
07/26/01
14:43:12
Intersection Averages for Int # 1 - .
Degree of Saturation (v/c) 0.83 Vehicle Delay 55.8 Level of Service E+
-------------------------------------------------------------
Sq 64 ~ Phase l ~ Phase 2 ~ Phase 3( Phase 4 ~ Phase 5
* ~ ~++ I ~ I
*
v ~ ****~
++++ v
North I <+ ~ <* + +>~ * *> ****>
+ I * + + i * * I i +++v
* * *
-------------------------------------------------------------
G/C=0.056 ~ G/C=0.044 ~ G/C=0.178 ~ G/C=0.144 ~ G/C=0.356
G= 5.0" ~ G= 4.0" ~ G= 16.0" I G= 13.0" I G= 32.0"
Y+R= 4.0" Y+R= 4.0" ( Y+R= 4.0" Y+R= 4.0" Y+R= 4.0"
OFF= 0.0% ~ OFF=10.0% ~ OFF=18.9% ~ OFF=41.1% ~ OFF=60.0%
-------------------------------------------------------------
C= 90 sec G= 70.0 sec = 77.8% Y=20.0 sec = 22.2% Ped= 0.0 sec = 0.0%
-------------------------------------------------------------------------------
Lane (Width/~ g/C I Service Rate Adj ~ ~ HCM ~ L ( Queue
Group i Lanes Reqd Used ~ @C (vph) @E ~Volume~ v/c ~ Delay ~ S Model 1~
-------------------------------------------------------------------------------
N Approach 66.9 E+
-------------------------------------------------------------------------------
-------------------------------------------------------------------------------
IRT+TH ~ 12/1 10.227 0.178 ~ 113 I 215 I 178 10.781 I 51.2 I D ~ 222 ft)
LT ~ 12/1 0.150 0.056 ~ 1 I 70 78 10.886 1102.5 *F ~ 120 ft~
-------------------------------------------------------------------------------
S Approach 54.7 D
-------------------------------------------------------------------------------
-------------------------------------------------------------------------------
IRT+TH ~ 12/1 10.323 0.267 ~ 244 ~ 356 ~ 328 0.921 ~ 60.8 I*E+~ 435 ftI
LT 12/1 10.172 0.144 ~ 65 ~ 216 ~ 133 0.578 ~ 39.5 I*D+~ 153 ft
-------------------------------------------------------------------------------
E Approach 42.9 D+
-------------------------------------------------------------------------------
-------------------------------------------------------------------------------
RT ~ 12/1 (0.150 0.356 ~ 315 ~ 405 ~ 50 0.123 19.7 B 41 ft~
TH ~ 12/1 0.359 0.356 ~ 487 ~ 596 ~ 494 0.829 36.0 D+` 544 ft
LT ~ 12/1 0.210 10.144 ~ 65 ~ 216 ~ 200 0.870 ~ 65.8 *E+~ 269 ft,
W Approach 64.0 E+
-----------------------
RT ~ 12/1 0.175 --------
0.356 ----------------------------
406 ~ 507 ~ 122 0.241 --------------------
20.7 ~ C+~ 102 ft
TH ~ 12/1 10.426 I
0.356 487 ~ 596 ~ 622 1.044 77.7 ~*E ~ 911 ft
LT ~ 12/1 0.177 0.144 ~ 65 ~ 216 ( 144 0.626 ~ 41.5 ~ D+~ 168 ft
Yelm Avenue Walgreens TIA 07/26/01
First Street/Yelm Avenue 14:43:22
PM Peak Hour; Projected 2002 volumes w/o project .
