361 Six-Year Street Plan 98-03
CITY OF YELM
RESOLUTION N0. 361
SIX-YEAR STREET PLAN 1998-2003
WHEREAS, pursuant to the requirements of RCW 35.77.010, the
City of Yelm has adopted a Comprehensive Six-Year Transportation
Program for the City; and
WHEREAS, by Resolution duly adopted by the City Council of
the City of Yelm, the said comprehensive Six-Year Transportation
Program has been revised and extended from time to time; and
WHEREAS, the City Council has determined that the Yelm
Comprehensive Six-Year Transportation Program as presently revised
and extended, should be further amended as provided in the
document annexed hereto in order to accommodate recent changes in
circumstances which were not anticipated when the Program was
last revised and extended.
NOW, THEREFORE, IT IS HEREBY RESOLVED by the City Council of
the City of Yelm that the Comprehensive Six-Year Transportation
Program for the ensuing six years be, and the same is hereby
amended as provided in the document annexed hereto which is by
this reference thereto incorporated herein as though fully set
forth herein; and
RESOLVED that a copy of this Resolution be filed by the City
Clerk with the Director of Transportation of the State of.
Washington.
ADOPTED this 11th day of June 1997.
y
Kathryn Wolf, Mayo
ATTEST:
9
Ag s P. Bennick, City Clerk
PASSED and APPROVED: June 11, 1997
ab\mso\resol\6yr98-03.doc
Ylmtip97
MPO :None
City :Yelm 1495
County :Thurston 34
Funo Project Imp Total Util
Six Year Transportation Program
(1998-2003)
sns/s7
1
Hearing Date 6Il 1197
Adoption Date 6/11/97
Resolution Number 361
CI Pri Identi6catIon Type Statue Length Codex Expenditure Schedule Fed Proj. Only
Phase Federal RAP, Eto. Local/ ~ (Local Agency Use) Env. RNV Req.
Start Date Fund Code Coet Code Cost State Total let 2nd 3rd 4th-6th Type Y/N; Date
Agency YELM 3 F 0.230 GCPTW PE 30
16 1 Edwards Street Improvements RW 26
Edwards Street CN 280
Yehn Avenue W to Coates Street NW Total 336
Widen roadway and improve to urban standards
CN 01/1998 SCA 275 60 336
TOTAL 275 60 335
Agency YELM 1 S 3.000 GCPTW PE 150 600
14 2 SR 610 to SR 607 North Loop Study (Y-3) RW
New Alignment CN
SR 610 to SR b07 Total 160 600
EIS, corridor analysis, pre-design engineering
PE 01/1998 Other 662 98 660
TOTAL 662 98 650
Agency YELM 3 S 0.210 GCPTW PE 26
16 3 Stevens Avenue Improvements RW 76
Stevens Avenue CN 110 100
First Street to West Road Total 210 100
Widen roadway and improve to minor urban arterial
• CN 0111998 - SCA 243 67 310
TOTAL 243 67 310
Agency YELM 3 S 0.190 GCPTW PE 26
17 4 Mosman Street Realignment ` RW 10
Mosman Street SE CN 110 106
SR 607 to Third Street Total 146 106
Realign rdwy, repair shldrs, pave, drainage, partial walks, and lighting
CN 01/1998 SCA 200 60 250 '
TOTAL 200 60 260
Agency YELM 1 F 1.600 O PE 210
14 6 SR 607/Flve Corners Connector (Y-2) - RW EIS NO
New Alignment CN
SR 607 to Five Corners intersection Total 210
EIS, corridor analysis, pre-design engineering
PE 01/1998 STP(1J) 186 26 210
TOTAL 185 26 210
Ylmtip97 Six Year Transportation Program 6/19/97
(1998-2003) 2
MPO :None
City :Yebn 1496
County :Thurston 34
Hearing Date 6/11/97
Adoption Date 6/11/97
Resolution Number 361
Funa Project Imp Total Util
Cl Pri Identification Type 'Statue Length Codea Eapenditure Soheduie Fed Proj. Only
Phase Federal RAP, Eto. Local/ (Local Agency Uae) Env. R/W Req.