SIGNAL2000/TEAPAC[Ver 1.01.00] - Summary of Parameter Values
Intersection Parameters for Int # 1
METROAREA CBD
SIMULATION PERIOD 15
LEVELOFSERVICE C S
NODELOCATION 0 0
QUEUEMODELS 1 90 25 40
Approach Parameters
APPLABELS N E S W
GRADES 0.0 0.0 0.0 0.0
PEDLEVELS 0 0 0 0
BIKEVOLUMES 0 0 0 0
PARKINGSIDES BOTH BOTH BOTH NONE
PARKVOLUMES 10 20 0 20
BUSVOLUMES 0 0 0 0
RIGHTTURNONREDS 0 0 0 0
UPSTREAMVC 0.00 0.00 0.00 0.00
Movement Parameters
MOVLABELS RT TH LT
VOLUMES 105 55 70
WIDTHS 0.0 12.0 12.0
LANES 0 1 1
GROUPTYPES NORM NORM NORM
UTILIZATIONS 0.00 0.00 0.00
TRUCKPERCENTS 2.0 2.0 2.0
PEAKHOURFACTORS 0.90 0.90 0.90
ARRIVALTYPES 3 3 3
ACTUATIONS YES YES YES
REQCLEARANCES 4.0 4.0 4.0
MINIMUMS 5.0 5.0 5.0
STARTUPLOST 2.0 2.0 2.0
ENDGAIN 2.0 2.0 2.0
STORAGE 0 0 0
INITIALQUEUE 0 0 0
IDEALSATFLOWS 1900 1900 1900
FACTORS 1.00 1.00 1.00
DELAYFACTOR5 1.00 1.00 1.00
NSTOPFACTORS 1.00 1.00 1.00
SATURATIONFLOWS 0 1285 1593
Phasing Parameters
SEQUENCES 64 64
PERMISSIVES NO NO
OVERLAPS NO NO
CYCLES 90 90
GREENTIMES 5. 00 4.00
YELLOWTIMES 4. 00 4.00
CRITICALS 3 9
EXCESS 0
RT TH LT
45 445 180
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1140 1676 1593
RT TH LT
225 70 120
0.0 12.0 12.0
0 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
0 1336 1593
RT TH LT
110 560 130
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1425 1676 1593
NO NO LEADLAGS
NO NO OFFSET
30 PEDTIME
16.00 13.00 32.00
4.00 4.00 4.00
8 6 11
NONE NONE
0.00 1
0.0 0
Yelm Avenue Walgreens TIA 07/26/01
First Street/Yelm Avenue 14:43:40
PM Peak Hour; Projected 2002 volumes w/project
SIGNAL2000/TEAPAC[Ver 1.01.00] - Capacity Analysis Summary
Intersection Averages for Int # 1 - .
Degree of Saturation (v/c) 0.84 Vehicle Delay 57.5 Level of Service E+
Sq 64
**/**
/~~
North
-------------------------------------------------------------
Phase l ~ Phase 2 ~ Phase 3 ~ Phase 4 ~ Phase 5
i-----*-----i-----------i-+-+-------i---
* ~ I + + ~ ~ ++++
! v I ****
I
I I I I++++ v ~ ~
+ * + +
+ ~ * + +
-------------------------
G/C=0.056 ~ G/C=0.044
G= 5.0" ~ G= 4.0"
Y+R= 4.0" Y+R= 4.0"
OFF= 0.0% OFF=10.0%
C= 90 sec G= 70.0 sec
* *~
* *
* *
G/C=0.178
G= 16.0"
Y+R= 4.0"
OFF=18.9%
77.8% Y=2
****~
++++
v
-------------------------
G/C=0.144 ~ G/C=0.356
G= 13.0" ( G= 32.0°
Y+R= 4.0" ~ Y+R= 4.0"
OFF=41.1% ~ OFF=60.0%
-------------------------
0.0 sec = 22.2% Ped= 0.0 sec
0.0%
----------------
Lane Width/ ---------------
g/C ~ ---------
Service ------
Rate -----
Adj --------
~
~ -------
HCM -----
L ~
~ --------
Queue
Group ~ Lanes
---------------- l Reqd
------- Used ~
-------- @C (vph)
--------- @E ~Volume~ v/c
------------------- Delay
------- S Model
---------- l~
---
N Approach 66.9 E+
----------------
RT+TH 12/1 -------
0.227 --------
0.178 ~ ---------
113 ~ ------
215 ~ -----
178 --------
0.781 ~ -------
51.2 -----
~ D -----
222 ---
ft~
LT 112/1
---------------- 10.150
------- 0.056 ~
------- 1 ~
---------- 70 ~
------ 78
----- 0.886 ~
-------- 102.5
------- ~*F
----- 120
----- ft~
---
S Approach 57.3 E+
----------------
IRT+TH ~ 12/1 -------
10.328 -------
0.267 ----------
~ 244 ~ ------
356 ~ -----
334
0.938 ~
64.4
~*E+~
452
ft~
LT ~ 12/1
---------------- 0.172
------- 0.144
------- ( 65 ~
---------- 216 (
------ 133
----- 0.578
------- ~ 39.5
-------- ~*D+~
----- 153
----- ft~
---
E Approach 44.1 D+
----------------
RT ~ 12/1 -------
0.150 -------
0.356 --------
~ 315 -- -----
405 ~ - -----
50 -------
0.123 --------
~ 19.7 -----
~ B ~ -----
41 ---
ft~
TH 12/1 0.366 0.356 ( 487 I 596
I 506 0.849
, ~ 37.9 D+~
~ 567 ft~
LT ' 12/1
---------------- 0.210
------- 0.144
------- ( 65 ~
---------- 216
------ 200
----- 0.870
------- ~ 65.8
-------- *E+~
----- 269
----- ft~
---
W Approach 66.3 E+
----------------
RT ~ 12/1
~0 175
~0 356
~ 406 ~
507 ~ -----
122 -------
~0 241 --------
~ 20 7 -----
I C+~ -----
102 ---
ft~
TH ~ 12/1 0.429 0.356 ( 487
I 596 ~ 628 1.054 ~ 80.8 *F ~ 934 ft~
LT ~ 12/1
---------------- 0.177
------- (0.144
------- ~ 65
---------- 216 ~
------ 144
---- 0.626
-------- ( 41.5
-------- ~ D+~
----- 168
----- ft~
---
Yelm Avenue Walgreens TIA
First Street/Yelm Avenue
PM Peak Hour; Projected 2002 volumes w/project
SIGNAL2000/TEAPAC[Ver 1.01.00] - Summary of Parameter Values
Intersection Parameters for Int # 1
07/26/01
14:43:57
METROAREA CBD
SIMULATION PERIOD 15
LEVELOFSERVICE C S
NODELOCATION 0 0
QUEUEMODELS 1 90 25 40
Approach Parameters
APPLABELS N E S W
GRADES 0.0 0.0 0.0 0.0
PEDLEVELS 0 0 0 0
BIKEVOLUMES 0 0 0 0
PARKINGSIDES BOTH BOTH BOTH NONE
PARKVOLUMES 10 20 0 20
BUSVOLUMES 0 0 0 0
RIGHTTURNONREDS 0 0 0 0
UPSTREAMVC 0.00 0.00 0.00 0.00
Movement Parameters
MOVLABELS RT TH LT
VOLUMES 105 55 70
WIDTHS 0.0 12.0 12.0
LANES 0 1 1
GROUPTYPES NORM NORM NORM
UTILIZATIONS 0.00 0.00 0.00
TRUCKPERCENTS 2.0 2.0 2.0
PEAKHOURFACTORS 0.90 0.90 0.90
ARRIVALTYPES 3 3 3
ACTUATIONS YES YES YES
REQCLEARANCES 4.0 4.0 4.0
MINIMUMS 5.0 5.0 5.0
STARTUPLOST 2.0 2.0 2.0
ENDGAIN 2.0 2.0 2.0
STORAGE 0 0 0
INITIALQUEUE 0 0 0
IDEALSATFLOWS 1900 1900 1900
FACTORS 1.00 1.00 1.00
DELAYFACTORS 1.00 1.00 1.00
NSTOPFACTORS 1.00 1.00 1.00
SATURATIONFLOWS 0 1285 1593
Phasing Parameters
SEQUENCES 64 64
PERMISSIVES NO NO
OVERLAPS NO NO
CYCLES 90 90
GREENTIMES 5. 00 4.00
YELLOWTIMES 4. 00 4.00
CRITICALS 3 9
EXCESS 0
RT
45
12.0
1
NORM
0.00
2.0
0.90
3
YES
4.0
5.0
2.0
2.0
0
0
1900
1.00
1.00
1.00
1140
NO
NO
30
16.00
4.00
8
TH LT
455 180
12.0 12.0
1 1
NORM NORM
0.00 0.00
2.0 2.0
0.90 0.90
3 3
YES YES
4.0 4.0
5.0 5.0
2.0 2.0
2.0 2.0
0 0
0 0
1900 1900
1.00 1.00
1.00 1.00
1.00 1.00
1676 1593
NO
NO
13.00 32.00
4.00 4.00
6 11
RT TH LT
230 70 120
0.0 12.0 12.0
0 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
0 1335 1593
LEADLAGS
OFFSET
PEDTIME
RT TH LT
110 565 130
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1425 1676 1593
NONE NONE
0.00 1
0.0 0
Yelm Avenue Walgreens TIA
Creek Street/Yelm Avenue
PM Peak Hour; Existing 2001 traffic volumes
SIGNAL2000/TEAPAC[Ver 1.01.00] - Capacity Analysis Summary
07/26/01
14:44:21
Intersection Averages for Int # 1 - .