Start Date ,Fund Code Cost Code Cost State Total let 2nd Srd 4th~th Type Y/N; Date
Agency YELM 3 S 0.740 GCPTW PE 60
14 6 Yelm Avenue Improvements RW 76
Yehn Avenue CN 100 316
4th Street to Five Corners Total 236 316
Widen to 3141anes, urban arterial standards
CN 01/1999 SCA 476 76 650
TOTAL 476 76 650
Agency YELM 3 S 0.360 GCPTW PE 70
17 7 West Road Improvements RW 80
West Road CN 260 160
4th Street to 103rd Avenue Total 400 160
Widen to minor arterial standards
CN 01/2000 SCA 440 110 650
TOTAL 440 110 650
Agency YELM 3 S 0.660 TW PE 30
17 8 Railroad Street Improvements RW 10
Railroad Street NW (NP Road) CN 290
Railway to northeastern City Limits Total 330
Widen roadway, railroad crossing, new intersection alignment and lighting
CN 01/2000 SCA 297 33 330 "
TOTAL 297 33 330
Agency YELM 3 S 1.000 GCPTW PE 80
17 9 Yehn Avenue West Improvements RW 60
Yehn Avenue West CN 690
Yehn H.S. to First Street Total 130 690
Widen roadway to urban arterial standards ("core" rdwy only)
'
CN 01/2000 Other 610 210 720
TOTAL 610 210 720
Agency YELM 3 S 0.230 GCPTW PE 36
17 10 Mosman Street Improvements RW 16
Mosman Street CN 100 200
SR 607 to Solberg Street Total 160 200
Widen Roadway to neighborhood collector standards
CN 01/2000 SCA 280 70 350
TOTAL . 280 70 350
Yhntip97
MPO :None
City :Yelm 1496
County :Thurston 34
Six Year Transportation Program
(1998-2003)
6/19/97
3
Hearing Date 6/11/97
Adoption Dats 6111197
Resolution Number 361
Func Project Imp Total Util
Cl Pri Identification Type Status Length Codes Eapenditure Sohedule Fed Proj. Only
Phase Federal RAP, Eto. Local/ (Local Agency Use) Env. RIW Req.
Start Date Fund Code Cost Code Cost State Total 1st 2nd 8rd 4th-6th Type Y/N; Date
Agency YELM 3 S 0.170 GCPTW PE 26
17 11 Solberg Street Improvements RW 10
Solberg Street CN 100 140
Mosman Street to Yehn Avenue West Total 136 140
Widen Roadway to neighborhood collector standards
CN 01/2000 SCA 245 30 276
TOTAL 245 30 276
Agency YELM 3 S 0.180 GCPTW PE 20
17 12 Second, Street Improvements RW 10
Second Street SE CN 160
SR 607 to Mosman Street Tots/ 180
Repair shoulders, pave, drainage, walks and lighting
CN 01/2000 SCA 160 20 180
TOTAL 160 20 180
Agency YELM 1 S 0.140 O PE ~ 26
16 13 Stevens Avenue RW 106
New Alignment CN 80 80
Edwards Street to First Street Total 210 80
Construct new minor urban arterial segment
_ CN O1I2000 SCA 276 16 290
TOTAL 275 15 290
Agency YELM 3 S 0.740 GCPTW PE ~ 35
17 14 ~ Rhoton Road Improvements RW 16
Rhoton Road NW CN 340
Railroad Avenue to north City Limita Total 60 340
Widen roadway, drainage, lighting and resurfacing
CN 01/2000 SCA 361 39 390
TOTAL 351 39 390
Agency YELM 12 3 0.000 GCPTW PE 20
1? 16 Yelm Avenue W/Killion Road Intersection RW
Intersection realignment CN 130
Widen roadway, safety improvements Total 160
CN 0112001 Other 136 16 160
TOTAL 136 16 160
Ylmtip97
MPO :None
City :Yehn 1495
County :Thurston 34
Six Year Transportation Program
(1998-2003)
s/ls/s7
4
Hearing Date 6111/97
Adoption Date 6/11/97
Resolution Number 361
Funo Project Imp Total Utll
Cl Pri Identification Type Status Length Codes Expenditure Schedule Fed Proj: Only
Phase Federal RAP, Eto. Local/ (Local Agency Uae) Env. R/W Req.
Start Date Fund Code Cost Code Cost State Total 1st 2nd 8rd 4th-6th Type Y/N; Date
Agency YELM 12 S 0.000 GCPTW PE 20
17 16 Yelm Avenue W/93rd Avenue Intersection RW 10
Intersection Realignment CN 160
Widen roadways, safety improvements Total 180
CN 01/2001 Other 106 75 180
TOTAL 105 76 180
Agency YELM 3 S 0.110 GCPTW PE 20
17 17 Railroad Street SW RW 10
Railroad Street SW CN 130
Mosman Road to Washington Avenue Total 160
Realign, pave, drainage, sidewalks and lighting
CN 01/2001 SCA 144 16 160
TOTAL 144 16 160
Agency YELM 7 F 0.000 O PE
0 18 City-wide Roadway Re-surfacing RW
M~,y CN 10 10 lb 46
NIA Total 10 10 16 4b
Resurface with chip seal
CN 01/1998 80 80
TOTAL 80 80 -
Totals by Year: 1060 960. 1916 2036