Degree of Saturation (v/c) 0.60 Vehicle Delay 28.1 Level of Service C
Sq 74
**/**
/I~
North
-------------------------------------------------
Phase 1 ~ Phase 2 ~ Phase 3 ~ Phase 4
-------------------------------------------------
+ + +
I v I ~ I++++ v+++ I
I I <+ + +>
~ + + +
~ ~ + + +
------------------------
G/C=0.111 ~ G/C=0.200
G= 10.0" ~ G= 18.0"
Y+R= 4.0" I Y+R= 4.0"
OFF= 0.0% ~ OFF=15.6%
------------------------
C= 90 sec G= 74.0 sec
I++++> I
~++++ ~
v
-----------------------
G/C=0.089 G/C=0.422
G= 8.0" ~ G= 38.0"
Y+R= 4.0" ~ Y+R= 4.0"
OFF=40.0% ~ OFF=53.3%
-----------------------
82.2% Y=16.0 sec = 17.8%
Ped= 0.0 sec = 0.0%
---------
Lane ----------------------
Width/~ g/C ~ ---------
Service ------------
Rate Adj
l ---------------
~ HCM ~ ------------
L Queue
,
Group
--------- ~ Lanes) Reqd Used ~
---------------------- @C (vph)
--------- @E ~Volume
------------ v/c ~ Delay ~
--------------- Model l~
S
------------
N Approach 49.2 D
-----------
RT+TH ~ -----
12/1 -------
0.171 --------
0.111 ~ -------
1
~ -------
176 ~ ------
145 --------
0.751 -------
54.0 -----
~ D ~ -----
184 ---
ft)
LT ~
----------- 12/1
----- 0.140
------- 0.111 ~
-------- 1
------- 180 ~
------- 61
------ 0.310
-------- 37.7
------- ~ D+~
----- 68
----- ft~
---
S Approach 37.6 D+
-----------
~RT+TH ~ -----
12/1 -------
0.146 --------
0.200 -------
205 ~ -------
348 ~ ------
78 --------
0.222 ~ -------
30.5 -----
~ C ~ ----
78 ----
ft~
LT ~
----------- 12/1
----- y0.223
------- 0.200 I
-------- 206 ~
------- 350 ~
------- 250
------ 0.706 ~
-------- 39.9
------- ~ D+~
----- 284
---- ft~
----
E Approach 23.7 C+
-----------
RT 1 -----
12/1 -------
0.139 --------
0.422 ~ -------
578 ~ -------
669 ~ ------
50 --------
0.075 ~ -------
15.6 -----
~ B ----
36 ----
ft~
TH ~ 12/1 0.344 0.422 I 691 786 ~ 522 0.664 ~ 23.0 ~ C+ 477 ft~
LT (
----------- 12/1
----- 0.136
------- 0.089 ~
-------- 1 '
------- 139 ~
------- 50
------ 0.318 ~
-------- 39.6
------- ~ D+
----- 57
---- ft~
----
W Approach 23.1 C+
----------------
RT ~ 12/1 ---------------
0.303 0.422 ~ ------------------------------------
578 669 361 0.540 I 20.3 ~ ------------
C+~ 313 ftl
TH ~ 12/1 0.347 0.422 ~ 691 786 528 0.672 ~ 23.2 ~ C+~ 485 ft
LT ~ 12/1
---------------- 0.138 0.089 ~
--------------- 1 ~ 139 56 0.357 ~ 40.0 ~
------------------------------------ D+~ 65 ft
------------
Yelm Avenue Walgreens TIA 07/26/01
Creek Street/Yelm Avenue 14:44:32
PM Peak Hour; Existing 2001 traffic volumes
SIGNAL2000/TEAPAC[Ver 1.01.00] - Summary of Parameter Values
Intersection Parameters for Int # 1
METROAREA NONCBD
SIMULATION PERIOD 15
LEVELOFSERVICE C S
NODELOCATION 0 0
QUEUEMODELS 1 90 25 40
Approach Parameters
APPLABELS N E S W
GRADES 0.0 0.0 0.0 0.0
PEDLEVELS 0 0 0 0
BIKEVOLUMES 0 0 0 0
PARKINGSIDES NONE NONE NONE NONE
PARKVOLUMES 20 20 20 20
BUSVOLUMES 0 0 0 0
RIGHTTURNONREDS 0 0 0 0
UPSTREAMVC 0.00 0.00 0.00 0.00
Movement Parameters
MOVLABELS RT TH LT
VOLUMES 60 70 55
WIDTHS 0.0 12.0 12.0
LANES 0 1 1
GROUPTYPES NORM NORM NORM
UTILIZATIONS 0.00 0.00 0.00
TRUCKPERCENTS 2.0 2.0 2.0
PEAKHOURFACTORS 0.90 0.90 0.90
ARRIVALTYPES 3 3 3
ACTUATIONS YES YES YES
REQCLEARANCES 4.0 4.0 4.0
MINIMUMS 5.0 5.0 5.0
STARTUPLOST 2.0 2.0 2.0
ENDGAIN 2.0 2.0 2.0
STORAGE 0 0 0
INITIALQUEUE 0 0 0
IDEALSATFLOWS 1900 1900 1900
FACTORS 1.00 1.00 1.00
DELAYFACTORS 1.00 1.00 1.00
NSTOPFACTORS 1.00 1.00 1.00
SATURATIONFLOWS 0 1734 1770
RT TH LT
45 470 45
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1583 1863 1770
RT TH LT
25 45 225
0.0 12.0 12.0
0 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
0 1762 1770
RT TH LT
325 475 50
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1583 1863 1770
Phasing Parameters
SEQUENCES 74 ALL
PERMISSIVES NO NO NO NO
OVERLAPS NO NO NO NO
CYCLES 90 90 30
GREENTIMES 10.00 18.00 8.00 38.00
YELLOWTIMES 4.00 4.00 4.00 4.00
CRITICALS 0 0 0 0
EXCESS 0
LEADLAGS
OFFSET
PEDTIME
NONE NONE
0.00 1
0.0 0
Yelm Avenue Walgreens TIA 07/26/01
Creek Street/Yelm Avenue 14:44:48
PM Peak Hour; Projected 2002 volumes w/o project
SIGNAL2000/TEAPAC[Ver 1.01.00] - Capacity Analysis Summary
Intersection Averages for Int # 1 - .
Degree of Saturation (v/c) 0.66 Vehicle Delay 30.4 Level of Service C
-------------------------
Sq 74 ~ Phase l ~ Phase 2 ~ ------------
Phase 3 ~ ------------
Phase 4
+ + +
~ + + + ~ ++++~
/i\
v ~ ++++,
++++ v
No
th <+ + +>~ I ++++>
i
i + + + I ++++
+ + + ( v
-------------
G/C=0.111 ------------
G/C=0.200 ~ ------------
G/C=0.089 ~ -----------
G/C=0.422 -
G= 10.0° I G= 18.0" ~ G= 8.0" G= 38.0"
Y+R= 4.0" ~ Y+R= 4.0" I Y+R= 4.0" ` Y+R= 4.0"
OFF= 0.0% ~ OFF=15.6% ~ OFF=40.0% ~ OFF=53.3%
-------------------------
C= 90 sec G= 74.0 sec = ------------
82.2% Y=16 ------------
.0 sec = 17.8%
Ped= 0.0
sec
= 0
.0%
-------------------------------
Lane (Width/~ g/C ~ ---------------------------
Service Rate Adj ~ ---------
I HCM ~ ----
L I -----
Queu ---
e
Group ~ Lanes Reqd Used ~
------------------------------- @C (vph) @E
------------ ~Volumel v/c
--------------- f Delay ~
--------- S Model
--------- 1~
---
N Approach 49.2 D
-------------------------------
IRT+TH 112/1 0.171 0.111 ~ ------------
1 ~ 176 ---------------
~ 145 0.751 ---------
~ 54.0 ~ ----
D -----
184 ---
ft~
LT 112/1 0.140 0.111 ~
------------------------------- 1 ~ 180
------------ ~ 61 0.310
--------------- ~ 37.7 ~
--------- 1
D+
---- 68
----- ft~
---
S Approach 44.5 D+
------------------------
~RT+TH 12/1 0.146 1 -------
0.200 ~ ------------
205 ~ 348 ---------------
~ 78 0.222 ---------
~ 30.5 ~ ----
C ~ -----
78 ---
ft~
LT ~ 12/1 10.242 10.200 ~
------------------------------- 206 ~ 350
------------ ~ 289 (0.816
--------------- ~ 48.2 ~
--------- D ~
---- 350
----- ftl
---
E Approach 25.5 C+
-------------------------------
RT 12/1 0.139 0.422 ~ ------------
578 ~ 669 ---------
~ 50 ------
0.075 ---------
~ 15.6 ~ ----
B ~ -----
36 ---
ft~
TH ` 12/1 0.367 0.422 ~ 691 ~ 786 ~ 572 1 0.728 ~ 25.1 ~ C+ 545 ft~
LT ~ 12/1 0.136 0.089 ~
------------------------------- l ~ 139
------------ ~ 50 0.318
--------------- ~ 39.6 I
--------- D+I
---- 57
----- ft~
---
W Approach 24.9 C+
-------------------------------------------------------------------------------
RT ~ 12/1 0.327 0.422 ~ 578 ~ 669 406 0.607 ~ 21.8 C+~ 365 ft~
TH ~ 12/1 0.370 0.422 ~ 691 786 578 0.735 ~ 25.4 I C+~ 554 ft
LT ~ 12/1 0.140 10.089 ~ 1 139 61 0.389 ~ 40.3 ~ D+I 71 ftl
-------------------------------------------------------------------------------
Yelm Avenue Walgreens TIA 07/26/01
Creek Street/Yelm Avenue 14:44:58
PM Peak Hour; Projected 2002 volumes w/o project
SIGNAL2000/TEAPAC[Ver 1.01.00] - Summary of Parameter Values
Intersection Parameters for Int # 1
METROAREA NONCBD
SIMULATION PERIOD 15
LEVELOFSERVICE C S
NODELOCATION 0 0
QUEUEMODELS 1 90 25 40
Approach Parameters
APPLABELS N E S W
GRADES 0.0 0.0 0.0 0.0
PEDLEVELS 0 0 0 0
BIKEVOLUMES 0 0 0 0
PARKINGSIDES NONE NONE NONE NONE
PARKVOLUMES 20 20 20 20
BUSVOLUMES 0 0 0 0
RIGHTTURNONREDS 0 0 0 0
UPSTREAMVC 0.00 0.00 0.00 0.00
Movement Parameters
MOVLABELS RT TH LT
VOLUMES 60 70 55
WIDTHS 0.0 12.0 12.0
LANES 0 1 1
GROUPTYPES NORM NORM NORM
UTILIZATIONS 0.00 0.00 0.00
TRUCKPERCENTS 2.0 2.0 2.0
PEAKHOURFACTORS 0.90 0.90 0.90
ARRIVALTYPES 3 3 3
ACTUATIONS YES YES YES
REQCLEARANCES 4.0 4.0 4.0
MINIMUMS 5.0 5.0 5.0
STARTUPLOST 2.0 2.0 2.0
ENDGAIN 2.0 2.0 2.0
STORAGE 0 0 0
INITIALQUEUE 0 0 0
IDEALSATFLOWS 1900 1900 1900
FACTORS 1.00 1.00 1.00
DELAYFACTORS 1.00 1.00 1.00
NSTOPFACTORS 1.00 1.00 1.00
SATURATIONFLOWS 0 1734 1770
Phasing Parameters
SEQUENCES 74 ALL
PERMISSIVES NO NO
OVERLAPS NO NO
CYCLES 90 90
GREENTIMES 10. 00 1 8.00
YELLOWTIMES 4. 00 4.00
CRITICALS 0 0
EXCESS 0
RT TH LT
45 515 45
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1583 1863 1770
NO NO
NO NO
30
8.00 38.00
4.00 4.00
0 0
RT TH LT
25 45 260
0.0 12.0 12.0
0 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
0 1762 1770
LEADLAGS
OFFSET
PEDTIME
RT TH LT
365 520 55
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1583 1863 1770
NONE NONE
0.00 1
0.0 0
Yelm Avenue Walgreens TIA
Creek Street/Yelm Avenue
PM Peak Hour; Projected 2002 volumes w/project
SIGNAL2000/TEAPAC[Ver 1.01.00] - Capacity Analysis Summary
07/26/01
14:45:18
Intersection Averages for Int # 1 - .
Degree of Saturation (v/c) 0.69 Vehicle Delay 33.8 Level of Service C
-------------------------------------------------
Sq 74 ~ Phase 1 ~ Phase 2 ~ Phase 3 I Phase 4
+ + +
v ~ ~ ~ ++++
++++ v
North ~ <+ + +>~ ++++>
+ + + ~ ~ v
-------------------------------------------------
G/C=0.156 I G/C=0.200 I G/C=0.089 ~ G/C=0.378
G= 14.0" G= 18.0" I G= 8.0" I G= 34.0"
Y+R= 4.0" ~ Y+R= 4.0" Y+R= 4.0" Y+R= 4.0"
OFF= 0.0% ~ OFF=20.0% OFF=44.4% ~ OFF=57.8%
-------------------------------------------------
C= 90 sec G= 74.0 sec = 82.2% Y=16.0 sec = 17.8%
Ped= 0.0 sec = 0.0%
---------
Lane -------------
(Width/) --------
g/C ----------
~ Service -----------
Rate Adj -------
~ ---------
HCM ~ ----
L --------
Queue
Group
--------- ~ Lanesl Reqd
------------- Used
-------- ~ @C (vph)
---------- @E
---- ~Volume~ v/c
-------------- ~ Delay ~
--------- S
---- Model
----- 1~
---
N Approach 37.8 D+
---------
~RT+TH --------
~ 12/1 -----
0.181 --------
0.156 ----------
~ 104 ~ ----
260 -------
I 167 -------
0.614 ---------
~ 39.6 ----
D+~ -----
191 ---
ft~
LT
--------- ~ 12/1 0.150
------------- 0.156
-------- ~ 105 ~
---------- 263
---- I 89
------- 0.324
------- I
~ 34.5
--------- C ~
---- 95
----- ft~
---
S Approach 45.4 D
---------
IRT+TH -------------
~ 12/1 0.150 --
1 ------
0.200 ----------
~ 207 ~ ----
351 -------
~ 89 -------
0.251 ---------
~ 30.7 ~ ----
C ~ -----
89 ---
ft~
LT
--------- ~ 12/1 0.245
------------- 10.200
-------- ~ 206 ~
---------- 350
---- ~ 294
------- 1
0.831
------- ~ 49.8 ~
--------- D (
---- 360
----- ft~
---
E Approach 31.5 C
-------------------------------------------------------------------------------
RT ~ 12/1 0.146 0.378 ~ 497 ~ 598 ~ 67 0.112 ~ 18.3 ~ B ~ 52 ft~
TH ( 12/1 0.367 0.378 I 596 ~ 704 ~ 572 0.813 32.4 ~ C 602 ft~
LT ~ 12/1 0.136 0.089 ~ 1 ~ 139 I 50 0.318 ' 39.6 ~ D+I 57 ft~
-------------------------------------------------------------------------------
W Approach 30.1 C
-----------------------
RT ~ 12/1 0.321 ---------------
0.378 497 ---------------------
598 ( 394 0.659 I ------------
25.9 I C+~ --------
381 ft~
TH ~ 12/1 0.365 0.378 596 704 ~ 567 0.805 I 31.9 I C ~ 594 ft~
LT ~ 12/1 (0.140
----------------------- 0.089 ~ 1 ~
--------------- 139 ~ 61 0.389 ~
--------------------- 40.3 ~ D+~
------------ 71 ft~
--------
Yelm Avenue Walgreens TIA 07/26/01
Creek Street/Yelm Avenue 14:45:27
PM Peak Hour; Projected 2002 volumes w/project
SIGNAL2000/TEAPAC[Ver 1.01.00] - Summary of Parameter Values
Intersection Parameters for Int # 1
METROAREA NONCBD
SIMULATION PERIOD 15
LEVELOFSERVICE C S
NODELOCATION 0 0
QUEUEMODELS 1 90 25 40
Approach Parameters
APPLABELS N E S W
GRADES 0.0 0.0 0.0 0.0
PEDLEVELS 0 0 0 0
BIKEVOLUMES 0 0 0 0
PARKINGSIDES NONE NONE NONE NONE
PARKVOLUMES 20 20 20 20
BUSVOLUMES 0 0 0 0
RIGHTTURNONREDS 0 0 0 0
UPSTREAMVC 0.00 0.00 0.00 0.00
Movement Parameters
MOVLABELS RT TH LT
VOLUMES 60 90 80
WIDTHS 0.0 12.0 12.0
LANES 0 1 1
GROUPTYPES NORM NORM NORM
UTILIZATIONS 0.00 0.00 0.00
TRUCKPERCENTS 2.0 2.0 2.0
PEAKHOURFACTORS 0.90 0.90 0.90
ARRIVALTYPES 3 3 3
ACTUATIONS YES YES YES
REQCLEARANCES 4.0 4.0 4.0
MINIMUMS 5.0 5.0 5.0
STARTUPLOST 2.0 2.0 2.0
ENDGAIN 2.0 2.0 2.0
STORAGE 0 0 0
INITIALQUEUE 0 0 0
IDEALSATFLOWS 1900 1900 1900
FACTORS 1.00 1.00 1.00
DELAYFACTORS 1.00 1.00 1.00
NSTOPFACTORS 1.00 1.00 1.00
SATURATIONFLOWS 0 1751 1770
Phasing Parameters
SEQUENCES 74 ALL
PERMISSIVES NO NO
OVERLAPS NO NO
CYCLES 90 90
GREENTIMES 14. 00 18.00
YELLOWTIMES 4. 00 4.00
CRITICALS 0 0
EXCESS 0
RT TH LT
60 515 45
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1583 1863 1770
NO NO
NO NO
30
8.00 34.00
4.00 4.00
0 0
RT TH LT
25 55 265
0.0 12.0 12.0
0 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4.0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
0 1775 1770
LEADLAGS
OFFSET
PEDTIME
RT TH LT
355 510 55
12.0 12.0 12.0
1 1 1
NORM NORM NORM
0.00 0.00 0.00
2.0 2.0 2.0
0.90 0.90 0.90
3 3 3
YES YES YES
4. 0 4.0 4.0
5.0 5.0 5.0
2.0 2.0 2.0
2.0 2.0 2.0
0 0 0
0 0 0
1900 1900 1900
1.00 1.00 1.00
1.00 1.00 1.00
1.00 1.00 1.00
1583 1863 1770
NONE NONE
0.00 1
0.0 0
Two-Way Stop Control
Page 1 of 2
TWO-WAY STOP CONTROL SUMMARY
General Information Site Information
nal st geo
genc /Co. Shea Grou
Date Performed 7/26/2001
nal sis Time Period m k hour
Intersection
urisdiction Yelm
nal sis Year 2002
Pro'ect ID Yelm Avenue Wal teens
East/Vllest Street: Site Drivewa North/South Street: Creek Street
Intersection Orientation: North-South Stud Period hrs : 0.25
ehicle Volumes and Ad'ustments
Major Street Northbound Southbound
Movement 1 2 3 4 5 6
L T R L T R
olume 25 145 0 0 190 10
Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00
Hourly Flow Rate, HFR 25 145 0 0 190 10
Percent Heavy Vehicles 0 -- -- 0 -- --
Median Type Undivided
RT Channelized 0 0
Lanes 1 1 0 0 1 0
Configuration L T TR
U stream Si nal 1 0
Minor Street Westbound Eastbound
Movement 7 8 9 10 11 12
L T R L T R
olume 0 0 0 10 0 40
Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00
Hourly Flow Rate, HFR 0 0 0 10 0 40
Percent Heavy Vehicles 0 0 0 0 0 0
Percent Grade (%) 0 0
Flared Approach N N
Storage 0 0
RT Channelized 0 0
Lanes 0 0 0 1 0 1
Configuration L R
Dela ,Queue Length, and Level o f Service
pproach NB SB Westbound Eastbound
Movement 1 4 7 8 9 10 11 12
Lane Configuration L L R
(vph) 25 10 40
C (m) (vph) 1384 607 851
lc 0.02 0.02 0.05
5% queue length 0.06 0.05 0.15
Control Delay 7.6 11.0 9.4
LOS A 8 A
pproach Delay -- -- g.g
pproach LOS -- -- A
file://C:\Documents and Settings\smithgeo\Local Settings\Temp\u2k5A.tmp 7/26/2001
Two-Way Stop Control
Page 1 of 2
TWO-WAY STOP CONTROL SUMMARY
General Information Site Information
nal st geo Intersection
enc /Co. Shea Grou urisdiction
Date Performed 7/26/2001 nal sis Year 2002
nal sis Time Period m k hour Pro'ect ID Yelm Avenue Wal reens
East/West Street: Yelm Avenue North/South Street: Site Drivewa
Intersection Orientation: East-West Stud Period hrs : 0.25
ehicle Volumes and Ad'ustments
Ma'or Street Eastbound Westbound
Movement 1 2 3 4 5 6
L T R L T R
olume 30 920 0 0 820 10
Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00
Hourly Flow Rate, HFR 30 920 0 0 820 10
Percent Heavy Vehicles 0 -- -- 0 -- --
Median Type Undivided
RT Channelized 0 0
Lanes 1 1 0 0 2 0
Configuration L T T TR
U stream Si nal 0 1
Minor Street Northbound Southbound
Movement 7 8 9 10 11 12
L T R L T R
olume 0 0 0 5 0 30
Peak-Hour Factor, PHF 1.00 1.00 1.00 1.00 1.00 1.00
Hourly Flow Rate, HFR 0 0 0 5 0 30
Percent Heavy Vehicles 0 0 0 0 0 0
Percent Grade (%) 0 0
Flared Approach N N
Storage 0 0
RT Channelized 0 0
Lanes 0 0 0 1 0 1
Configuration L R
Dela ,Queue Len th, and Level o f Service
pproach EB WB Northbound Southbound
Movement 1 4 7 8 9 10 11 12
Lane Configuration L L R
(vph) 30 5 30
C (m) (vph) 807 71 625
lc 0.04 0.07 0.05
95% queue length 0.12 0.22 0.15
Control Delay 9.6 59.5 11.1
LOS A F B
pproach Delay -- -- 18.0
pproach LOS -- -- C